Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013
The full official text, structured for quick navigation. Copy any provision or jump straight to a section.
- Enacted
- 2013
- Sections
- 2
Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013 is Malaysia P.U. (A), cited as P.U. (A) 108 2013, currently marked in force and first recorded in 2013.
Front matterCover and publication detailsOpenClose
P.U. (A) 108
WARTA KERAJAAN PERSEKUTUAN
FEDERAL GOVERNMENT
GAZETTE
PERINTAH TENAGA BOLEH BAHARU
(PINDAAN JADUAL) 2013
RENEWABLE ENERGY (AMENDMENT OF SCHEDULE)
ORDER 2013
DISIARKAN OLEH/
JABATAN PEGUAM NEGARA/
ATTORNEY GENERAL’S CHAMBERS
P.U. (A) 108 2
AKTA TENAGA BOLEH BAHARU 2011
PERINTAH TENAGA BOLEH BAHARU (PINDAAN JADUAL) 2013
Opening note
Preamble
- PADA menjalankan kuasa yang diberikan oleh seksyen 63 Akta Tenaga Boleh Baharu 2011 [Akta 725], Menteri membuat perintah yang berikut: Nama dan permulaan kuat kuasa
Seksyen 2
Jadual kepada Akta 725 dipinda berkenaan dengan Sumber Boleh Baharu
Fotovolta Suria dalam Ruang Pertama
(a)
dengan menggantikan perkataan “8” dalam Ruang Kelima yang bertentangan dengan subperenggan (a)(iii),(iv),(v) dan (vi) dalam Ruang
Kedua perkataan “20”; dan
(b)
dengan menggantikan perkataan “8” dalam Ruang Kelima yang bertentangan dengan subperenggan (b)(iii) dan (iv) dalam Ruang Kedua perkataan “0”.
Dibuat 20 Mac 2013
[KeTTHA:BP(S)9/14 Klt. 4(38); PN(PU2)693/IV]
DATO’ SRI PETER CHIN FAH KUI
Menteri Tenaga, Teknologi Hijau dan Air
P.U. (A) 108 3
RENEWABLE ENERGY ACT 2011
RENEWABLE ENERGY (AMENDMENT OF SCHEDULE) ORDER 2013
Opening note
Preamble
- IN exercise of the powers conferred by section 63 of the Renewable Energy Act 2011 [Act 725], the Minister makes the following order: Citation and commencement 1.
(2)
This Order comes into operation on 28 March 2013.
Amendment of Schedule 2.
The Schedule to Act 725 is amended in respect of Renewable Resource Solar
Photovoltaic in the First Column
(a)
by substituting for the word “8” in the Fifth Column appearing against subparagraphs (a)(iii),(iv),(v) and (vi) in the Second Column the word
“20”; and
(b)
by substituting for the word “8” in the Fifth Column appearing against subparagraphs (b)(iii) and (iv) in the Second Column the word “0”.
Made 20 March 2013
[KeTTHA:BP(S)9/14 Klt. 4(38); PN(PU2)693/IV]
DATO’ SRI PETER CHIN FAH KUI
Minister of Energy, Green Technology and Water
Common questions
- What is Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013?
- Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013 is Malaysia P.U. (A), cited as P.U. (A) 108 2013, currently marked in force and first recorded in 2013.
- Is Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013 still in force?
- Yes — Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013 is currently in force.
- When did Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013 take effect?
- Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013 was first recorded in 2013.
- How many sections does Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013 have?
- Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013 contains 2 sections.
- Where can I read the official version of Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013?
- The official text of Perintah Tenaga Boleh Baharu (Pindaan Jadual) 2013 is published at lom.agc.gov.my.
Something wrong on this page?
If one provision's text doesn't match the official source, use Suggest a fix beside that provision — it opens an editor next to the source document. For anything else — a missing amendment, a broken link, out-of-date content, or a removal request — report it here.