Seksyen 1
(1)
Perintah ini bolehlah dinamakan Perintah Tenaga Boleh Baharu
(Pindaan Jadual) 2019.
/akn/my/act/pua/2019/20
The full official text, structured for quick navigation. Copy any provision or jump straight to a section.
Quick answer
PERINTAH TENAGA BOLEH BAHARU (PINDAAN JADUAL) 2019 is Malaysia P.U. (A), cited as P.U. (A) 20 2019, currently marked in force and first recorded in 2019.
Opening note
Perintah ini bolehlah dinamakan Perintah Tenaga Boleh Baharu
(Pindaan Jadual) 2019.
Jadual kepada Akta Tenaga Boleh Baharu 2011 dipinda berhubung dengan sumber boleh baharu “Biogas”, dengan menggantikan butiran (a) dan butir-butir yang berhubungan dengannya dengan butiran dan butir-butir yang berikut:
Ruang
Pertama
Ruang
Kedua
Ruang
Ketiga
Ruang
Keempat
Ruang
Kelima
Sumber boleh baharu
Perihalan pepasangan tenaga boleh baharu yang layak
Kadar tarif galakan
(dalam ringgit bagi setiap kilowatt jam)
Tempoh berkuat kuasa
(bermula dari tarikh permulaan kuat kuasa tarif galakan)
Kadar pengurangan tahunan
Biogas
“(a) Pepasangan tenaga boleh baharu yang mempunyai kapasiti terpasang sehingga dan termasuk 5 megawatt
Kadar tarif galakan asas
221-0.2814
21 tahun
0%”.
P.U. (A) 20 3
Dibuat 24 Januari 2019
[MESTECC.700-1/2/5; PN(PU2)693/VI]
YEO BEE YIN
Menteri Tenaga, Sains, Teknologi, Alam Sekitar dan Perubahan Iklim
P.U. (A) 20 4
RENEWABLE ENERGY ACT 2011
RENEWABLE ENERGY (AMENDMENT OF SCHEDULE) ORDER 2019
Opening note
This order may be cited as the
Renewable
Energy
(Amendment of Schedule) Order 2019.
This Order comes into operation on 28 January 2019.
Amendment of Schedule 2.
The Schedule to the Renewable Energy Act 2011 is amended in relation to the renewable resource “Biogas”, by substituting for item (a) and the particulars relating to it the following item and particulars:
First
Column
Second
Column
Third
Column
Fourth
Column
Fifth
Column
Renewable resource
Description of qualifying renewable energy installation
Feed-in tariff rate (in ringgit per kilowatt hour)
Effective period
(commencing from the feed-in tariff commenceme nt date)
Annual degression rate
Biogas
“(a) Renewable energy installation having an installed capacity of up to and including 5 megawatts
Basic feed-in tariff rate
2210–0.2814
21 years
0%”.
P.U. (A) 20 5
Made 24 January 2019
[MESTECC.700-1/2/5; PN(PU2)693/VI]
YEO BEE YIN
Minister of Energy, Science, Technology, Environment and Climate Change