A person shall be eligible to apply for a feed-in approval allowing the person to participate in the feed-in tariff system if—

(a)

the person proposes to generate renewable energy from a renewable energy installation having an installed capacity of not more than thirty megawatts or such higher installed capacity as may be approved by the Minister; and

(b)

the person meets such other criteria as may be prescribed by the Authority from time to time.

Application for feed-in approval