Schedule
Schedule III of the KLRCA Adjudication Rules & Procedure (Revised as at 14.5.2014) on the “Administrative Fee Schedule” and in particular, para 1.1(c) which provides that the administrative fee is calculated at 20% of the adjudicator’s fee and this fee is in addition to the adjudicator’s fee and expenses payable by the parties. [67] Ms. WY Lim submitted for Wabina that the Adjudicator failed to consider all defences which were raised in the Adjudication Response including on the issue of costs and this renders the AD susceptible to being set aside for breach of natural justice. [68] Wabina’s position on costs is set out in paras 91 to 93 of the Adjudication Response as follows: “91. In the event that this Tribunal decides the dispute in favour of the Respondent, the Respondent should not be made liable for the costs of this adjudication and/or legal costs of this adjudication. Instead, the costs of this adjudication should be paid by the Claimant together with the legal costs and disbursements incurred by the Respondent. 92. Regulation 7 of the Construction Industry Payment and Adjudication Regulations 2014 sets out the matters to be taken into account in arriving at a decision on costs, including the complexity of the claim, the specialised skill, responsibility and time expended by parties, the preparation of documents and the value involved. 93. Alternatively, the Claimant ought to bear the costs of this Adjudication Proceedings for the portion of the additional amount claimed in the Payment Claim and the Notice of Adjudication as the Claimant had and clearly would have the knowledge of the SFA as early as in April 2021, prior to the issuance of the Payment Claim and Notice of Adjudication, which it now relies on.”. [69] A perusal of the AD shows that the Adjudicator dealt with the issue of costs in paras 171 to 174 of the AD. Basically, the Adjudicator’s determination that Wabina should bear the following costs (in RM) was based on sub-s 18(1) CIPAA: Adjudicator’s fees and AIAC administration fees 45,625.54 33. Adjudicator’s expenses (based on actual receipt) 00 AIAC registration fee 265.00 AIAC appointment of adjudicator fee 424.00 Preparation cost of adjudication proceeding 97,000.00 Other incidental cost 2,000.00 Total costs 145,347.54 [70] In its Additional Written Submissions dated 22.8.2022 (encl. 28), Fulloop cited the case authorities of BM City Realty & Construction Sdn Bhd v. Merger Insight (M) Sdn Bhd & Another Case [2016] 1 LNS 1096, TRT Engineering (M) Sdn Bhd v Hansol KNM Greentech Sdn Bhd and another case [2020] 1 LNS 88, Cempaka Majumas Sdn Bhd v. Ecoprasinos Engineering Sdn Bhd [2019] 1 LNS 2390 and Milsonland Development Sdn Bhd v Macro Resources Sdn Bhd [2018] 1 LNS 2078 to support its contention that the issue of cost awarded by the Adjudicator is not amenable to review by this Court in an application made under s 15 CIPAA. [71] Applying the ratio decidendi in these cases to the issue of quantum of costs in the instant case, it can be concluded that – (a) both Wabina and Fulloop were given the opportunity and had addressed the Adjudicator on the issue of costs vide the adjudication documents; (b) costs to follow the event means that Wabina as the unsuccessful party has to pay the costs to Fulloop as the successful party in the adjudication proceedings; (c) the Adjudicator has wide discretion to decide on the quantum of costs by taking into account all relevant circumstances including those as provided in regulation 7 of the CIPAA Regulations; (d) quantum of costs is not an area where this Court may interfere by way of reviewing or setting aside the same in the Setting Aside Application. In TRT Engineering (supra), the High Court held, among others, that: “[18] … (2) once an adjudicator has awarded Costs to a successful party in the adjudication in accordance with the "Costs To Follow The Event" Rule, the adjudicator has a wide discretion under s. 18(1) CIPAA to award the amount of Costs. Such a wide discretion is not fettered by s. 19 CIPAA and reg. 8 CIPAR. If Parliament