2 Subject to Clause 5.3, SSB agrees and acknowledges that the contribution to be made by CCSHK to SSB under Clause 5.1 shall be made in accordance with the following tranches:- First tranche : no more than RM8,321,847.00 to be paid on 24 December 2010; Second tranche : no more than RM5,825,293.00 to be paid when the total amount of invoices issued by SSB to MBSB for the On-Going Projects are no less than RM12,482,771.00; and Third tranche : no more than RM1,664,369.00 to be paid when CCSHK has received RM16,643,694.00 from the On-Going Projects". [6] In gist, CCL was to have received RM16,643,694.00 from Sediabena, payable from 90% of the payments received by Sediabena from Maxis. CCL would have made a profit of RM832,185.00. [7] Disputes arose between them, which led to CCL terminating the agreement. At this point, CCL had only paid the first tranche of RM8,321,847.00. CCL had refused to pay the second tranche as Sediabena did not provide the invoices to enable it to verify the amount billed to Maxis. CCL then commenced a suit against Sediabana in 2014, with the latter counterclaiming. The trial was on the issue of liability first. On 20 December 2015, the High Court gave judgment in favour of CCL and dismissed Sediabena's Counterclaim. The High Court held that CCL had validly terminated the agreement due to Sediabena's breach in failing to provide the invoices and ordered damages to be assessed. [8] Consequent to unsuccessful appeals by both parties to the Court of Appeal and Federal Court, CCL commenced assessing damages in the High Court. Both parties called witnesses to give evidence. CCL's claim for damages [9] CCL's claim as set out by the High Court were as follows: Claim No. 1 RM16,643,694.00 based on clause 5.7 of the agreement. Claim No. 2 RM8,321,847.00 being the first tranche of payment made by CCL under the agreement. Claims No. 3 and 5 Sums incurred by CCL towards the operational and capital expenditure for the project under the agreement. Claim No. 4 RM9,417,490.56 being 90% of all sums received by Sediabena from Maxis, which CCL claims it is entitled to under clause 6 of the agreement. The High Court's decision [10] The High Court had only allowed Claim No.2 with interest of 4% per annum from 10 December 2015 but dismissed Sediabena's claim for set-off based on the net loss approach. The rest of Sediabena's claims were dismissed. [11] The High Court's brief grounds in paragraph 11 of the Grounds of Judgment are as follows: "[11] Based on the foregoing, this Court awards damages to Plaintiff as follows:- a) Claim No.1. This Court agrees with the view of Defendant's counsel that there is no basis for Plaintiff to invoke clause 5.7 of the SAA to support its claim for RM16,643,694.00 as the payment of the $ 2^{nd} $ tranche has not been made to Defendant. As such this claim is dismissed. b) Claim No.2. It is an undisputed fact that Plaintiff has paid this amount to Defendant in accordance with clause 5.2 of SAA (the agreement). Hence, this Court allows this claim of RM8,321,847.00 without being subject to the 'net loss approach'. c) Claim No. 3 and Claim No. 5. Claim No. 3 is in relation to further sums allegedly incurred by Plaintiff towards operational and capital expenditure for the Project Works. Claim No. 5 is for finance and other costs allegedly incurred for the funding and expenditure. The claims are based on 3 summary sheets namely China Cost Summary, China Labour Cost Summary and Malaysia Cost Summary, prepared by Plaintiff, containing the compilation of data of all operational and capital expenditure incurred either by Plaintiff or through its associated or sister companies. This Court dismissed these claims based on the following reasons:- i. The supporting documents do not show expenses incurred by Plaintiff. ii. Expenses incurred by Guangdong Telecommunication Engineering Co. Ltd and CCS Comservice (Malaysia) Sdn Bhd. who are not parties to this proceeding. iii. Plaintiff failed to provide any evidence to support the relationship between Plaintiff and the two companies. iv. No privity of contract between Defendant and the two companies. v. Defendant has no knowledge of the alleged expenses incurred by these two companies. vi. Plaintiff failed to provide evidence that expenses were incurred for the Project under