49.6 As clearly the amount of LAD suffered by the Respondent is well over the amount of the Performance Bond, and although in the face of my finding at paragraph 66.11 hereof that the termination was not properly effected and not valid and because of which the Respondent is not entitled to claim Damages, the utilization of the Performance Bond which is not tied to termination, was not wrongful.”. [46] The learned judge held that since the arbitrator had considered clause 37 and clause 40 on the LAD; since the arbitrator had found that the utilization of the performance bond is not tied to the determination of the plaintiff’s employment; and since the amount due for the LAD is significantly more than the amount of the performance bond, the arbitrator was right to rule that the defendant’s right to the proceeds of the performance bond is not related to the termination but to the losses suffered by the defendant and/or the amounts due to the defendant arising from the breach or breaches of the contract by the plaintiff. And since the arbitrator had given his reasons as to why the utilization of the performance bond is not wrongful, the learned judge declined to disturb the arbitrator’s findings. [47] Her Ladyship further held that there was no error of law in the interpretation and findings of the arbitrator on the performance bond, because the plaintiff had earlier on claimed/applied for an injunction to restrain the defendant from calling on the performance bond and the plaintiff’s claim had been dismissed by the court. Civil Appeal No. W-01(C)(A)-301-08/2017 17 [48] On Question 2, the learned judge agreed with the defendant that the reference to LAD by the arbitrator in determining the utilization of the performance bond does not mean that the arbitrator had imposed LAD on the plaintiff, but that the arbitrator had merely provided a comparison to show that if the defendant did claim for LAD, the amount due to the defendant will be more than the amount of the performance bond. The learned judge therefore found that Question 2 did not arise from the award. [49] With respect, we disagreed with the learned judge. The arbitrator did not state that he was making such comparison and from our reading of the award, in particular paragraphs 49.2, 49.3 and 49.6 quoted above, the arbitrator had in fact expressly found, pursuant to clause 40 of the COC, using the provisions of the LAD, that there was amount due to the defendant, which amount was more than the amount of the performance bond. [50] Whether or not the arbitrator had merely referred to the LAD (which was not pleaded and counterclaimed) as comparison for the losses that the defendant may recover from the plaintiff which losses were found to be significantly more than the amount of the performance bond, the pertinent question to ask is whether the arbitrator erred in law in his conclusion on the defendant’s entitlement to the performance bond, that the defendant’s utilization of the performance bond ‘was not unlawful’. [51] In our view, as a matter of law, the arbitrator was not entitled to reach the conclusions that he did. The lawfulness of the utilization of the performance bond depends on the terms of the COC, how the parties have raised the issue and what the responses were. It was not open to the Civil Appeal No. W-01(C)(A)-301-08/2017 18 arbitrator to dwell into areas or consider any other provisions of the COC which were not relied on, pleaded or counterclaimed. [52] In relation to the performance bond, the plaintiff’s claim as pleaded in paragraph 46 of the Points of Claim was that the defendant’s termination was wrongful and that the defendant had proceeded to make a demand on the performance bond based on such wrongful termination. In response, the defendant, in paragraph 34 of the Points of Defence claimed that the contract had been determined on 11.5.2010 due to the plaintiff’s complete suspension of works, that it had inter alia exercised its rights and obligations under the contract, and that it “continued to make demand on the performance bond under the provisions of the COC as the Claimant had failed to perform its obligation under the Contract”. [53] In its submissions, the defendant took the position that under clause 50 of the COC, it was entitled to forfeit the performance bond and use the monies to set-off for additional costs incurred in appointing a third party to complete the contract. The defendant further submitted that because the performance bond was an unconditional bond, it was entitled to call upon the bond wherever it decides. Since the plaintiff was in breach, the determination was valid; and this in turn meant that the call and utilization of the performance bond was within its contractual rights. [54] The learned arbitrator had found that the determination was invalid; that “a condition precedent to claiming the amounts incurred in utilizing a Completion Contractor to complete the uncompleted works, has not been met” (see paragraph 75.2 of the Award). Given such a finding which remains unchallenged, the defendant would not in law, be entitled to claim for its Civil Appeal No. W-01(C)(A)-301-08/2017 19 losses, including costs incurred in mitigating its losses. The arbitrator has as much admitted this to be the case (see paragraphs 76.1 to 76.3 of the Award). [55] In attempting to do justice and adjudging that the losses should lie where they fell, the arbitrator however, failed to have regard to the fact that the defendant had called and utilized the performance bond for its “additional costs” in completion. Such costs are actually the losses that are supposed to lie where they fell. In other words, the defendant was to bear those costs itself. While the defendant’s right to cash in on the performance bond was said to be related to the losses apparently suffered by the defendant, and not related to the termination, the encashment of the performance bond on 4.12.2012, after the termination on 11.5.2010 together with the pleas and submissions taken by the defendant indicate quite categorically, that the performance bound was utilized to cover the defendant’s losses. Under such circumstances, the law does not countenance a result and conclusion that was reached by the arbitrator. [56] We also agreed with the plaintiff that there was no legal basis for the arbitrator to consider and justify the utilization of the performance bond by reference to the imposition of LAD. There was no plea or counterclaim to this effect; and in any event, the conditions for such an imposition were not met. No CNC was issued and more importantly, the date of completion (11.3.2011) has yet to lapse when the contract was determined on 11.5.2010. Civil Appeal No. W-01(C)(A)-301-08/2017 20 [57] Questions 1 and 2 were thus questions of law arising out of the award i.e. whether, in dismissing the defendant’s counterclaim, the arbitrator erred in law in holding that the defendant could retain and recover the amount of the performance bond for losses suffered by the defendant using the agreed provisions of the LAD, which was not pleaded. The conclusion of the learned arbitrator on the utilization of the performance bond falls under paragraph