had intended for an adjudicator's wide discretion to award the quantum of Costs under s. 18(1) CIPAA to be subject to s. 19 CIPAA and reg. 8 CIPAR, Parliament would have expressly provided as such in s. 18(1) CIPAA. The legislature did not however provide any restriction on an adjudicator's wide discretion to award the amount of Costs pursuant to s. 18(1) CIPAA; and (3) by virtue of s. 18(2) CIPAA, the legislature has intended for - (a) the "Costs To Follow The Event" Rule; and (b) an adjudicator's wide discretion to fix the amount of Costs - to override any agreement between the parties regarding Costs. Subsection 18(2) CIPAA therefore fortifies the construction of ss. 18(1), 19 CIPAA and reg. 8 CIPAR as stated in the above sub-paragraph (2). … [20] There is another reason why Hansol cannot rely on the Fees, Expenses and Taxes awarded by the Adjudicator in the AD to support Hansol’s OS. As explained in NAZA Engineering & Construction, at [14], in a Setting Aside Application, the court cannot review the Fees, Expenses and Taxes awarded by an adjudicator. In any event, the Fees, Expenses and Taxes granted by the Adjudicator in this case do not fall under s. 15(b), (a) and (d) CIPAA …”. In Multazam Development Sdn Bhd v Felda Global Ventures Plantations (M) Sdn Bhd [2020] MLJU 606, the High Court found that: “[39] … there is no provision in the CIPAA which permits an appeal or even the setting aside of a cost order made by the adjudicator. There are limited grounds of court intervention as provided in ss. 15 and 16 of the CIPAA relating to challenges by the losing party and in s. 28 and accordingly s. 30 in relation to enforcement by the winning party in the adjudication proceedings. Consequently, the extent of permissible court intervention must, in my view, be subject to the expressio unius est exclusio alterius principle.”. (see too, paras 54 to 66 in the decision of this Court in Samado Sdn Bhd v Kerajaan Malaysia [2020] MLJU 274); and (e) Wabina has not established that there is a denial of natural justice as the Adjudicator had, in the exercise of his discretion, awarded the entire costs as sought by Fulloop based primarily on the power as statutorily provided under sub-s 18(1) CIPAA. Wabina has not submitted any valid or strong reasons for this Court to take a different view from that as expressed in several previous judgments. Moreover, Wabina had agreed to the fees as proposed by the Adjudicator, the calculation of which had taken into account the disputed amount as per the Payment Claim and the Notice of Adjudication. II. The Stay Application [72] Wabina’s Stay Application is made pursuant to para 16(1)(b) CIPAA which reads as follows: “Stay of Adjudication Decision 16. (1) A party may apply to the High Court for a stay of an adjudication decision in the following circumstances: (a) … (b) the subject matter of the adjudication decision is pending final determination by arbitration or the court.”. [73] It is immediately notable that, unlike in the majority of cases where there is an arbitration proceeding pending between parties who were the parties in the adjudication proceedings, in this case the arbitration proceeding is between Wabina as the main contractor and Seal as the employer. [74] Irrespective of this unique circumstance, Wabina asserted that a stay of the AD pending disposal of the ongoing arbitration between Wabina and Seal ought to be allowed since the position after the decision of the Federal Court in View Esteem (see particularly paras 79, 81 and 82 of the judgment) is settled in that a more flexible approach is to be taken and the Court can stay the AD where there are clear and unequivocal errors or the justice of the case warrants it. [75] Specifically, Wabina relied on the following grounds to support its application and the findings of this Court are explained alongside each ground: (a) The dispute by Seal as to the amount payable to Wabina in the arbitration between Wabina and Seal Wabina claims that there are special circumstances in its favour for a stay of the AD to be granted