Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian) (Pungutan Tol) (Lebuh Raya Shah Alam) (Pindaan) 2013 is Malaysia P.U. (A), cited as P.U. (A) 9 2013, currently marked in force and first recorded in 2013.

Front matterCover and publication detailsOpen

P.U. (A) 9

WARTA KERAJAAN PERSEKUTUAN

FEDERAL GOVERNMENT

GAZETTE

PERINTAH JALAN-JALAN PERSEKUTUAN (PENGURUSAN

PERSENDIRIAN)(PUNGUTAN TOL) (LEBUH RAYA SHAH

ALAM)(PINDAAN) 2013

FEDERAL ROADS (PRIVATE MANAGEMENT) (COLLECTION

OF TOLLS)(SHAH ALAM EXPRESSWAY) (AMENDMENT)

ORDER 2013

DISIARKAN OLEH/

JABATAN PEGUAM NEGARA/

ATTORNEY GENERAL’S CHAMBERS

P.U. (A) 9 2

AKTA JALAN-JALAN PERSEKUTUAN (PENGURUSAN PERSENDIRIAN) 1984

PERINTAH JALAN-JALAN PERSEKUTUAN (PENGURUSAN PERSENDIRIAN) (PUNGUTAN

TOL) (LEBUH RAYA SHAH ALAM) (PINDAAN) 2013

Opening note

Preamble

  1. PADA menjalankan kuasa yang diberikan oleh seksyen 2 Akta Jalan-Jalan Persekutuan (Pengurusan Persendirian) 1984 [Akta 306], Menteri membuat perintah yang berikut: Nama dan permulaan kuat kuasa

Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian)(Pungutan Tol)

(Lebuh Raya Shah Alam) 1999 [P.U. (A) 69/1999], yang disebut “Perintah ibu” dalam

Perintah ini, dipinda dalam subperenggan 2(1)—

(a)

dengan menggantikan perkataan “ruang (2) Bahagian I hingga III Jadual

Pertama” dengan perkataan “ruang (2) Bahagian I hingga IV Jadual Pertama” ;

dan

(b)

dengan menggantikan perkataan “ruang (1) Bahagian I hingga III” dengan perkataan “ruang (1) Bahagian I hingga IV”.

Pindaan Jadual Pertama

Perintah ibu dipinda dengan menggantikan Jadual Pertama dengan Jadual yang berikut:

P.U. (A) 9 3

“JADUAL PERTAMA

[subperenggan 2(1)]

Bahagian I

KADAR TOL BAGI TEMPOH KONSESI DARI 1 JANUARI 2007 HINGGA 14 JANUARI 2013

Seksyen 3

Kenderaan yang mempunyai dua gandar dan lima atau enam roda (kecuali bas)

30 3.30 3.30 3.30 3.

Kenderaan yang mempunyai tiga gandar atau lebih (kecuali bas)

40 4.40 4.40 4.40 4.

Teksi 1.10 1.10 1.10 1.10

(2)

Tol Kena Dibayar

Plaza Tol

Awan

Besar

Barat

Plaza Tol

Awan Besar

Timur

Plaza Tol

Sunway

Plaza Tol

Kemuning 1.

Kenderaan yang mempunyai dua gandar dan tiga atau empat roda (kecuali teksi dan bas)

Bahagian II

KADAR TOL BAGI TEMPOH KONSESI DARI 15 JANUARI 2013 HINGGA 31 DISEMBER 2015

Seksyen 2

Kenderaan yang mempunyai dua gandar dan lima atau enam roda (kecuali bas)

Seksyen 4

Kenderaan yang mempunyai tiga gandar atau lebih (kecuali bas)

00 4.00 4.00 4.00 4.

Teksi 1.00 1.00 1.00 1.00 5.

Bas 1.50 1.50 1.50 1.50

(2)

Tol Kena Dibayar

Plaza Tol

Awan

Besar

Barat

Plaza Tol

Awan Besar

Timur

Plaza Tol

Sunway

Plaza Tol

Kemuning 1.

