In these Rules, unless the context otherwise requires —

“acceptance test report” means a report prepared by a qualified person under rule 14 of the Sabah Renewable Energy (Technical and Operational Requirements)

Rules 2024;

“application”, in relation to an application for a feed-in approval, means an application which has fulfilled all applicable requirements under Part II of the

Sabah Renewable Energy (Technical and Operational Requirements) Rules 2024;

“associate”, in relation to a distribution licensee, means —

(a)

a person holding, directly or indirectly, more than forty-nine per centum of the voting power or issued share capital (excluding preference shares)

of the distribution licensee;

5

(b)

a company, in which the distribution licensee holds, directly or indirectly, more than forty-nine per centum of the voting power or issued share capital (excluding preference shares); or

(c)

a company, in which a third person holds, directly or indirectly, more than forty-nine per centum of the voting power or issued share capital

(excluding preference shares) of the company and such third person also holds more than forty-nine per centum of the voting power or issued share capital (excluding preference shares) in the distribution licensee;

“basic feed-in tariff rate” means —

(a)

in relation to a renewable energy installation utilizing biogas, biomass or solar photovoltaic as its renewable resource, the basic feed-in tariff rate as set out in row (a) of the third column of the Schedule to the

Enactment; and

(b)

in relation to a renewable energy installation utilizing small hydropower or geothermal as its renewable resource, the basic feed-in tariff rate as set out in the third column of the Schedule to the Enactment, and as reduced progressively under section 19 of the Enactment;

“bonus feed-in tariff rate”, in relation to a renewable energy installation utilizing biogas, biomass or solar photovoltaic as its renewable resource, means the bonus feed-in tariff rate as set out in row (b) of the third column of the Schedule to the Enactment and as reduced progressively under section 19 of the Enactment;

“buildings” means roofed building structures which can be independently used and entered into by human beings and are primarily designed for the purpose of sheltering human beings, animals or objects from the external environment;

“connection point” has the meaning assigned to it in rule 2 of the Sabah

Renewable Energy (Technical and Operational Requirements) Rules 2024;

“foreign company” has the meaning assigned to it in the Companies Act 2016

[Act 777];

“initial operation date” has the meaning assigned to it in rule 2 of the Sabah

Renewable Energy (Technical and Operational Requirements) Rules 2024;

“interconnection cables” means the cables or lines for transporting electricity from a renewable energy installation to a connection point;

6

“milestone” means a significant stage or event in the development of a renewable energy installation;

“qualified person” has the meaning assigned to it in rule 2 of the Sabah

Renewable Energy (Technical and Operational Requirements) Rules 2024; and

“revenue meter” has the meaning assigned to it in rule 2 of the Sabah Renewable