(g), and (h) of the Statement of Claim by awarding global general damages amounting to RM2.4 million. This sum was calculated based on payments allegedly received by the Appellant through its collaborations with third parties, namely Oakdale Aquatech Sdn. Bhd. and Dongjia Inc. [68] However, in assessing damages, a party is required to elect between reliance loss (i.e. loss of profits) and expectation loss (i.e. wasted expenditure or costs incurred in preparing to perform the contract), as established by the Court of Appeal in Ban Chuan Trading Co Sdn. Bhd. v Ng Bak Guan [2004] 1 MLJ 411 and Peninsular Home Sdn. Bhd. v Ko Lim Tristar Sdn. Bhd. [2024] 2 MLJ 623. [69] Under clause 10 of the Collaboration Agreement. Under this clause, the Respondent's maximum entitlement is limited to 3% of the Appellant's annual gross income. Accordingly, general damages cannot include sums allegedly earned by the Appellant through thirdparty collaborations (such as with Oakdale Aquatech Sdn. Bhd. and Dongjia Inc.). Additionally, the Respondent did not plead any claim for secret profits or unjust enrichment. [70] The learned High Court Judge had at paragraph 84 (e) the Grounds of Judgment, allowed the Respondent's claim for general damages. The High Court had awarded the sum of RM2,400,000.00 to the Respondent. [71] At paragraph 75 (c) of the Grounds of Judgment, the High Court had stated the Appellant had breached and repudiated Clause 10 of the Collaboration Agreement by failing to pay 3% of its annual gross revenue to the Appellant each year. Based on the Appellant's evidence, which was not challenged or rebutted by the Respondent, the Respondent was required to make the said 3% payment annually within 30 days from the date its financial statements were approved. However, the Respondent made the said 3% payment only twice to the Appellant over the nine (9) years during which the Collaboration Agreement was in force, namely a sum of RM33,549.51 on 31 December 2013 and a sum of RM28,634.13 on 1 December 2014. [72] Based on the findings in paragraph 75 (c) of the Grounds of Judgment, the High Court found that the Respondent had breached the terms of the Collaboration Agreement, which allowed the Appellant to terminate the Collaboration Agreement. [73] We find several difficulties with this award. First, the Respondent did not plead a claim for an account of profits or unjust enrichment. Second, clause 10 of the Collaboration Agreement limits the Respondent's contractual entitlement to 3% of the Appellant's gross income from marine produce - not third-party collaboration payments. Third, the Respondent did not prove any actual loss directly caused by the alleged misrepresentation with the requisite particularity. [74] However, the High Court found that the Appellant had committed fraudulent misrepresentation. Under section 19 of the Contracts Act 1950, the Respondent could have rescinded the contract and claimed restitution, or affirmed the contract and claimed damages for deceit. The Respondent did neither; instead, it claimed general damages on an unparticularised basis. [75] In the absence of a proper legal basis and proper proof, the award of RM2.4 million in general damages cannot stand. We therefore set aside the award of RM2.4 million for general damages. This ground of appeal is also allowed in part. [76] It is prudent to establish here, that the setting aside of the damages awards does not affect the core findings that the Collaboration Agreement expired on 4 May 2017 and that the Respondent is entitled to vacant possession. The damages were ancillary and were not strictly proved. Issue 4: Whether the learned High Court Judge erred in dismissing the Appellant's Counterclaim. [77] Whether the dismissal was a direct consequence of the errors in the findings on the primary claims. [78] Whether the Appellant had established a prima facie right to remain in possession based on the correct interpretation of the contract's duration and the Respondent's failure to issue proper termination notices. [79] It is the Appellant's contention that the High Court's dismissal was based on the erroneous finding that the Collaboration Agreement and Tenancy Agreement were induced by fraud and misrepresentation and had consequently expired in 2017. Counsel for the Appellant submitted that the learned High Court Judge failed to accord adequate weight to the Appellant's counterclaim, which was grounded on its right to remain in possession pursuant to the 30-year contractual tenure and the automatic extension mechanism under Clause 4 of the Collaboration Agreement. [80] Having held that the Collaboration Agreement expired on 4 May 2017 and was not extended by mutual written agreement, the Appellant's counterclaim has no foundation. The Appellant has no right to remain in possession under the expired agreements. The High Court correctly dismissed the counterclaim. [81] The Appellant's alternative claim for damages (if the agreement was terminated) does not arise because the Collaboration Agreement had expired, not terminated. [82] The order for vacant possession is affirmed. The Appellant has been holding over without any lawful basis since 4 May 2017. The Respondent is the registered proprietor of the land and is entitled to vacant possession. E. CONCLUSION [83] For all the foregoing reasons, we make the following orders: