/akn/my/act/pua/2017/11

PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017

The full official text, structured for quick navigation. Copy any provision or jump straight to a section.

Open source PDF
Type
P.U. (A)
Status
In force
Enacted
2017
Sections
5

Quick answer

About this p.u. (a)

PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017 is Malaysia P.U. (A), cited as P.U. (A) 11 2017, currently marked in force and first recorded in 2017.

Opening note

Preamble

Suggest a correction
  1. PADA menjalankan kuasa yang diberikan oleh subseksyen 55(3) Akta Kilang dan Jentera 1967 [Akta 139], Menteri membuat perintah yang berikut: Nama

Seksyen 1

Perintah ini bolehlah dinamakan

Open as pageSuggest a correction

Perintah

Kilang dan

Jentera

(Pengecualian kepada BP PETRONAS Acetyls Sdn. Bhd., Kertih, Terengganu) 2017.

Seksyen 2

Pengecualian

Open as pageSuggest a correction

Semua jentera yang didaftarkan dengan Ketua Pemeriksa, dengan nombor pendaftaran dan perihalan yang dinyatakan dalam ruang (1) dan (2) Jadual, atas nama

BP PETRONAS Acetyls Sdn. Bhd., Kertih, Terengganu yang telah dikeluarkan perakuan kelayakan, adalah dikecualikan daripada persediaan yang dikehendaki di bawah perenggan 17(b) Peraturan-Peraturan (Pemberitahu, Perakuan Kelayakan dan

Pemeriksaan) Kilang dan Jentera 1970 [P.U. (A) 43/1970] bagi pemeriksaan ulangan yang berikutnya selepas habis tempoh perakuan kelayakan itu sebagaimana yang dinyatakan dalam ruang (3) Jadual.

Seksyen 3

Syarat pengecualian

Open as pageSuggest a correction

Pengecualian di bawah perenggan 2 tertakluk kepada syarat bahawa semua jentera yang dinyatakan dalam Jadual menjalani pemeriksaan luaran dan ujian tanpa musnah, dan Pemeriksa berpuas hati dengan keputusan pemeriksaan dan ujian itu.

P.U. (A) 11 3

Jadual

Suggest a correction

JADUAL

(1)

No. Pendaftaran

(2)

Perihalan Jentera

(3)

Tarikh Habis Tempoh

127456

Bejana tekanan tidak berapi 24 Februari 2017

127457

Bejana tekanan tidak berapi 24 Februari 2017

127458

Bejana tekanan tidak berapi 24 Februari 2017

127459

Bejana tekanan tidak berapi 24 Februari 2017

127460

Bejana tekanan tidak berapi 24 Februari 2017

127461

Bejana tekanan tidak berapi 24 Februari 2017

127462

Bejana tekanan tidak berapi 24 Februari 2017

127463

Bejana tekanan tidak berapi 24 Februari 2017

127464

Bejana tekanan tidak berapi 15 Januari 2017

127465

Bejana tekanan tidak berapi 24 Februari 2017

127466

Bejana tekanan tidak berapi 24 Februari 2017

127467

Bejana tekanan tidak berapi 15 Januari 2017

127468

Bejana tekanan tidak berapi 24 Februari 2017

127469

Bejana tekanan tidak berapi 24 Februari 2017

127471

Bejana tekanan tidak berapi 9 Februari 2017

127472

Bejana tekanan tidak berapi 9 Februari 2017

127473

Bejana tekanan tidak berapi 9 Februari 2017

127474

Bejana tekanan tidak berapi 24 Februari 2017

P.U. (A) 11 4

(1)

No. Pendaftaran

(2)

Perihalan Jentera

(3)

