17.11 Whether the Defendant has made the advance payment of RM100,000.00 to the Plaintiff. If Yes, whether the Defendant is entitled to claim for the said payment from the Plaintiff. Analysis & Findings Did The Defendant Agree To The Hand Over Of The Site [18] From an analysis of the Issues To Be Tried, I find that the core issue in the matter before me is whether there is an agreement to hand over incomplete works. [19] It is undisputed in the case before me that the Plaintiff did not complete the works under the Contract. [20] It is the Defendant’s case that the Plaintiff had failed to complete its works and that the works carried out by the Defendant contained defects. [21] To this the Plaintiff alleges that there was purportedly an agreement not to complete its works by the Defendant’s actions which led the Plaintiff to believe that the hand over was valid. [22] I have found that the Plaintiff is not the only sub-subcontractor working in the Project and that the project also involves other trades but I must state, even at this early stage of my decision, that the Plaintiff has an obligation to work in co-ordination with other sub-subcontractors appointed and or to interface other related activities for the execution of the erection of work to prevent any physical disruption to the overall construction work. This is pursuant to the Addendum to the LOA which states [23] The Plaintiff has also raised its concern that certain areas of work consists of obstruction and hindered the progress of the Plaintiff’s work. To this I find that the Plaintiff has under the LOA an obligation to ensure that it has inspected the site and to satisfy itself of the conditions of the site including any physical obstructions for which the LOA states as follows [24] I also note that the Plaintiff submits that it was the instruction given by DW5, Low Keng Mun, to hand over the Works on an as is where is basis to the Defendant. [25] I have found that there are various letters dated 25.7.2020, 28.8.2020 and 14.9.2020 from the Plaintiff to the Defendant for various hand over of contract works for different locations, which can be found at Bundle AL pages 10,13,15, 23, 26 ,27, 28, 32, 33 and 34 respectively which, from the evidence before me, the Defendant did not appear to challenge nor by its conduct denied such handover letters. [26] I have observed that the Plaintiff’s letter dated 3.3.2021 had stated that it had completed the works including that under Locations 14 and 16 as of 25.2.2021: [27] The above evidence would from my findings however contradict the Plaintiff’s assertions that the Defendant had agreed to any handover prior to 3.3.2021 when the Plaintiff’s own evidence, as indicated above, shows that the Plaintiff had only completed its works on 25.2.2021. [28] This Court had also noted that the Plaintiff had in the aforesaid letters relied on alleged joint surveys allegedly proving the Defendant’s acceptance of the Plaintiff’s handover of the Works. However, from the Plaintiff’s Statement of Reply and Defence to Counterclaim (“SOR”), it was pleaded in paragraph 10 (a) therein that the joint surveys were carried out with the Defendant as a basis to allege that the Plaintiff’s Works were completed. [29] Thus, I have examined the said joint surveys, and I find that the same had only evidenced at best that the Plaintiff carried out its works in terms of the earthworks up until a certain level. The evidence in the said surveys do not show the quality of work done or that the Plaintiff completed the works up until the level that ought to have been completed by the Plaintiff under the Contract. [30] The above can also be seen from the testimony of PW2, Mohd Hafizul bin Hashim, when questioned by the Court on the purpose of the joint survey and where PW2 then testified as seen in NOP stated 17.7.2024 at page 50 lines 5 to 27 Saya ada satu soalan sebelum saya lepaskan En Hafizul. Berdasarkan dokumen yang telah dirujuk kepada En Hafizul berkenaan dengan joint survey, ingat lagi? Ya. Ada isu point dan apa-apa yang tertulis di sana. Boleh sahkan tak dengan Mahkamah, adakah joint survey tersebut menunjukkan apa-apa defect? Kalau dilihat daripada dokumen itu sahaja. Defect tak boleh menunjukkan di joint survey. Jadi, tujuan joint survey ialah untuk? Untuk hand over benda yang tak ada defect. Yang tak ada defect? Tak ada defect. Dan yang mana kerja telah dijalankan? Dijalankan dengan sempurna. [31] I acknowledge the case of United Exploration (M) Sdn Bhd v IJM Corp Bhd [2011] 8 MLJ 161; [2010] MLJU 894, where the Court therein held the defendant had adduced evidence of having written to the plaintiff reminding them to take measures to move on with their work in order to avoid delay in completing the project but the plaintiff did not see it fit to reply to the letter or to express any disagreement. If there had never been any failure on the part of the plaintiff in carrying out the project, it was only reasonable to expect from it a prompt and vigorous