SAA. vii. Plaintiff cannot recover more than he would have been entitled to if Defendant had not broken the contract. d) Claim No. 4 - This is Plaintiff's claim for RM9,417,490.56 being 90% of all sums received by Defendant from Maxis in accordance with clause 6.1 of SAA. This Court noted that the High Court's decision (affirmed by the Court of Appeal) has not allowed Plaintiff's claim on breach of trust. Similarly, this Court dismissed this claim. Based on the balance of probabilities, this Court allows damages of RM8,321,847.00 to be paid to Plaintiff with no order as to cost." Findings [12] There are two methods for measuring damages suffered by parties: The expectation loss approach - where the party is restored to a position as if the contract had been performed and mainly to recover the profits that the party had lost or deprived; The reliance loss approach - where the party is to be restored to its position before the contract is entered, to recover the expenditure incurred for the contract before the breach or termination. CCL's failure to elect [13] We will first address Sediabena's contention that only nominal damages can be awarded to CCL as its claim is premised on expectation and reliance loss and, therefore, uncertain. [14] Sediabena contended that a party must elect to either claim for expectation loss, such as loss of profits, or reliance loss for wasted expenditure. Relying on the case of Delpuri-Hari Corp JV Sdn Bhd v Perbadanan Kemajuan Negeri Selangor [2014] 1 LNS 1075 (CA), it was submitted that a party seeking damages must elect and that it is not for the court to do so, and that a failure to do so would render the claim uncertain and that only nominal damages can be awarded. Sediabena contended that CCL had failed to make an election and that the High Court had failed to consider this legal principle by allowing CCL's claim in toto under Claim No.2. [15] We are disinclined to agree with Sediabena's proposition. We agree with CCL's proposition that an election is only necessary where alternative and inconsistent remedies are sought and that the election can be made at any time before judgment is given; see the Privy Council case of Tang Min Tat (decd) (personal representative) Capacious Investments Ltd [1996] 1 All ER 193. CCL, in this assessment, seeks compensation for Sediabena's breach, which can be assessed using either the expectation or reliance approach. These are legal approaches with the ultimate aim of compensating CCL. [16] The Delpuri-Hari (supra) case is distinguishable as the appellant sought liquidated damages for loss of profits and wasted expenditures. The court there held that the appellant was not entitled to claim for both at the same time and that the appellant should have made an election and not leave it to the court to exclude reliance losses from an expectation loss or vice versa. CCL here is not seeking expectation and reliance loss concurrently but seeking to have them as an alternative. Unlike the appellant in Delpuri-Hari, which sought liquidated damages, CCL here is seeking to have the damages assessed. [17] We will now address CCL's claims based on the High Court's findings. Claim No.1 [18] CCL's claim was premised on clause 5.7 of the agreement, which states as follows: "5.7 For the avoidance of doubt, CCSHK is entitled to receive RM16,643,694.00 from the On-Going Projects and shall be paid from 90% of all payments and proceeds accruing and received by SSB under the On-Going Projects to be distributed in accordance with the Agreed Benefit Ratio under the Dedicated Account. The parties agree and acknowledge that any amount in excess of the RM16,643,694.00 from the On-Going Projects shall accrue to SSB. However, in the event the total payment received by CCSHK under the On-Going Projects is less than RM16,643,694.00 ("Shortfall"), SSB shall reimburse CCSHK for the Shortfall and such reimbursement shall be paid from the payment or share to be received by SSB under the New Projects ("SSB Share of New Projects") and CCSHK is hereby irrevocably and unconditionally authorised by SSB to make any deduction from the SSB Share of New Projects for this purpose." [19] CCL's primary obligation under the agreement was to provide financial support not exceeding RM15,811,509.00 in three tranches as follows: