Seksyen 1
(1)
Kaedah-kaedah ini bolehlah dinamakan Kaedah-Kaedah Tenaga Boleh
Baharu (Kelulusan Galakan dan Kadar Tarif Galakan) (Pindaan) (No. 2) 2013.
(2)
Kaedah-Kaedah ini disifatkan telah mula berkuat kuasa pada 28 Mac 2013.
Pindaan kaedah 19
/akn/my/act/pua/2013/312
The full official text, structured for quick navigation. Copy any provision or jump straight to a section.
Quick answer
KAEDAH-KAEDAH TENAGA BOLEH BAHARU (KELULUSAN GALAKAN DAN KADAR TARIF GALAKAN) (PINDAAN) (NO. 2) 2013 is Malaysia P.U. (A), cited as P.U. (A) 312 2013, currently marked in force and first recorded in 2013.
Opening note
Kaedah-kaedah ini bolehlah dinamakan Kaedah-Kaedah Tenaga Boleh
Baharu (Kelulusan Galakan dan Kadar Tarif Galakan) (Pindaan) (No. 2) 2013.
Kaedah-Kaedah ini disifatkan telah mula berkuat kuasa pada 28 Mac 2013.
Pindaan kaedah 19
Kaedah-Kaedah Tenaga Boleh Baharu (Kelulusan Galakan dan Kadar Tarif Galakan)
011 [P.U. (A) 385/2011], yang disebut “Kaedah-Kaedah ibu” dalam Kaedah-Kaedah ini, dipinda dalam subkaedah 19(6) dengan memotong perkataan “dan membayar fi yang ditetapkan dalam Jadual Kedua,”.
Penggantian Jadual Kedua
Kaedah-Kaedah ibu dipinda dengan menggantikan Jadual Kedua dengan Jadual yang berikut:
“JADUAL KEDUA
(Subkaedah 4(1), 4A(3), 13A(2), 16(2), 18(1), dan kaedah 24)
FI
Butir
Jenis Fi
Jumlah fi (RM)
Borang permohonan bagi kelulusan galakan—
00 bagi setiap borang
P.U. (A) 312 3
Butir
Jenis Fi
Jumlah fi (RM)
melalui perantara elektronik atau secara penghantaran elektronik
Tiada 2.
Fi permohonan bagi kelulusan galakan 10.00 bagi setiap kilowatt kapasiti terpasang
(tertakluk kepada fi minimum RM100.00)
Fi pemprosesan yang kena dibayar oleh penjana yang layak yang merupakan seorang individu bagi permohonan kelulusan galakan yang dikemukakan—
00 bagi setiap permohonan
00 bagi setiap permohonan 4.
Fi pemprosesan yang kena dibayar oleh penjana yang layak selain individu bagi permohonan kelulusan galakan yang dikemukakan—
00 bagi setiap permohonan
00 bagi setiap permohonan 5.
Fi pemprosesan yang kena dibayar oleh penjana yang layak yang merupakan seorang individu bagi suatu pindaan kepada butir-butir dalam permohonannya bagi kelulusan galakan 50.00 6.
Fi pemprosesan yang kena dibayar oleh penjana yang layak selain individu bagi suatu pindaan kepada butir-butir dalam permohonannya bagi kelulusan galakan 100.00 7.
Fi pemprosesan yang kena dibayar oleh seseorang pemegang kelulusan galakan yang merupakan seorang individu bagi pindaan kepada kelulusan galakannya yang berhubungan dengan—
kad pengenalan pendaftaran nasional atau nombor pasport pemegang kelulusan galakan
00
00
P.U. (A) 312 4
Butir
Jenis Fi
Jumlah fi (RM)
Fi pemprosesan yang kena dibayar oleh pemegang kelulusan galakan selain seorang individu bagi pindaan kepada kelulusan galakannya yang berhubungan dengan—
00
00 9.
