Content
1 IN THE FEDERAL COURT OF MALAYSIA ( APPELLATE JURISDICTION ) CIVIL APPEAL NO: 02-66-10/2015(K) BETWEEN USIMA SDN BHD (No. Syarikat : 206761-H) … APPELLANT AND LEE HOR FONG (berniaga di bawah nama dan gaya PEMBINAAN LH FONG) … RESPONDENT [ In the Court of Appeal Malaysia ] (Appellate Jurisdiction) Civil Appeal No. K-02-2633-10/2011 ] Between Lee Hor Fong (berniaga di bawah nama dan gaya PEMBINAAN LH FONG) … Appellant And Usima Sdn Bhd (No. Syarikat : 206761-H) … Respondent CORAM Zulkefli Ahmad Makinudin, PCA Suriyadi Halim Omar, FCJ Hasan Lah, FCJ Ramly Ali, FCJ Balia Yusof Wahi, FCJ 2 JUDGMENT OF THE COURT Background Facts [1] The Appellant, Usima Sdn. Bhd. (hereinafter referred to as Usima) was appointed as the main contractor by Jabatan Kerja Raya (“JKR”) to construct a water tank and carry out pipe laying works (the main contract). The Respondent, Lee Hor Fong (hereinafter referred to as LHF) was the subcontractor appointed by Usima to carry out the works. [2] By a Letter of Award dated 5.11.2002 , Usima appointed LHF as its subcontractor to carry out and complete the contract works for a total sum of RM9,510,863.51 commencing on 30.9.2001. The completion date for the contract was 7.3.2003. In the said letter of award, it was stated that the terms and conditions of the main contract will be deemed to form and be construed as part of the subcontract. [3] Dispute arose between the parties and by a letter dated 13.1.2003 Usima terminated the subcontract alleging that LHF had breached the terms of the contract by abandoning the contract works. [4] LHF commenced action against Usima in the High Court claiming for a sum of RM3,159,540.15. This claim was premised on Usima’s 3 refusal to pay for work done as represented by interim certificates number 15, 16 and 17 and a further sum of RM143,472.62 from the retention sum. [5] Usima filed a counter-claim for a total sum of RM2,034,908.27, being the costs incurred as management fees, and the cost to engage new subcontractors to complete the project and carry out rectification works, agreed liquidated damages and interest on advance payment. [6] On 9.10.2011, the High Court dismissed LHF’s claims on the grounds that LHF had failed to complete the contract works within the stipulated time and had abandoned the construction site. The learned High Court judge also allowed the counter-claim by Usima. Decision of the High Court [7] In dismissing LHF’s claims, the learned High Court judge considered that the pertinent question before the court was, when was the contract between the parties terminated. Was it on 13.1.2003 or on 20.2.2003. 4 [8] The significance of these two dates may be gleaned from the judgment of the learned High Court judge found at page 16 of his judgment: “….although the letter of termination was dated on the 13th January 2003 and received by the Plaintiff on the 20th February 2003, there were ample evidence to show that the Plaintiff had abandoned the construction site as early as mid-December 2002. This is evident by the appointment of the third parties to complete the uncompleted contract works.” [9] The learned High Court judge found that LHF had abandoned the contract. At page 17 of the judgment, His Lordship opined: “…The Court was of the further view that if Clause 51(c)(i) and (ii) is relevant to be the guideline as to how the contract work should be terminated, from the evidence adduced, the Defendant had complied with it by sending out notices in the form of memo before terminating the contract (Agreement). In the circumstances, the Court was of the view that the Defendant was not in breach of the contract when it terminated it and therefore was entitled to appoint other contractors to finish the uncompleted contract works. The Court was also of the view that since the Defendant was at all material time the main contractor of the contract work and it suffices that the issuance of the memo to the Plaintiff were indicative that the Plaintiff had abandoned the construction site.” [10] Being over cautious perhaps, the learned High Court judge also stated that if he was wrong in finding that Usima was not in breach of the 5 contract, the amount claimed by LHF based on the interim certificates would be subjected to re-measurement. [11] Aggrieved by the decision of the High Court, LHF lodged an appeal to the Court of Appeal. By its decision on 2.12.2013, the Court of Appeal unanimously allowed the appeal and the decision of the High Court was set aside. The Court of Appeal also dismissed Usima’s counter-claim. Decision of the Court of Appeal [12] In allowing LHF’s appeal, it was the unanimous view of the court that the learned High Court judge had erred in finding that LHF had abandoned the construction site. At page 5 of its judgment, the Court of Appeal found: “…. abandonment never featured in the respondent's notices to the appellant which referred to delays by the appellant, not least the letter of termination dated 13.01.2003 which was totally devoid of any reference to abandonment. It is elementary that delay cannot be said to constitute abandonment especially where, as here, the completion date was months away and until then the appellant was entitled to programme its works as it pleased. Time was not of the essence because it was not specified to be so in the contract which also provided for liquidated agreed damages as indicated by the respondent's counterclaim therefor.” 