/akn/my/act/pua/2013/271

PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013

The full official text, structured for quick navigation. Copy any provision or jump straight to a section.

Open source PDF
Type
P.U. (A)
Status
In force
Enacted
2013
Sections
5

Quick answer

About this p.u. (a)

PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013 is Malaysia P.U. (A), cited as P.U. (A) 271 2013, currently marked in force and first recorded in 2013.

Opening note

Preamble

Suggest a correction
  1. PADA menjalankan kuasa yang diberikan oleh subseksyen 55(3) Akta Kilang dan Jentera 1967 [Akta 139], Menteri membuat perintah yang berikut: Nama

Seksyen 1

Open as pageSuggest a correction

Perintah ini bolehlah dinamakan Perintah Kilang dan Jentera (Pengecualian kepada Petronas Gas Berhad, Centralised Utility Facilities, Gebeng, Pahang) 2013.

Seksyen 2

Pengecualian

Open as pageSuggest a correction

Semua jentera yang didaftarkan dengan Ketua Pemeriksa, dengan nombor pendaftaran dan perihalan yang dinyatakan dalam ruang (1) dan (2) Jadual, atas nama

Petronas Gas Berhad, Centralised Utility Facilities, Gebeng, Pahang yang telah dikeluarkan perakuan kelayakan, dikecualikan daripada persediaan yang dikehendaki di bawah perenggan 17(b) Peraturan-Peraturan (Pemberitahu, Perakuan Kelayakan dan

Pemeriksaan) Kilang dan Jentera 1970 [P.U. (A) 43/1970] bagi pemeriksaan ulangan yang berikutnya selepas habis tempoh perakuan kelayakan itu sebagaimana yang dinyatakan dalam ruang (3) Jadual.

Seksyen 3

Syarat pengecualian

Open as pageSuggest a correction

Pengecualian di bawah perenggan 2 tertakluk kepada syarat bahawa semua jentera yang dinyatakan dalam Jadual menjalani pemeriksaan luaran dan ujian tanpa musnah, dan Pemeriksa berpuas hati dengan keputusan pemeriksaan dan ujian itu.

P.U. (A) 271 3

Jadual

Suggest a correction

JADUAL

(1)

(2)

(3)

No. Pendaftaran

Perihalan Jentera

Tarikh Habis Tempoh

129218

Bejana tekanan tidak berapi 27 Disember 2012

129336

Bejana tekanan tidak berapi 27 Disember 2012

129337

Bejana tekanan tidak berapi 27 Disember 2012

129338

Bejana tekanan tidak berapi 27 Disember 2012

129755

Bejana tekanan tidak berapi 27 Disember 2012

129339

Bejana tekanan tidak berapi 27 Disember 2012

129340

Bejana tekanan tidak berapi 27 Disember 2012

129341

Bejana tekanan tidak berapi 27 Disember 2012

129342

Bejana tekanan tidak berapi 27 Disember 2012

129343

Bejana tekanan tidak berapi 27 Disember 2012

129756

Bejana tekanan tidak berapi 27 Disember 2012

129219

Bejana tekanan tidak berapi 27 Disember 2012

129757

Bejana tekanan tidak berapi 27 Disember 2012

129216

Bejana tekanan tidak berapi 27 Disember 2012

129758

Bejana tekanan tidak berapi 27 Disember 2012

129759

Bejana tekanan tidak berapi 27 Disember 2012

129760

Bejana tekanan tidak berapi 27 Disember 2012

129765

Bejana tekanan tidak berapi 27 Disember 2012

110770

Bejana tekanan tidak berapi 27 Disember 2012

110771

Bejana tekanan tidak berapi 27 Disember 2012

110772

Bejana tekanan tidak berapi 27 Disember 2012

54

Bejana tekanan tidak berapi 23 Jun 2013

55

Bejana tekanan tidak berapi 23 Jun 2013

56

Bejana tekanan tidak berapi 23 Jun 2013

57

Bejana tekanan tidak berapi 23 Jun 2013

58

Bejana tekanan tidak berapi 23 Jun 2013

59

Bejana tekanan tidak berapi 23 Jun 2013

61

Bejana tekanan tidak berapi 23 Jun 2013

P.U. (A) 271 4

(1)

(2)

(3)

No. Pendaftaran

Perihalan Jentera

Tarikh Habis Tempoh

62

Bejana tekanan tidak berapi 23 Jun 2013

63

Bejana tekanan tidak berapi 23 Jun 2013

64

Bejana tekanan tidak berapi 23 Jun 2013

65

Bejana tekanan tidak berapi 23 Jun 2013

66

Bejana tekanan tidak berapi 23 Jun 2013

67

Bejana tekanan tidak berapi 23 Jun 2013

68

Bejana tekanan tidak berapi 23 Jun 2013

69

Bejana tekanan tidak berapi 23 Jun 2013

70

Bejana tekanan tidak berapi 23 Jun 2013

71

Bejana tekanan tidak berapi 23 Jun 2013

72

Bejana tekanan tidak berapi 23 Jun 2013

73

Bejana tekanan tidak berapi 23 Jun 2013

74

Bejana tekanan tidak berapi 23 Jun 2013

75

Bejana tekanan tidak berapi 23 Jun 2013

76

Bejana tekanan tidak berapi 23 Jun 2013

78

Bejana tekanan tidak berapi 23 Jun 2013

79

Bejana tekanan tidak berapi 23 Jun 2013

80

Bejana tekanan tidak berapi 23 Jun 2013

81

Bejana tekanan tidak berapi 23 Jun 2013

Dibuat 20 Ogos 2013

[KSM/PUU/T/01/02/03 Jld.22; PN(PU2)235/XXXVII]

