Zeta’s AIR affirmed by the same deponent on 12.10.2021 (encl. 5). Background Facts [5] JAKS Island Circle Sdn Bhd is the employer (‘Employer’) of the project known as “Cadangan Membina Dua (2) Blok Pejabat 14 - 17 Tingkat, Tiga (3) Blok Pangsapuri Servis 25 - 34 Tingkat Dengan Sepuluh (10) Podium Yang Mengandungi Mezanin Kemudahan Pangsapuri, Ruang Perniagaan (33 Yunit), Pejabat Dan Tempat Letak Kereta Beserta Empat (4) Aras Basemen Tempat Letak Kereta Di Atas Lot 141 (PT16), Jalan 13/6, Seksyen 13, Bandar Petaling Jaya, Daerah Petaling, Selangor Darul Ehsan Untuk Tutuan Jaks Island Circle Sdn Bhd.” (‘Project’). The Employer appointed JAKS as the main contractor of the Project. [6] By the Letter of Award dated 12.11.2014 (‘LoA’), JAKS accepted Zeta’s tender for the “Electrical 11 KV & LV Installation & Electrical Power Supply for ACMV Services” (‘Works’) for the sub-contract fixed lump sum price of RM29,600,000.00 inclusive of a contingency sum of RM800,000.00. [7] The parties agreed that the Agreement And Conditions Of PAM Sub-Contract 2006 For Use Where The Sub-Contractor Is Nominated Under The PAM Contract 2006 (‘PAM Sub-Contract’) shall form part of the sub-contract documents. [8] The completion date for the Works is 31.12.2020. [9] According to Zeta, the process of certification and payment during the tenure of the sub-contract was that Turner & Townsend (‘Consultant’) would certify and issue their Payment Valuation Recommendation (‘PVR’) and JAKS would then issue the Certificate of Interim Payment (‘IPC’) by relying on the PVR. JAKS would subsequently make payment to Zeta based on the IPC. [10] Disagreements loomed ahead for the parties. On one hand, Zeta claimed that after the issuance of PVR Nos. 45 to 50 and IPC No. 44 on 27.2.2020, JAKS started to delay in making payments to Zeta. Zeta had sent letters dated 10.6.2020, 21.7.2020 and 16.10.2020 to JAKS to pay the outstanding amounts which were due between June and October 2020. Some part payments were made by JAKS to Zeta during this period. [11] On the other hand, JAKS had written a series of letters of its own to Zeta dated 5.6.2020, 15.6.2020, 22.6.2020 and 17.11.2020 to complain about, among others, Zeta’s sub-par performance of the Works and failure to ensure its supervisor is on site to supervise the Works, the need for defects rectification works and delay in completing the Works. [12] On 30.11.2020, Zeta issued its Progress Claim No. 64 for the sum of RM5,045,176.36. However, payment was not forthcoming from JAKS. Hence, on 16.12.2020, Zeta issued the notice under Clause 26.15 of the PAM Sub-Contract of its intention to suspend the execution of the Works (‘Notice To Suspend Works’) until such time when payment in the sum of RM1,608,001.51 is made. [13] A meeting was held on 17.12.2020 between the representatives from JAKS, Zeta, the Employer and the Consultant and as expected, the parties have different versions of the discussions which took place at the meeting. JAKS had prepared the Minutes of Meeting, and this was circulated to the parties who attended the meeting vide a letter dated 24.12.2020. In the third last paragraph of the said letter, JAKS said that it had on 21.12.2020, offered to pay RM500,000.00 by December and another RM500,000.00 by January 2021 hoping to move the progress of the Works but the offer was declined by Zeta. [14] On 22.12.2020, JAKS wrote to Zeta stating that, despite repetitive reminders, Zeta has failed to carry out the Works in respect of the Engineer’s Instruction (‘EI’) No. 69 and in order not to further delay the Project, JAKS will be taking over and engaging a third party to complete the Works. [15] Thereafter, Zeta sent its letter dated 24.12.2020 whilst JAKS responded vide letter dated 28.12.2020, to convey their respective positions on the proposed appointment of a third party, each asserting that the other is in breach of the PAM Sub-Contract. [16] Zeta then issued the letter dated 29.12.2020 to JAKS alleging that JAKS’ action amount to a fundamental breach of the sub-contract that goes to the root of the same and shows that JAKS have no intention to abide by the terms of the sub-contract. Zeta additionally claimed that JAKS’ action is a wrongful repudiation of the sub-contract, and it deemed the agreement between the parties was terminated (‘Notice of Termination’). [17] The representatives from JAKS, Zeta and the Consultant had conducted a joint inspection on 31.12.2020 (‘1st JI’) and a list of outstanding works by Zeta dated 6.1.2021 was prepared. A second joint inspection was conducted on 25.2.2021 (‘2nd JI’). [18] Meanwhile, Zeta submitted its Payment Claim pursuant to s 5 of the CIPAA on 2.2.2021 for the total claimed amount of RM6,654,238.23. This amount was subsequently reduced to RM6,604,238.23. [19] This was followed with the submission of the Payment Response, Notice of Adjudication, Adjudication Claim, Adjudication Response and Adjudication Reply on 17.2.2021, 19.2.2021, 6.4.2021, 20.4.2021 and 28.4.2021, respectively. [20] The Adjudicator, having considered the arguments of the parties, had determined in para 259 of the AD that: “(a) The Claimant’s claim against the Respondent for the sum of RM6,160,776.36 is hereby allowed with costs.