Perintah Tenaga Boleh Baharu (Pindaan Jadual) (No. 2) 2019 is Malaysia P.U. (A), cited as P.U. (A) 103 2019, currently marked in force and first recorded in 2019.

Front matterCover and publication detailsOpen

P.U. (A) 103

WARTA KERAJAAN PERSEKUTUAN

FEDERAL GOVERNMENT

GAZETTE

PERINTAH TENAGA BOLEH BAHARU

(PINDAAN JADUAL) (NO. 2) 2019

RENEWABLE ENERGY

(AMENDMENT OF SCHEDULE) (NO. 2) ORDER 2019

DISIARKAN OLEH/

JABATAN PEGUAM NEGARA/

ATTORNEY GENERAL’S CHAMBERS

P.U. (A) 103 2

AKTA TENAGA BOLEH BAHARU 2011

PERINTAH TENAGA BOLEH BAHARU (PINDAAN JADUAL) (NO. 2) 2019

Opening note

Preamble

  1. PADA menjalankan kuasa yang diberikan oleh seksyen 63 Akta Tenaga Boleh Baharu 2011 [Akta 725], Menteri membuat perintah yang berikut: Nama

Pindaan Jadual

Jadual kepada Akta Tenaga Boleh Baharu 2011 dipinda berhubung dengan sumber boleh baharu “Biojisim”, berhubung dengan subbutiran (b)(iv), dalam

Ruang Ketiga, dengan menggantikan perkataan “+ 0.0982” dengan perkataan “0”.

Dibuat 29 Mac 2019

[MESTECC: 700-1/2/5; PN(PU2)693/VI]

YEO BEE YIN

Menteri Tenaga, Sains, Teknologi, Alam Sekitar dan Perubahan Iklim

P.U. (A) 103 3

RENEWABLE ENERGY ACT 2011

RENEWABLE ENERGY (AMENDMENT OF SCHEDULE) (NO. 2) ORDER 2019

Opening note

Preamble

  1. IN exercise of the powers conferred by section 63 of the Renewable Energy Act 2011 [Act 725], the Minister makes the following order: Citation 1. This order may be cited as the Renewable Energy (Amendment of Schedule) (No. 2) Order 2019. Amendment of Schedule 2. The Schedule to the Renewable Energy Act 2011 is amended in relation to the renewable resource “Biomass”, in relation to subitem (b)(iv), in the Third Column, by substituting for the words “+ 0.0982” the word “0”. Made 29 March 2019 [MESTECC: 700-1/2/5; PN(PU2)693/VI] YEO BEE YIN Minister of Energy, Science, Technology, Environment and Climate Change

Common questions

What is Perintah Tenaga Boleh Baharu (Pindaan Jadual) (No. 2) 2019?
Perintah Tenaga Boleh Baharu (Pindaan Jadual) (No. 2) 2019 is Malaysia P.U. (A), cited as P.U. (A) 103 2019, currently marked in force and first recorded in 2019.
Is Perintah Tenaga Boleh Baharu (Pindaan Jadual) (No. 2) 2019 still in force?
Yes — Perintah Tenaga Boleh Baharu (Pindaan Jadual) (No. 2) 2019 is currently in force.
When did Perintah Tenaga Boleh Baharu (Pindaan Jadual) (No. 2) 2019 take effect?
Perintah Tenaga Boleh Baharu (Pindaan Jadual) (No. 2) 2019 was first recorded in 2019.
How many sections does Perintah Tenaga Boleh Baharu (Pindaan Jadual) (No. 2) 2019 have?
Perintah Tenaga Boleh Baharu (Pindaan Jadual) (No. 2) 2019 contains 2 sections.
Where can I read the official version of Perintah Tenaga Boleh Baharu (Pindaan Jadual) (No. 2) 2019?
The official text of Perintah Tenaga Boleh Baharu (Pindaan Jadual) (No. 2) 2019 is published at lom.agc.gov.my.

Something wrong on this page?

If one provision's text doesn't match the official source, use Suggest a fix beside that provision — it opens an editor next to the source document. For anything else — a missing amendment, a broken link, out-of-date content, or a removal request — report it here.