DATUK RICHARD RIOT ANAK JAEM

Menteri Sumber Manusia

P.U. (A) 271 5

FACTORIES AND MACHINERY ACT 1967

FACTORIES AND MACHINERY (EXEMPTION TO PETRONAS GAS BERHAD,

CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) ORDER 2013

IN exercise of the powers conferred by subsection 55(3) of the Factories and Machinery

Act 1967 [Act 139], the Minister makes the following order:

Citation 1.

This order may be cited as the Factories and Machinery (Exemption to

Petronas Gas Berhad, Centralised Utility Facilities, Gebeng, Pahang) Order 2013.

Exemption 2.

All machinery registered with the Chief Inspector, with the registration number and description as specified in columns (1) and (2) of the Schedule, in the name of

Petronas Gas Berhad, Centralised Utility Facilities, Gebeng, Pahang which have been issued with certificates of fitness, are exempted from the preparation required under paragraph 17(b) of the Factories and Machinery (Notification, Certificate of Fitness and

Inspection) Regulations 1970 [P.U. (A) 43/1970] for subsequent regular inspection after the expiry of such certificates of fitness as specified in column (3) of the Schedule.

Condition of exemption 3.

The exemption under paragraph 2 is subject to the conditions that all of the machinery as specified in the Schedule undergo an external inspection and non-destructive tests, and the Inspector is satisfied with the result of such inspection and tests.

P.U. (A) 271 6

Jadual

Suggest a correction

(1)

(2)

(3)

Registration No.

Description of Machinery

Expiry Date

129218

Unfired pressure vessel 27 December 2012

129336

Unfired pressure vessel 27 December 2012

129337

Unfired pressure vessel 27 December 2012

129338

Unfired pressure vessel 27 December 2012

129755

Unfired pressure vessel 27 December 2012

129339

Unfired pressure vessel 27 December 2012

129340

Unfired pressure vessel 27 December 2012

129341

Unfired pressure vessel 27 December 2012

129342

Unfired pressure vessel 27 December 2012

129343

Unfired pressure vessel 27 December 2012

129756

Unfired pressure vessel 27 December 2012

129219

Unfired pressure vessel 27 December 2012

129757

Unfired pressure vessel 27 December 2012

129216

Unfired pressure vessel 27 December 2012

129758

Unfired pressure vessel 27 December 2012

129759

Unfired pressure vessel 27 December 2012

129760

Unfired pressure vessel 27 December 2012

129765

Unfired pressure vessel 27 December 2012

110770

Unfired pressure vessel 27 December 2012

110771

Unfired pressure vessel 27 December 2012

110772

Unfired pressure vessel 27 December 2012

54

Unfired pressure vessel 23 June 2013

55

Unfired pressure vessel 23 June 2013

56

Unfired pressure vessel 23 June 2013

57

Unfired pressure vessel 23 June 2013

58

Unfired pressure vessel 23 June 2013

59

Unfired pressure vessel 23 June 2013

61

Unfired pressure vessel 23 June 2013

P.U. (A) 271 7

(1)

(2)

(3)

Registration No.

Description of Machinery

Expiry Date

62

Unfired pressure vessel 23 June 2013

63

Unfired pressure vessel 23 June 2013

64

Unfired pressure vessel 23 June 2013

65

Unfired pressure vessel 23 June 2013

66

Unfired pressure vessel 23 June 2013

67

Unfired pressure vessel 23 June 2013

68

Unfired pressure vessel 23 June 2013

69

Unfired pressure vessel 23 June 2013

70

Unfired pressure vessel 23 June 2013

71

Unfired pressure vessel 23 June 2013

72

Unfired pressure vessel 23 June 2013

73

Unfired pressure vessel 23 June 2013

74

Unfired pressure vessel 23 June 2013

75

Unfired pressure vessel 23 June 2013

76

Unfired pressure vessel 23 June 2013

78

Unfired pressure vessel 23 June 2013

79

Unfired pressure vessel 23 June 2013

80

Unfired pressure vessel 23 June 2013

81

Unfired pressure vessel 23 June 2013

Made 20 August 2013

[KSM/PUU/T/01/02/03 Jld.22; PN(PU2)235/XXXVII]

DATUK RICHARD RIOT ANAK JAEM

Minister of Human Resources

Common questions

What is PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013?
PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013 is Malaysia P.U. (A), cited as P.U. (A) 271 2013, currently marked in force and first recorded in 2013.
Is PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013 still in force?
Yes — PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013 is currently in force.
When did PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013 take effect?
PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013 was first recorded in 2013.
How many sections does PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013 have?
PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013 contains 3 sections.
Where can I read the official version of PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013?
The official text of PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013 is published at lom.agc.gov.my.
PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, GEBENG, PAHANG) 2013 (No. 271)