pending arbitration. According to Wabina, Seal alleged that it was entitled to impose liquidated damages (‘LD’) for the purported non-completion of the Project within the Revised Completion Date and to set off the entire LD from any sums due to be paid to Wabina. It is on this basis that Seal has ceased to make any payment starting from IPC No. 32. As such, Seal as the paying party is denying that there is any outstanding amount to be paid to the relevant parties including Fulloop. Fulloop’s claims in the adjudication proceedings against Wabina are thus not final yet. Furthermore, the issue on the Final Account for the Project is also disputed in the arbitration proceedings as Seal does not recognise any Statement of Final Account or draft Final Account prepared by any party, including the SFA, which was not acknowledged or approved by Seal as the employer and paying party. To date, Seal has also not disclosed its substantive and complete valuation for the Final Account. Meanwhile, Wabina has pleaded a Notice of Indemnity against all NSC, including Fulloop (dated 2.4.2020), in the event that Seal’s claim is allowed in the civil suit, which was subsequently stayed for to allow for the dispute to be referred to arbitration. Wabina asserted that Fulloop was aware of the arbitration proceedings between Wabina and Seal but Fulloop did not take any action to be involved in the said proceedings and nor did Fulloop dispute or deny the Notice of Indemnity. My view on this ground is, firstly, by virtue of s 13 CIPAA, an adjudication decision is binding unless, among others, the dispute is finally decided by arbitration or the court (see para(c) in s 13). The commonly utilised expression that an adjudication decision is of “temporary finality” or is “provisionally binding” is basically to describe the effect of the adjudication decision as stipulated in s 13 CIPAA. The word “dispute” in s 13(c) CIPAA, in my view, means the payment dispute between the parties in the adjudication proceedings, and it is this dispute that will be finally decided by the arbitral tribunal in the arbitration or by the court in the civil suit involving the same parties. As a matter of logical deduction, it cannot mean any other dispute to which one or both parties in the adjudication proceedings is, or are, not privy to. Secondly, the words “the subject matter of the decision” in s 13(b) CIPAA are similar to the words “subject matter of the adjudication decision” in para 16(1)(b) CIPAA. The issues or questions which are dealt with in the adjudication decision are those which were raised or submitted by the parties in the adjudication proceedings. The final determination to be made by arbitration or the court must necessarily involve the subject matter of the dispute between both parties in the adjudication and not to some other party or parties. Hence, by applying s 13(c) CIPAA, the AD is binding unless the dispute between Fulloop and Wabina is finally decided in the arbitration to which they are the parties. In the same vein, if Wabina wishes to apply for a stay of the AD pursuant to para16(1)(b) CIPAA, there must be an arbitration proceeding between Wabina and Fulloop which is afoot. Since Fulloop is not the claimant or the respondent in an arbitration proceeding involving Wabina as the opponent, the arbitration proceedings between Wabina and Seal does not, and cannot, constitute special circumstances for a stay of the AD to be granted. In fact, Wabina has not even fulfilled the threshold requirement in para 16(1)(b) CIPAA as there is no arbitration between Fulloop and Wabina regarding the subject matter of the AD which is pending determination. Fulloop’s knowledge of the arbitration proceedings between Wabina and Seal (see Wabina’s solicitor’s letter to Fulloop dated 30.4.2021) and Fulloop’s decision in not wanting to be involved in the said proceedings, are not legitimate grounds for this Court to extend the meaning of the word “arbitration” in para 16(1)(b) CIPAA to encompass the arbitration proceedings between Wabina and Seal. For the