Tarikh Habis Tempoh

127475

Bejana tekanan tidak berapi 24 Februari 2017

127476

Bejana tekanan tidak berapi 24 Februari 2017

127477

Bejana tekanan tidak berapi 24 Februari 2017

127479

Bejana tekanan tidak berapi 24 Februari 2017

127480

Bejana tekanan tidak berapi 24 Februari 2017

127481

Bejana tekanan tidak berapi 24 Februari 2017

127482

Bejana tekanan tidak berapi 24 Februari 2017

127483

Bejana tekanan tidak berapi 24 Februari 2017

127512

Bejana tekanan tidak berapi 24 Februari 2017

127513

Bejana tekanan tidak berapi 24 Februari 2017

127514

Bejana tekanan tidak berapi 24 Februari 2017

127515

Bejana tekanan tidak berapi 24 Februari 2017

127516

Bejana tekanan tidak berapi 24 Februari 2017

127517

Bejana tekanan tidak berapi 24 Februari 2017

127518

Bejana tekanan tidak berapi 24 Februari 2017

127519

Bejana tekanan tidak berapi 24 Februari 2017

127520

Bejana tekanan tidak berapi 24 Februari 2017

127521

Bejana tekanan tidak berapi 24 Februari 2017

127524

Bejana tekanan tidak berapi 24 Februari 2017

P.U. (A) 11 5

(1)

No. Pendaftaran

(2)

Perihalan Jentera

(3)

Tarikh Habis Tempoh

127525

Bejana tekanan tidak berapi 24 Februari 2017

127526

Bejana tekanan tidak berapi 24 Februari 2017

127527

Bejana tekanan tidak berapi 24 Februari 2017

127528

Bejana tekanan tidak berapi 9 Februari 2017

127529

Bejana tekanan tidak berapi 9 Februari 2017

127530

Bejana tekanan tidak berapi 9 Februari 2017

127531

Bejana tekanan tidak berapi 9 Februari 2017

127532

Bejana tekanan tidak berapi 24 Februari 2017

127533

Bejana tekanan tidak berapi 24 Februari 2017

127534

Bejana tekanan tidak berapi 24 Februari 2017

127535

Bejana tekanan tidak berapi 24 Februari 2017

127536

Bejana tekanan tidak berapi 9 Februari 2017

127537

Bejana tekanan tidak berapi 9 Februari 2017

127538

Bejana tekanan tidak berapi 9 Februari 2017

127539

Bejana tekanan tidak berapi 24 Februari 2017

127540

Bejana tekanan tidak berapi 9 Februari 2017

127541

Bejana tekanan tidak berapi 24 Februari 2017

140238

Bejana tekanan tidak berapi 24 Februari 2017

140491

Bejana tekanan tidak berapi 15 Januari 2017

P.U. (A) 11 6

(1)

No. Pendaftaran

(2)

Perihalan Jentera

(3)

Tarikh Habis Tempoh

753

Bejana tekanan tidak berapi 24 Februari 2017

911

Bejana tekanan tidak berapi 24 Februari 2017

1540

Bejana tekanan tidak berapi 24 Februari 2017

3116

Bejana tekanan tidak berapi 24 Februari 2017

Dibuat 9 Januari 2017

[KSM/PUU/(S)/600-1/2/10/2 JLD. 5; PN(PU2)235/XLV]

DATO’ SRI RICHARD RIOT ANAK JAEM

Menteri Sumber Manusia

P.U. (A) 11 7

FACTORIES AND MACHINERY ACT 1967

FACTORIES AND MACHINERY (EXEMPTION TO BP PETRONAS ACETYLS SDN. BHD.,

KERTIH, TERENGGANU) ORDER 2017

IN exercise of the powers conferred by subsection 55(3)

of the Factories and Machinery Act 1967 [Act 139], the Minister makes the following order:

Citation

1. This order may be cited as the

Factories and

Machinery

(Exemption to BP PETRONAS Acetyls Sdn. Bhd., Kertih, Terengganu) Order 2017.

Exemption 2.

All machinery registered with the Chief Inspector, with the registration numbers and descriptions as specified in columns (1) and (2) of the Schedule, in the name of BP PETRONAS Acetyls Sdn. Bhd., Kertih, Terengganu which have been issued with certificates of fitness, are exempted from the preparation required under paragraph 17(b) of the Factories and Machinery (Notification, Certificate of Fitness and

Inspection) Regulations 1970 [P.U. (A) 43/1970] for subsequent regular inspection after the expiry of such certificates of fitness as specified in column (3) of the Schedule.

Condition of exemption

3. The exemption under paragraph 2 is subject to the condition that all of the machinery as specified in the Schedule undergo an external inspection and non-destructive tests, and the Inspector is satisfied with the result of such inspection and tests.

P.U. (A) 11 8

Jadual

Suggest a correction

(1)

Registration No.

