Seksyen 1
(1)
Peraturan-peraturan ini bolehlah dinamakan Peraturan-Peraturan
(Dandang Stim dan Pengandung Tekanan Tidak Berapi) Kilang dan Jentera
(Pindaan) 2014.
The full official text, structured for quick navigation. Copy any provision or jump straight to a section.
Peraturan-Peraturan (Dandang Stim dan Pengandung Tekanan Tidak Berapi) Kilang dan Jentera (Pindaan) 2014 is Malaysia P.U. (A), cited as P.U. (A) 40 2014, currently marked in force and first recorded in 2014.
P.U. (A) 40
WARTA KERAJAAN PERSEKUTUAN
FEDERAL GOVERNMENT
GAZETTE
PERATURAN-PERATURAN (DANDANG STIM DAN
PENGANDUNG TEKANAN TIDAK BERAPI) KILANG
DAN JENTERA (PINDAAN) 2014
FACTORIES AND MACHINERY (STEAM BOILER
AND UNFIRED PRESSURE VESSEL) (AMENDMENT)
REGULATIONS 2014
DISIARKAN OLEH/
JABATAN PEGUAM NEGARA/
ATTORNEY GENERAL’S CHAMBERS
P.U. (A) 40 2
AKTA KILANG DAN JENTERA 1967
PERATURAN-PERATURAN (DANDANG STIM DAN PENGANDUNG TEKANAN
TIDAK BERAPI) KILANG DAN JENTERA (PINDAAN) 2014
Opening note
Peraturan-peraturan ini bolehlah dinamakan Peraturan-Peraturan
(Dandang Stim dan Pengandung Tekanan Tidak Berapi) Kilang dan Jentera
(Pindaan) 2014.
Pindaan Jadual Keempat
Jadual Keempat Peraturan-Peraturan (Dandang Stim dan Pengandung Tekanan
Tidak Berapi) Kilang dan Jentera 1970 [P.U. (A) 5/1970] dipinda dengan memasukkan selepas butiran 40 butiran yang berikut:
“41. Japan Inspection Co. Ltd., Tokyo. ”.
Dibuat 29 Januari 2014
[KSM/PUU/(S)/600-1/2/8/10/1; PN(PU2)235/XXXIX]
DATO’ SRI RICHARD RIOT ANAK JAEM
Menteri Sumber Manusia
P.U. (A) 40 3
FACTORIES AND MACHINERY ACT 1967
FACTORIES AND MACHINERY (STEAM BOILER AND UNFIRED PRESSURE VESSEL)
(AMENDMENT) REGULATIONS 2014
IN exercise of the powers conferred by subsection 56(1) of the Factories and Machinery
Act 1967 [Act 139], the Minister makes the following regulations:
Citation and commencement 1.
(1)
These regulations may be cited as the Factories and Machinery
(Steam Boiler and Unfired Pressure Vessel) (Amendment) Regulations 2014.
(2)
These Regulations come into operation on 4 February 2014.
Amendment of Fourth Schedule 2.
The Fourth Schedule of the Factories and Machinery (Steam Boiler and Unfired
Pressure Vessel) Regulations 1970 [P.U. (A) 5/1970] is amended by inserting after item 40 the following item:
“41. Japan Inspection Co. Ltd., Tokyo. ”.
Made 29 January 2014
[KSM/PUU/(S)/600-1/2/8/10/1; PN(PU2)235/XXXIX]
DATO’ SRI RICHARD RIOT ANAK JAEM
Minister of Human Resources
If one provision's text doesn't match the official source, use Suggest a fix beside that provision — it opens an editor next to the source document. For anything else — a missing amendment, a broken link, out-of-date content, or a removal request — report it here.