6 [13] The Court of Appeal also held that clause 51 of the main contract was not complied with by Usima because the letter of award (P11) appointing LHF to execute and complete the contract expressly provided for the main contract to be part of the contract between them. The Court of Appeal found that the learned High Court judge had failed to consider whether the notices and the letter of termination dated 13.1.2003 complied with clause 51 of the main contract. In the said letter of termination dated 13.1.2003, LHF was only given 7 days to make good the breach whereas clause 51(a) gives a period of 14 days. [14] On the issue of re-measurement of the interim certificates, the decision of the learned trial judge was held to be erroneous on the ground that the interim certificates upon which LHF’s claim were based, had already been measured and certified by the employer's consultant. The evidence relied on by the learned High Court judge referred to joint measurement before the issue of the interim certificates. [15] On Usima’s counter-claim, the Court of Appeal found that the trial judge had erred in allowing the same without reference to and in the absence of any evidence to support such claims. 7 [16] Usima sought for leave to appeal against the decision of the Court of Appeal and this Court had, on 10.9.2015 granted leave to Usima to appeal on the following questions of law: i. Whether the termination clause (Clause 51) found in the main contract [JKR 203A (Revised 10/83)] which is to be operated by the SO, can apply to the subcontract? ii. Can interim certificates under a provisional subcontract based on bills of quantities issued by Superintending Officer (“SO”) to the Applicant (Main Contractor) be considered as final amount of the value of work done to entitle the Court of Appeal to enter judgment based on the value of these certificates? iii. Whether in a provisional contract based on bills of quantities, interim certificates which are subject to re-measurement and not issued to the Respondent (Subcontractor) can be relied on by the Respondent as evidence of the value of work which they had carried out? iv. Whether as a matter of law a party to a construction contract is entitled to programme its work as it pleases? v. Can direct payments paid by the Applicant (Main Contractor) directly to the sub-subcontractors be disregarded in the claim 8 made by the subcontractor (Respondent) against the Applicant (Main Contractor)? [17] At the hearing of the appeal, learned counsel for Usima had abandoned questions number (i) and (iv) and proceeded to deal with questions number (ii) and (iii) together and with question number (v) to be dealt separately on its own. Our decision : Questions (ii) and (iii) [18] Questions (ii) and (iii) both deal with interim certificates and what merits determination by this court is whether such certificates may be considered as a final amount of the value of work done and the issue of re-measurement. [19] We will start with the subject of interim certificates. [20] By its very nature, an interim certificate can never be considered as a final determination of the value of works done or programmed in the contract. We reproduce below what the learned author Chow Kok Fong states in his book titled Law and Practice of Construction Contracts 4th Edition Volume 1 at pages 441 and 442: 9 “8.12 Interim certificates are certifications of payments made in accordance with some timeline stipulated in a construction contract. In essence, a certificate is a statement by the certifier (typically the architect, engineer, contract administrator or Superintending Officer) that during the period covered by the certificate, the contractor has carried out the works and supplied materials up to the value shown in the certificate as well as the net amount which the contractor is entitled to be paid, after allowing for the adjustments permitted by the terms of the contract. These certifications are never intended to be a precise or final determination of the value of the works. Thus, Hobhouse J in Secretary of State for Transport v Brise-Farr Joint Venture (1993) noted: At the interim stage, it cannot always be a wholly exact exercise. It must include an element of assessment and judgment. Its purpose is not to produce a final determination of the remuneration to which the contractor is entitled but is to provide a fair system of monthly progress payments to be made to the contractor.