Fi permohonan yang kena dibayar oleh pemegang kelulusan galakan yang merupakan seorang individu bagi pengubahan syarat kelulusan galakannya 500.00 10.
Fi permohonan yang kena dibayar oleh pemegang kelulusan galakan selain seorang individu bagi pengubahan syarat kelulusan galakannya 2500.00 11.
Fi permohonan bagi kelulusan galakan penggantian 50.00 12.
Fi permohonan yang kena dibayar oleh pemegang kelulusan galakan yang merupakan seorang individu bagi penyerahhakan atau pemindahan hakmilik kelulusan galakannya 500.00 13.
Fi permohonan yang kena dibayar oleh pemegang kelulusan galakan selain seorang individu bagi penyerahhakan atau pemindahan hakmilik kelulusan galakannya 2500.00
Dibuat 10 Oktober 2013
[SEDA/LGL(S)RE/13-YY (5); PN(PU2)693/III]
DATUK DR. YEE MOH CHAI
Pengerusi
Pihak Berkuasa Pembangunan Tenaga Lestari Malaysia
P.U. (A) 312 5
RENEWABLE ENERGY ACT 2011
RENEWABLE ENERGY (FEED-IN APPROVAL AND FEED-IN TARIFF RATE) (AMENDMENT)
(NO. 2) RULES 2013
Opening note
These rules may be cited as the Renewable Energy (Feed-In Approval and
Feed-in Tariff Rate) (Amendment) (No. 2) Rules 2013.
These Rules are deemed to have come into operation on 28 March 2013.
Amendment of rule 19 2.
The Renewable Energy (Feed-in Approval and Feed-in Tariff Rate) Rules 2011
[P.U. (A) 385/2011], which are referred to as the “principal Rules” in these Rules, are amended in subrule 19(6) by deleting the words “and upon payment of the processing fee as prescribed in the Second Schedule,”.
Substitution of Second Schedule 3.
The principal Rules are amended by substituting for the Second Schedule the following Schedule:
“SECOND SCHEDULE
(Subrules 4(1), 4A(3), 13A(2), 16(2), 18(1), and rule 24)
FEES
Item
Type of fees
Amount of fees (RM)
Application form for feed-in approval—
00 per form
P.U. (A) 312 6
Item
Type of fees
Amount of fees (RM)
by an electronic medium or by way of an electronic transmission
Nil 2.
Application fee for feed-in approval 10.00 per kilowatt of the installed capacity
(subject to a minimum fee of
RM100.00)
Processing fee payable by an eligible producer who is an individual for the application for feed-in approval submitted—
00 per application
00 per application
Processing fee payable by an eligible producer other than an individual for the application for feed-in approval submitted—
00 per application
00 per application
Processing fee payable by an eligible producer who is an individual for an amendment to the particulars in his application for a feed-in approval 50.00 6.
Processing fee payable by an eligible producer other than an individual for an amendment to the particulars in its application for a feed-in approval 100.00 7.
Processing fee payable by a feed-in approval holder who is an individual for an amendment to his feed-in approval relating to—
00
00 8.
Processing fee payable by a feed-in approval holder other than an individual for an amendment to its feed-in approval relating to—
00
00
P.U. (A) 312 7
Item
Type of fees
Amount of fees (RM)
Application fee payable by a feed-in approval holder who is an individual for variation of the conditions of his feed-in approval 500.00 10.
Application fee payable by a feed-in approval holder other than an individual for variation of the conditions of its feed-in approval 2500.00 11.
Application fee for replacement feed-in approval 50.00 12.
Application fee payable by a feed-in approval holder who is an individual for an assignment or transfer of feed-in approval 500.00 13.
Application fee payable by a feed-in approval holder other than an individual for an assignment or transfer of feed-in approval 2500.00
Made 10 October 2013
[SEDA/LGL(S)RE/13-YY (5); PN(PU2)693/III]
DATUK DR. YEE MOH CHAI
Chairman
Sustainable Energy Development Authority Malaysia