(2)

Description of Machinery

(3)

Expiry Date

127456

Unfired pressure vessel 24 February 2017

127457

Unfired pressure vessel 24 February 2017

127458

Unfired pressure vessel 24 February 2017

127459

Unfired pressure vessel 24 February 2017

127460

Unfired pressure vessel 24 February 2017

127461

Unfired pressure vessel 24 February 2017

127462

Unfired pressure vessel 24 February 2017

127463

Unfired pressure vessel 24 February 2017

127464

Unfired pressure vessel 15 January 2017

127465

Unfired pressure vessel 24 February 2017

127466

Unfired pressure vessel 24 February 2017

127467

Unfired pressure vessel 15 January 2017

127468

Unfired pressure vessel 24 February 2017

127469

Unfired pressure vessel 24 February 2017

127471

Unfired pressure vessel 9 February 2017

127472

Unfired pressure vessel 9 February 2017

127473

Unfired pressure vessel 9 February 2017

127474

Unfired pressure vessel 24 February 2017

P.U. (A) 11 9

(1)

Registration No.

(2)

Description of Machinery

(3)

Expiry Date

127475

Unfired pressure vessel 24 February 2017

127476

Unfired pressure vessel 24 February 2017

127477

Unfired pressure vessel 24 February 2017

127479

Unfired pressure vessel 24 February 2017

127480

Unfired pressure vessel 24 February 2017

127481

Unfired pressure vessel 24 February 2017

127482

Unfired pressure vessel 24 February 2017

127483

Unfired pressure vessel 24 February 2017

127512

Unfired pressure vessel 24 February 2017

127513

Unfired pressure vessel 24 February 2017

127514

Unfired pressure vessel 24 February 2017

127515

Unfired pressure vessel 24 February 2017

127516

Unfired pressure vessel 24 February 2017

127517

Unfired pressure vessel 24 February 2017

127518

Unfired pressure vessel 24 February 2017

127519

Unfired pressure vessel 24 February 2017

127520

Unfired pressure vessel 24 February 2017

127521

Unfired pressure vessel 24 February 2017

127524

Unfired pressure vessel 24 February 2017

P.U. (A) 11 10

(1)

Registration No.

(2)

Description of Machinery

(3)

Expiry Date

127525

Unfired pressure vessel 24 February 2017

127526

Unfired pressure vessel 24 February 2017

127527

Unfired pressure vessel 24 February 2017

127528

Unfired pressure vessel 9 February 2017

127529

Unfired pressure vessel 9 February 2017

127530

Unfired pressure vessel 9 February 2017

127531

Unfired pressure vessel 9 February 2017

127532

Unfired pressure vessel 24 February 2017

127533

Unfired pressure vessel 24 February 2017

127534

Unfired pressure vessel 24 February 2017

127535

Unfired pressure vessel 24 February 2017

127536

Unfired pressure vessel 9 February 2017

127537

Unfired pressure vessel 9 February 2017

127538

Unfired pressure vessel 9 February 2017

127539

Unfired pressure vessel 24 February 2017

127540

Unfired pressure vessel 9 February 2017

127541

Unfired pressure vessel 24 February 2017

140238

Unfired pressure vessel 24 February 2017

140491

Unfired pressure vessel 15 January 2017

P.U. (A) 11 11

(1)

Registration No.

(2)

Description of Machinery

(3)

Expiry Date

753

Unfired pressure vessel 24 February 2017

911

Unfired pressure vessel 24 February 2017

1540

Unfired pressure vessel 24 February 2017

3116

Unfired pressure vessel 24 February 2017

Made 9 January 2017

[KSM/PUU/(S)/600-1/2/10/2 JLD. 5; PN(PU2)235/XLV]

DATO’ SRI RICHARD RIOT ANAK JAEM

Minister of Human Resources

Common questions

What is PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017?
PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017 is Malaysia P.U. (A), cited as P.U. (A) 11 2017, currently marked in force and first recorded in 2017.
Is PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017 still in force?
Yes — PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017 is currently in force.
When did PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017 take effect?
PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017 was first recorded in 2017.
How many sections does PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017 have?
PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017 contains 3 sections.
Where can I read the official version of PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017?
The official text of PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA BP PETRONAS ACETYLS SDN. BHD., KERTIH, TERENGGANU) 2017 is published at lom.agc.gov.my.