Kenderaan yang mempunyai dua gandar dan tiga atau empat roda (kecuali teksi dan bas)

Bahagian III

KADAR TOL BAGI TEMPOH KONSESI DARI 1 JANUARI 2016 HINGGA 31 DISEMBER 2020

Seksyen 1

Kenderaan yang mempunyai dua gandar dan tiga atau empat roda (kecuali teksi dan bas)

Seksyen 2

Kenderaan yang mempunyai dua gandar dan lima atau enam roda (kecuali bas)

Seksyen 3

Kenderaan yang mempunyai tiga gandar atau lebih (kecuali bas)

(2)

Tol Kena Dibayar

Plaza Tol

Awan

Besar

Barat

Plaza Tol

Awan

Besar

Timur

Plaza Tol

Sunway

Plaza Tol

Kemuning

Bahagian IV

KADAR TOL BAGI TEMPOH KONSESI DARI 1 JANUARI 2021 HINGGA 18 OGOS 2023

Seksyen 4

Kenderaan yang mempunyai dua gandar dan lima atau enam roda (kecuali bas)

50 4.50 4.50 4.50 3.

Kenderaan yang mempunyai tiga gandar atau lebih (kecuali bas)

00 6.00 6.00 6.00 4.

Teksi 1.50 1.50 1.50 1.50 5.

Bas 2.20 2.20 2.20 2.20

Bagi maksud mengira bilangan gandar dan roda sesuatu kenderaan, gandar dan roda mana-mana treler yang ditarik oleh kenderaan itu hendaklah termasuk sebagai sebahagian daripada gandar dan roda kenderaan itu.”.

Dibuat 14 Januari 2013

[KKR. PUU.110-1/7/7; PN(PU2)426/LI]

DATO’ SERI SHAZIMAN BIN ABU MANSOR

Menteri Kerja Raya

P.U. (A) 9 6

FEDERAL ROADS (PRIVATE MANAGEMENT) ACT 1984

FEDERAL ROADS (PRIVATE MANAGEMENT) (COLLECTION OF TOLLS) (SHAH ALAM

EXPRESSWAY) (AMENDMENT) ORDER 2013

(2)

Tol Kena Dibayar

Plaza Tol

Awan

Besar

Barat

Plaza Tol

Awan

Besar

Timur

Plaza Tol

Sunway

Plaza Tol

Kemuning 1.

Kenderaan yang mempunyai dua gandar dan tiga atau empat roda (kecuali teksi dan bas)

Opening note

Preamble

  1. IN exercise of the powers conferred by section 2 of the Federal Roads (Private Management) Act 1984 [Act 306], the Minister makes the following order: Citation and commencement 1.

(1)

This order may be cited as the Federal Roads (Private Management)

(Collection of Tolls) (Shah Alam Expressway) (Amendment) Order 2013.

(2)

This Order comes into operation on 15 January 2013.

Amendment of paragraph 2 2.

The Federal Roads (Private Management) (Collection of Tolls) (Shah Alam

Expressway) Order 1999 [P.U. (A) 69/1999], which is referred to as the “principal

Order” in this Order, is amended in subparagraph 2(1)—

(a)

by substituting for the words “column (2) of Parts I to III of the First

Schedule” the words “column (2) of Parts I to IV of the First Schedule”; and

(b)

by substituting for the words “column (1) of Parts I to III” the words “column

(1)

of part I to IV”.

Amendment of First Schedule 3.

The principle Order is amended by substituting for the First Schedule the following Schedule:

P.U. (A) 9 7

“FIRST SCHEDULE

[subparagraph 2(1)]

Bahagian I

PART I

RATES OF TOLL FOR THE CONCESSION PERIOD FROM 1 JANUARY 2007 UNTIL

14 JANUARY 2013

Seksyen 3

Vehicles having two axles and five or six wheels (excluding buses)

30 3.30 3.30 3.30 3.

Seksyen 4

Vehicles having three axles or more (excluding buses)

40 4.40 4.40 4.40 4.

Taxis 1.10 1.10 1.10 1.10 5.

Buses 1.70 1.70 1.70 1.70

(2)

Toll Payable

Awan

Besar West

Toll Plaza

Awan

Besar East

Toll Plaza

Sunway

Plaza Toll

Kemuning

Plaza Toll 1.

Vehicles having two axles and three or four wheels

(excluding taxis and buses)

Bahagian II

PART II

RATES OF TOLL FOR THE CONCESSION PERIOD FROM 15 JANUARY 2013 UNTIL

31 DECEMBER 2015

Seksyen 3

Vehicles having two axles and five or six wheels (excluding buses)

00 3.00 3.00 3.00 3.

