Part III · Adjudicator

25. Powers of the adjudicator

Feedback & support

The adjudicator shall have the powers to—

(a)

establish the procedures in conducting the adjudication proceedings including limiting the submission of documents by the parties;

(b)

order the discovery and production of documents;

(c)

set deadlines for the production of documents;

(d)

draw on his own knowledge and expertise;

(e)

appoint independent experts to inquire and report on specific matters with the consent of the parties;

(f)

call for meetings with the parties;

(g)

conduct any hearing and limiting the hearing time;

(h)

carry out inspection of the site, work, material or goods relating to the dispute including opening up any work done;

(i)

inquisitorially take the initiative to ascertain the facts and the law required for the decision;

(j)

issue any direction as may be necessary or expedient;

(k)

order interrogatories to be answered;

(l)

order that any evidence be given on oath;

(m)

review and revise any certificate issued or to be issued pursuant to a construction work contract, decision, instruction, opinion or valuation of the parties or contract administrator relevant to the dispute;

(n)

decide or declare on any matter notwithstanding no certificate has been issued in respect of the matter;

(o)

award financing costs and interest; and

(p)

extend any time limit imposed on the parties under this

Act as reasonably required.