Section 14E

Defect liability period

of Temporary Measures Reducing Impact Coronavirus Disease 2019 Covid 19 Enactment 2020

State EnactmentIn forceProvision 19 of 31
Section 14E
(1)

Notwithstanding any agreement entered into between a purchaser and a developer, in relation to any housing development, the period from 1 April 2021 to 31

March 2022 shall be excluded from the calculation of –

(a)

The defect liability period after the date purchaser takes vacant possession of a housing accommodation; and

(b)

The time for the developer to carry out works to repair and make good any defect, shrinkages and other faults in a housing accommodation.

12

(2)

Subsection (1) applies only to a purchaser and a developer of a housing development for which its first agreement was entered into before 28 May 2021.