denial. [32] I have also found that the Defendant’s witness, Suah Choo Heang (DW6) the project manager, had at the trial testified that he did not see a need to reply to the letter and admitted that the Defendant did not make any demand to the Plaintiff to come back to complete the Works upon its handover to the Defendant. The NOP states Ok. So, my question, my instruction is the Plaintiff is just a few kilometres away, and this handover is actually proposed and accepted between the parties, it’s a mutual agreement. Agree or disagree? Disagree. I suggest to you that at the point of time the Plaintiff is just slight kilometres away, you can at any time just tell the Plaintiff to come back and finish the work. Agree or disagree? Disagree. But, you never take any action to tell or convey the message to the Plaintiff that their work is not acceptable. Agree or disagree? Disagree. So, what have you done to tell the Plaintiff that come back to work, your work is incomplete? The work has been delayed so long, and I have been imposed penalty by my client with the amount of close to, possible between RM50,000 to RM100,000 per day. So, with the impact I’m facing, I have to finish the work as soon as possible, rather than still calling them back to finish the work. It will cause further delay. That means you never informed the Plaintiff, and you decided to do it yourself. I had to do it, not I decided to do it. I am compelled or forced to do it by myself to avoid further damage. Everyday I can’t afford the RM50,000 to RM100,000 penalty. [33] I also refer to the Court of Appeal case of David Wong Hong Leong v Noor Azman bin Adnan [1995] 4 CLJ 155 which is authority for the fact that the Courts have taken notice that, in the ordinary course of business, if one man of business states in a letter to another that he has agreed to do certain things, the person who receives that letter must answer it if he means to dispute the fact that he did so agree. In delivering the judgement of the Appellate Court, Gopal Sri Ram JCA had stated “In this context, we recall to mind the following passage in the judgment of Edgar Joseph Jr. J. in Tan Cheng Hock v. Chan Thean Soo [1986] CLJU 42; [1986] 1 LNS 42[1987] 2 MLJ 479-487: In Wiedemann v. Walpole [1891] 2 Q.B. 534, 537 an action for breach of promise of marriage, it was held, that the mere fact that the defendant did not answer letters written to him by the plaintiff in which she stated that he had promised to marry her, was no evidence corroborating the plaintiff's testimony in support of such promise. Lord Esher M.R., in his judgment, remarked, Here, we have only to see whether the mere fact of not answering the letters, with nothing else for us to consider is any evidence in corroboration of the promise.' (Emphasis added). Earlier, in his judgment, he said, 'Now there are cases - business and mercantile cases in which the Courts have taken notice that, in the ordinary course of business, if one man of business states in a letter to another that he has agreed to do certain things, the person who receives that letter must answer it if he means to dispute the fact that he did so agree. (The emphasis is ours.)” [34] Applying the aforesaid cases to the matter before me, I find that the evidence before this Court shows that there was a letter from the Defendant to the Plaintiff dated 16.11.2020 at page 310 of Bundle T stating that the Works for Locations 14,15 and 17 (Phase 1) were incomplete and that the Plaintiff had “..intentionally demobolized all your machinery and manpower…without finishing the Works as per specification and to the Client acceptable conditions.” [35] The aforesaid letter appears to have been issued a few months after the Plaintiff started to allegedly hand over the Works i.e 10.7.2020 and the same was verified by DW6, Suah Choo Heang, the Defendant’s Project Manager in his testimony before the Court. [36] There is however also before this Court a letter dated 21.12.2020 from the Plaintiff to the Defendant, as per Bundle AL page 51, where the Plaintiff had expressly stated inter alia that they “…disagree on the words of ‘Non Completion of Works’ due to mutual agreement from both parties during handing over stage” and stated that this was “..an afterthought action…” as well as “..we have not yet demobilize our machinery and manpower…..but we are proceeding with the second stage work before Renggan Viaduct…” [37] From the trial, it appears that the above letter was not replied to by the Defendant. However, on a balance of probabilities and the facts before this Court, I do hold that there is before me only sufficient evidence to show that the handover of the Works from the Plaintiff to the Defendant was requested upon but that the same did not necessarily amount to an agreed handover. [38] In any event, the handover of the Works to the Defendant based on the Plaintiff’s pleaded case, as seen in its Reply to the Amended Defence and Defence to the Amended Counter Claim is that there was