sake of completeness, it should be mentioned that Ms. K. Sheela did submit that the Adjudicator had addressed the outcome of the adjudication proceedings between Wabina and Seal (see too, Seal Properties (KL) Sdn Bhd v Wabina Constructions & Engineering Sdn Bhd [2021] MLJU 1045) under the “Issue of the possibility that the Claimant had received payments in full from the Employer” at paras 128 to 145 of the AD. The Adjudicator made a finding of fact that the adjudication decision dated 24.2.2020 proves that the adjudicated sum of RM7,025,008.30 awarded to Wabina is inclusive of Fulloop’s value of work under Payment Certificate Nos. 28B, 29 and 30 and that this amount had been fully paid by Seal to Wabina. Wabina’s contentions surrounding the LD claim by Seal were also dealt with by the Adjudicator in paras 146 to 162 in the AD under the “Issue of the Claimant shall be liable to its apportioned Liquidated Damages, in the event that any claim for the Liquidated Damages by the Employer against the Respondent is allowed”. The Adjudicator concluded that the LD claim by Seal against Wabina is not crystallised yet because Seal has made an application to the Federal Court against the adjudication decision dated 24.2.2020 and the arbitration proceeding between Wabina and Seal was still on-going. Moreover, the Adjudicator found that Wabina did not issue the Certificate of Non-Completion to Fulloop and the documentary evidence relating to which party had caused delay to the Project and the outstanding works as at the Revised Completion Date were lacking. (b) Financial standing of Fulloop Wabina relied on the SSM search on Fulloop especially the company charges and summary of financial information in submitting that Fulloop’s financial standing appears to be weak and raises concerns of its ability to repay the Adjudication Sum in the event that the arbitration award is granted in favour of Seal to impose and to set off the entire LD against the outstanding amounts to Wabina and which ought to be indemnified by Fulloop pursuant to the Notice of Indemnity. In paras 44 and 45 of the AIS, Wabina averred that Fulloop’s profit after tax for the financial year end of 31.10.2020 is RM399,810.00, which is much lesser than the Adjudication Sum, and that Fulloop has seven charges with financial institutions which remain unsatisfied, two of which were created recently on 21.7.2021. However, the part on “Company Charges” in the SSM Search in “EKSHIBIT 2” of the AIS shows only six unsatisfied charges. It is common for parties when making arguments in respect of SSM searches to be selective in their reading of the “Summary of Financial Information” by highlighting only the details which support their contentions. My assessment of the said Financial Information, being the sole document relied upon by Wabina in contending that Fulloop’s financial position is weak, is that Fulloop remains a growing concern. It recorded revenue of RM19,021,282.00 and has a total of current and non-current assets of RM34,905,309.00 as compared to a total current and non-current liabilities of RM24,314,903.00. Fulloop’s share capital is RM2.5 million and its retained earnings is RM8,090,406.00. Considering Fulloop’s financial status as at 31.10.2020 in toto, it is my considered view that Fulloop would be able to re-pay the Adjudication Sum in the event that Fulloop has to indemnify Wabina following the final award in the arbitration proceedings between Wabina and Seal. [76] The Court is satisfied that there are no clear or unequivocal errors in the AD (see the grounds as discussed under the Setting Aside Application), the justice of the case does not merit a stay of the AD (see the legal principles as expounded and applied in, among others, EA Technique (M) Sdn Bhd v Malaysia Marine and Heavy Engineering Sdn Bhd [2020] MLJU 2058, Panzana Enterprise Sdn Bhd v Mkp Builders Sdn Bhd [2020] MLJU 607, Maju Holdings Sdn Bhd v. Spring Energy Sdn Bhd [2021] 1 LNS 367, Office 2 Go (M) Sdn Bhd v Probina Projek Sdn Bhd and another case [2021] MLJU 2009 and Damai City