Penetapan Tarikh Permulaan Kuat Kuasa

The text

29 Jun 2026 29 June 2026

P.U. (B) 220

WARTA KERAJAAN PERSEKUTUAN

FEDERAL GOVERNMENT

GAZETTE

PENETAPAN TARIKH PERMULAAN KUAT KUASA

APPOINTMENT OF DATE OF COMING INTO OPERATION

DISIARKAN OLEH/

JABATAN PEGUAM NEGARA/

ATTORNEY GENERAL’S CHAMBERS

P.U. (B) 220 2

AKTA BEKALAN ELEKTRIK (PINDAAN) 2025

PENETAPAN TARIKH PERMULAAN KUAT KUASA

Preamble

PADA menjalankan kuasa yang diberikan oleh subseksyen 1(2) Akta Bekalan Elektrik

(Pindaan) 2025 [Akta A1775], Menteri menetapkan 1 Julai 2026 sebagai tarikh Akta itu mula berkuat kuasa.

Bertarikh 23 Jun 2026

[PETRA.BBE.100-1/1/2 Jld.3(S); PN(U2)3363]

DATUK AMAR HAJI FADILLAH BIN HAJI YUSOF

Menteri Peralihan Tenaga dan Transformasi Air

ELECTRICITY SUPPLY (AMENDMENT) ACT 2025

APPOINTMENT OF DATE OF COMING INTO OPERATION

Preamble

IN exercise of the powers conferred by subsection 1(2) of the Electricity Supply

(Amendment) Act 2025 [Act A1775], the Minister appoints 1 July 2026 as the date on which the Act comes into operation.

Dated 23 June 2026

[PETRA.BBE.100-1/1/2 Jld.3(S); PN(U2)3363]

DATUK AMAR HAJI FADILLAH BIN HAJI YUSOF