Vehicles having three axles or 4.00 4.00 4.00 4.00

P.U. (A) 9 8

more (excluding buses)

Seksyen 4

Taxis 1.00 1.00 1.00 1.00 5.

Buses 1.50 1.50 1.50 1.50

(2)

Toll Payable

Awan

Besar West

Toll Plaza

Awan

Besar East

Toll Plaza

Sunway

Plaza Toll

Kemuning

Plaza Toll 1.

Vehicles having two axles and three or four wheels

(excluding taxis and buses)

Bahagian III

PART III

RATES OF TOLL FOR THE CONCESSION PERIOD FROM 1 JANUARY 2016 UNTIL

31 DECEMBER 2020

Seksyen 3

Vehicles having two axles and five or six wheels (excluding buses)

70 3.70 3.70 3.70 3.

Vehicles having three axles or more (excluding buses)

Seksyen 5

00 5.00 5.00 5.00 4.

Taxis 1.20 1.20 1.20 1.20 5.

Buses 1.90 1.90 1.90 1.90

(2)

Toll Payable

Awan

Besar West

Toll Plaza

Awan

Besar East

Toll Plaza

Sunway

Plaza Toll

Kemuning

Plaza Toll 1.

Vehicles having two axles and three or four wheels

(excluding taxis and buses)

Bahagian IV

PART IV

RATES OF TOLL FOR THE CONCESSION PERIOD FROM 1 JANUARY 2021 UNTIL

18 AUGUST 2023

Seksyen 2

Vehicles having two axles and five or six wheels

(excluding buses)

Seksyen 4

50 4.50 4.50 4.50 3.

Vehicles having three axles or more (excluding buses)

Seksyen 6

00 6.00 6.00 6.00 4.

Taxis 1.50 1.50 1.50 1.50 5.

Buses 2.20 2.20 2.20 2.20

For the purpose of calculating the number of axles and wheels of a vehicle, the axles and wheels of any trailer towed by the vehicle shall be included as part of the axles and wheels of the vehicle.”.

Made 14 January 2013

[KKR. PUU.110-1/7/7; PN(PU2)426/LI]

DATO’ SERI SHAZIMAN BIN ABU MANSOR

Minister of Works

(2)

Toll Payable

Awan

Besar

West Toll

Plaza

Awan

Besar

East Toll

Plaza

Sunway

Plaza Toll

Kemuning Plaza

Toll 1.

Vehicles having two axles and three or four wheels

(excluding taxis and buses)

Common questions

What is Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian) (Pungutan Tol) (Lebuh Raya Shah Alam) (Pindaan) 2013?
Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian) (Pungutan Tol) (Lebuh Raya Shah Alam) (Pindaan) 2013 is Malaysia P.U. (A), cited as P.U. (A) 9 2013, currently marked in force and first recorded in 2013.
Is Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian) (Pungutan Tol) (Lebuh Raya Shah Alam) (Pindaan) 2013 still in force?
Yes — Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian) (Pungutan Tol) (Lebuh Raya Shah Alam) (Pindaan) 2013 is currently in force.
When did Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian) (Pungutan Tol) (Lebuh Raya Shah Alam) (Pindaan) 2013 take effect?
Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian) (Pungutan Tol) (Lebuh Raya Shah Alam) (Pindaan) 2013 was first recorded in 2013.
How many sections does Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian) (Pungutan Tol) (Lebuh Raya Shah Alam) (Pindaan) 2013 have?
Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian) (Pungutan Tol) (Lebuh Raya Shah Alam) (Pindaan) 2013 contains 33 sections.
Where can I read the official version of Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian) (Pungutan Tol) (Lebuh Raya Shah Alam) (Pindaan) 2013?
The official text of Perintah Jalan-Jalan Persekutuan (Pengurusan Persendirian) (Pungutan Tol) (Lebuh Raya Shah Alam) (Pindaan) 2013 is published at lom.agc.gov.my.

Something wrong on this page?

If one provision's text doesn't match the official source, use Suggest a fix beside that provision — it opens an editor next to the source document. For anything else — a missing amendment, a broken link, out-of-date content, or a removal request — report it here.