Sdn Bhd v MCC Overseas (M) Sdn Bhd and other cases [2022] MLJU 1951) and there are no special circumstances to justify the exercise of the discretion of this Court towards a positive outcome for Wabina in the Stay Application. [77] To date, Fulloop has not received any payment from Wabina and in my opinion, there is no valid reason as to why Fulloop should be kept from reaping the fruits of the adjudication process which it had commenced since July 2021. III. The Enforcement Application [78] The provision governing the “Enforcement of adjudication decision as judgment” in the CIPAA reads as follows: “28. (1) A party may enforce an adjudication decision by applying to the High Court for an order to enforce the adjudication decision as if it is a judgment or order of the High Court. (2) The High Court may make an order in respect of the adjudication decision either wholly or partly and may make an order in respect of interest on the adjudicated amount payable. (3) The order made under subsection (2) may be executed in accordance with the rules on execution of the orders or judgment of the High Court.”. [79] Fulloop submitted that the AD should be enforced as if it is a judgment or order of the High Court so as to uphold the purpose of the CIPAA; the Adjudicator has the jurisdiction to hear the adjudication pursuant to sub-s 27(3) CIPAA and he has performed his duties and obligations and exercised his powers in accordance with ss 24 and 25 CIPAA; the merits of the AD cannot be raised at this stage; and there are no clear errors in the AD. [80] I agree with Fulloop. In addition, Fulloop has fulfilled the conditions for an order to be made to enforce the AD, namely, the AD is rendered in favor of Fulloop; Wabina has not paid the Adjudication Sum by the due date for payment as determined in the AD; and there is no prohibition to the grant of the order as sought by Fulloop (see Inai Kiara Sdn Bhd v Puteri Nusantara Sdn Bhd [2019] 2 CLJ 229 and the multitude of cases which have followed the said decision). Conclusion [81] Based on all the above said considerations, the Setting Aside Application and the Stay Application in O.S No. 42 and O.S No. 78 were dismissed and the Enforcement Application in O.S No. 67 was allowed with orders made as to costs as first stated in para 3 above. Dated: 26 October 2022 (ALIZA SULAIMAN) Judge Construction Court 2 High Court Kuala Lumpur Counsels/ Solicitors: For the Plaintiff in O.S. No. 42 & O.S.78 and the Defendant in O.S. No. 67: Lim Wooi Ying Messrs. The Chambers of Yu Shin Ong Advocates & Solicitors Unit 12A, Level 12, Menara KWSP Jalan Sultan Ahmad Shah 10050 Penang For the Plaintiff in O.S. No. 67 and the Defendant in O.S. No. 42 & O.S. No. 78: K. Sheela T. Vinayaka Das (Priya Ranjani Muthusamy with her) Messrs. Sheela Vinayaka & Co. Advocates & Solicitors No. 20-G, Jalan 65C Pekeliling Business Centre Off Jalan Pahang Barat 53000 Kuala Lumpur Cases, legislation and other sources referred to in the submissions by learned counsels and in the Grounds of Judgment: Cases: Ahmad Zaki Sdn Bhd v. Swaja Fascade Sdn Bhd & Anor And Another Case [2019] 1 LNS 1774 Alpha Galaxy Sdn Bhd v Euro Destar (M) Sdn Bhd and another case [2021] MLJU 767 Antah Schindler Sdn Bhd v. Golden Base Construction Sdn Bhd [2020] 1 LNS 1189 Badiaddin bin Mohd Mahidin & Anor v Arab Malaysian Finance Bhd [1998] 1 MLJ 393 Balfour Beatty Engineering Services (HY) Ltd v Shepherd Construction Ltd [2009] EWHC 2218 (TCC) Bina Puri Construction Sdn Bhd v. Hing Nyit Enterprise Sdn Bhd [2015] 8 CLJ 728 BM City Realty & Construction Sdn Bhd v. Merger Insight (M) Sdn Bhd & Another Case [2016] 1 LNS 1096 Bumimetro Construction Sdn Bhd v. Mayland Universal Sdn Bhd & Another Case [2017] 1 LNS 1959 Bond M & E (KL) Sdn Bhd v Isyoda (M) Sdn Bhd (Brampton Holdings Sdn Bhd, third party) [2017] MLJU 376 Cantillon Ltd v Urvasco Ltd [2008] EWHC 282 (TCC) Casmet Sdn Bhd v Otis Elevator Company (M) Sdn Bhd [2021] MLJU 560 Cempaka Majumas Sdn Bhd v. Ecoprasinos Engineering Sdn Bhd [2019] 1 LNS 2390 Ching Yew Chye & Ors v Pavitar Singh