a failure by the Defendant to give clear instructions which led to the handover of the Works to the Defendant and not that there was a mutual agreement to handover. This again flies against the evidence relied on by the Plaintiff at the trial. [39] After looking at the totality of the evidence before me, I further find that only Location 13 was properly handed over on 23.1.2020 by the Plaintiff where the Plaintiff submitted the Inspection Checkpoint Forms, ref no.: CRJGR-SIPY-ICF-INF-S3.3-QAL-ALL-0002, dated 20.1.2020 , refer to Bundle AD pages 7 to 12 ref no. CRJGR-SIPY-ICF-S3.3-QAL-ALL-0004, dated 22.1.2020, Bundle AD pages 13 to 16, and ref no. CRJGR-SIPY-ICF-S3.3-QAL-ALL-00005 dated 22.1.2020 as per Bundle AD pages 17 to 24. [40] The documents above are in my considered view proof that the Plaintiff recognised the proper procedure to handover the works by submitting the requisite inspection checkpoint forms and conducting a joint inspection with the Main Subcontractor. I have consequently observed that these requirements were not observed by the Plaintiff for any of the other Locations. [41] I also hold that the Plaintiff did not deny that as of 3.3.2021 i.e the date the Plaintiff wrote in to apply for the issuance of the certificate of practical completion, the alleged practical completion had not been achieved, see the testimony of Chai Ying Kong (PW1) under cross examination which can be found in the Notes of Proceedings (NOP) at enclosure 159 page 56 lines 2 to 29 where PW 1 testified: Jadi, bila dalam surat 03/03/2021 di sini, En Chai atau Plaintif meminta certificate of practical completion. Apa yang dinyatakan atau direpresentasikan oleh pihak Plaintif adalah bahawa practical completion telah pun dicapai ya. Ya. Tetapi En Chai bersetuju bahawa practical completion untuk seluruh skop kerja pihak Plaintif sebenarnya tidak dicapai setakat 03/03/2021. Sebab kita sudah siap kerja. Jawab soalan. Kita tak ada kerja yang perlu buat. Practical completion untuk seluruh skop kerja pihak Plaintif belum lagi disiapkan setakat 03/03/2021. Saya mahu kata skop kerja saya yang boleh saya siapkan pada masa itu sudah disiapkan. Jadi, saya menyatakan kepada En Chai bahawa setakat 03/03/2021, practical completion belum lagi dicapai. Untuk skop kerja Plaintif yang boleh dicapai telah disiapkan, sebab tak ada arahan baru daripada Defendan untuk kita buat kerja lagi. Mesin semua ada – [42] During the trial the Plaintiff claims that it was constrained to handover the Site as a result of inter alia other drainage works ongoing that obstructed the Plaintiff from completing the Works. From the facts before me I find that the Works site is about 10km long as seen from a copy of the site plan as found in Bundle AM page 163. [43] I have further observed that the Works site is such that works can proceed concurrently at several locations, as one location does not depend on the completion of another. This is explained by DW6 in his evidence at the NOP at enclosure 160 pages 292 to 293 lines 34 to 10 Can I just get you to explain, when you say works should proceed concurrently, what did you mean? Can you just explain? Yes, for example, if the drainage work is ongoing, so you don’t have to finish all the drainage work then only you start the sand or sub-ballast work. For example if the drainage work finish 50%, then you can just continue the, no, the 50m then you can just start the 50m and coordinating with each other to complete the work concurrently. Alright. And when you say the major works were the Plaintiff’s, what did you mean? Yes. Because before the drainage work start, the Plaintiff have to get ready the platform for the Plaintiff work to start as well. Without the Plaintiff’s work ready, the drainage work cannot start. So everything is related to the Plaintiff. So it’s some sort of the coordinating. Without the Plaintiff, the drainage work also cannot start. [44] I therefore hold that the Plaintiff’s remedy in such a situation would be to seek an extension of time. [45] It is my further decision that it is no excuse under law for the Plaintiff to abandon the balance of the Works, as the Plaintiff could have, but did not, apply for EOT. [46] Looking at the case as a whole, I therefore accept that the other respective chainages could only be handed over to the Defendant Main Subcontractor on the dates as follows, which are as recorded in the respective Quality Inspection Checkpoint Forms which I have examined and confirmed and with the dates in bold and underlined representing the last dates the Works for each Location could be regarded as being handed over and the KAHD being attained:- Chainage Location KAHD eventually achieved by Defendant Quality Control Inspection Checkpoint Form 1.1. CH684975 – CH685450 14 1.9.2020 S3.3-QAL-ALL-00009 [Bundle AD / pp 76 – 94] Chainage Location KAHD eventually achieved by Defendant Quality Control Inspection Checkpoint Form 1.2. CH687050 – CH687400 14 6.10.2020 S3.3-QAL-ALL-00013 [Bundle AD / pp 124 – 144]