… In my judgment, it is trite law that a contractor can only terminate his contract with his employer (at common law, as opposed to the exercise of an express termination clause) if he shows, inter alia, a repudiatory breach by the employer in the sense that the employer has evinced an absolute refusal not to perform his side of the contract. There is no intermediate right in a building contract to suspend works. If the contractor insists on the continued performance of the contract i.e. he affirms the contract, he must himself continue to perform his primary obligations under the contract i.e. to continue performing the contract works. This is why suspension of the works by the contractor i.e. not continuing with his primary obligations, becomes itself a repudiatory breach by the contractor. Even if the Plaintiff can establish that the Defendant is in repudiatory breach of the contract, the Plaintiff would have no right to suspend works, but instead would have had to elect to either terminate the contract or insist on due performance. By suspending works without valid legal cause, the Plaintiff has in fact repudiated its contractual obligations.... As there was no provision in the rudimentary contract between parties conferring a right to suspend works for non-payment of certified sums, the Plaintiff's admitted suspension was wrongful." [67] Due to the defendant’s reluctance to address and entertain the safety issues (which they are not entitled to do so as per the contract) and to resolve the problem quickly, the plaintiff then consulted independent consultants Swasta Sekutu (M) Sdn Bhd to inspect and assess the condition of the lifts. Swasta Sekutu (M) Sdn Bhd was present at the joint inspection meeting on 28 October 2015. Based on the Preliminary Survey Report by Swasta Sekutu (M) Sdn Bhd, the plaintiff then appointed C-Elevator Technology (M) Sdn Bhd to carry out rectifications works on the lifts. C-Elevator submitted a quotation for the amount of RM77,358.80 for rectification of the defects. [68] On 21 March 2016, the fully functioning lifts were handed over by C-Elevator to the plaintiff and been working well and are fully utilised by the School. [69] Now coming back to the plaintiff’s claim for LAD, as we have said that the lifts have to be completed by 28 February 2015. However, defendant failed to complete on or before the deadline. Hence, the amount of LAD to be paid is based on the Letter of Award up to the date of JKKP certification (see clause 6 LOA). This would be a period of 94 days calculated from 1 March 2015 to 2 June 2015 (and not on the day of JKKP inspection i.e. on 24 May 2015 as alleged by the defendant). [70] Clause 16 of the LOA provides for LAD of RM10,000 per day (and not limited to 5% of the contract value which amounts to RM28,300.00 as argued by the defendant based on Clause 7 of the General Conditions of Sales which was never pleaded by the defendant in its defence). Clearly there is a discrepancy between Clause 7 GCS and Clause 16 of the LOA. Clause 8 of the LOA provides that in the event of any discrepancy between the LOA and other documents, the LOA will take precedence. Therefore Clause 16 would prevail. [71] As such, the total LAD due up to the date of JKKP certification is RM940,000.00 (even though the lifts were not fit or safe to be used). The defendant also did not apply for extension of time to the Architect, in accordance with the terms of the LOA for failure to complete the lift installation within the 6 months period. [72] According to the defendant, the plaintiff granted an extension of time until 30 April 2015 for the defendant to complete the installation testing and commissioning of the lifts is untrue and unsupported by any documentary evidence. The defendant relies on a letter issued by the plaintiff on 6 March 2015. In this letter, reference is made to a discussion between parties on 4 March 2015, wherein the plaintiff was informed by the defendant that work could only be completed by 30 April 2015. However, in this letter, the plaintiff also makes the following statements very clear: "Notwithstanding the above, we reserve our rights to damages due to the delay on delivery and installation with approvals of all 3 lifts as per letter of award as the completion date was to be 28/2/2015." [73] In relation to Extension of time, Clause 23.0 of the PAM Contract 2006 (Without Quantities) provides as follows: