16. Payment and duration of feed-in tariff

(1)

Subject to paragraph 21(3)(a), a feed-in approval holder shall, during the effective period, be paid the feed-in tariff by the distribution licensee with whom the feed-in approval holder has entered into a renewable energy power purchase agreement for renewable energy generated by his or its renewable energy installation based on the applicable feed-in tariff rate as adjusted under section 18.

(2)

The Authority may prescribe rules setting out the criteria to be met by a renewable energy installation for the purposes of ascertaining the eligibility of a feed-in approval holder to receive a particular feed-in tariff rate.