a/l Manjeet Singh & Anor [2018] 10 MLJ 612 CR Sea (Malaysia) Sdn Bhd v Zedelta Sdn Bhd (WA-24C-217-12/2021 & WA-24C-26-01/2022) Damai City Sdn Bhd v MCC Overseas (M) Sdn Bhd and other cases [2022] MLJU 1951 Desa Samudra Sdn Bhd v. Bandar Teknik Sdn Bhd & Ors [2012] 1 CLJ 429 Dr Che Wan Fadhil bin Che Wan Putra dan lain lain (menuntut bagi pihak mereka sendiri dan bagi pihak 127 orang yang lain) lwn Universiti Teknologi Malaysia [2010] 9 MLJ 736 EA Technique (M) Sdn Bhd v. Malaysia Marine and Heavy Engineering Sdn Bhd [2020] 1 LNS 1851 Giatreka Sdn Bhd v SGW Engineering Construction Sdn Bhd and another appeal [2019] MLJU 1477 Granstep Development Sdn Bhd v. Tan Chong Heng Construction Sdn Bhd [2022] 5 MLRH 444 Hong Xin Construction Sdn Bhd v Tewara Sdn Bhd [2020] MLJU 552 Inai Kiara Sdn Bhd v. Puteri Nusantara Sdn Bhd [2019] 2 CLJ 229 Ireka Engineering & Construction Sdn Bhd v Tri Pacific Engineering Sdn Bhd and another summons [2020] MLJU 548 Kembang Serantau Sdn Bhd v. Perbadanan Putrajaya [2022] 1 LNS 375 Kepong Prospecting Ltd & Ors v Schmidt [1968] 1 MLJ 170 Kerajaan Malaysia v. Shimizu Corporation & Ors [2018] 1 LNS 202 Kerajaan Malaysia v Global Upline Sdn Bhd and another appeal [2017] 1 MLJ 170 Maju Holdings Sdn Bhd v. Spring Energy Sdn Bhd [2020] 1 LNS 1194 Maju Holdings Sdn Bhd v. Spring Energy Sdn Bhd [2021] 1 LNS 367 Mammoth Empire Construction Sdn Bhd v STAM Engineering Sdn Bhd and another case [2019] 10 MLJ 58 Martego Sdn Bhd v. Arkitek Meor & Chew Sdn Bhd & Another Appeal [2018] 2 CLJ 163 Meda Property Services Sdn. Bhd. v Abric Cladding Sdn. Bhd. [2000] MLJU 310 Meridian Contracts Sdn Bhd v Bauer (Malaysia) Sdn Bhd and another summon [2020] MLJU 1405 Milsonland Development Sdn Bhd v Macro Resources Sdn Bhd [2018] 1 LNS 2078 Ming Ann Holdings Sdn Bhd v. Danaharta Urus Sdn Bhd [2002] 3 CLJ 380 MKP Builders Sdn Bhd v PC Geotechnic Sdn Bhd [2021] MLJU 1061 Office 2 Go (M) Sdn Bhd v Probina Projek Sdn Bhd and another case [2021] MLJU 2009 Otis Elevator Company (M) Sdn. Bhd. v. Castmet Sdn. Bhd. [2020] 1 LNS 2169 Panzana Enterprise Sdn Bhd v Mkp Builders Sdn Bhd [2020] MLJU 607 PCP Construction Sdn Bhd v Leap Modulation Sdn Bhd and other suits [2017] MLJU 905 Pinsia Development Sdn Bhd & Ors v Hj Abdul Hadi Ahmad & Ors [2005] 1 CLJ 416 Puncak Niaga Construction Sdn Bhd v Mersing Construction & Engineering Sdn Bhd and other cases [2021] MLJU 1824 PWC Corp Sdn Bhd v Ireka Engineering & Construction Sdn Bhd and another appeal [2018] MLJU 152 Ranhill E&C Sdn Bhd v. Tioxide (M) Sdn Bhd & Other Cases [2015] 1 LNS 1435 Samado Sdn Bhd v Kerajaan Malaysia [2020] MLJU 274 Seal Properties (KL) Sdn Bhd v Wabina Constructions & Engineering Sdn Bhd [2021] MLJU 1045 SQA Builders Sdn Bhd v Luxor Holdings Sdn Bhd and another suit [2017] MLJU 833 Subang Skypark Sdn Bhd v Arcadius Sdn Bhd [2015] 11 MLJ 818 Sundralingam v Ramanathan Chettiar [1967] 2 MLJ 211 Suwiri Sdn Bhd v Government of the State of Sabah [2008] 1 MLJ 743 Tecnicas Reunidas Malaysia Sdn Bhd v Petrovietnam Engineering Consultancy JSC (PVE) & Anor and other cases [2021] MLJU 2633 Terminal Perintis Sdn Bhd v Tan Ngee Hong Construction Sdn Bhd and another case [2017] MLJU 242 TRT Engineering (M) Sdn Bhd v Hansol KNM Greentech Sdn Bhd and another case [2020] MLJU 148; [2020] 1 LNS 88 Uzma Engineering Sdn. Bhd. v Khan Co. Ltd. and another summons [2020] MLJU 1272 View Esteem Sdn Bhd v Bina Puri Holdings Bhd [2018] 2 MLJ 22 View Esteem Sdn Bhd v Bina Puri Holdings Sdn Bhd [2015] MLJU 695 Wong Huat Construction Co v Ireka Engineering & Construction Sdn Bhd [2017] MLJU 739 Zana Bina Sdn Bhd v. Cosmic Master Development Sdn Bhd & Other Case [2017] 1 LNS 185 Legislation: Construction Industry Payment and Adjudication Act 2012, ss 4, 5, 13, 15, 16, 18, 25, 27, 28, 31, 35 & 37 Construction Industry Payment and Adjudication Regulations 2014, Regulations 6 & 7 Rules of Court 2012, O. 7, O. 28, O. 69A rr. 1, 2, 3, 5 and 7 & O. 92, r. Other source(s) referred to: Lam Wai Loon and Ivan YF Loo, Construction Adjudication In Malaysia, Third Edition, Sweet & Maxwell, 2022