5. Payment claim

Feedback & support
(1)

An unpaid party may serve a payment claim on a non-paying party for payment pursuant to a construction contract.

(2)

The payment claim shall be in writing and shall include—

(a)

the amount claimed and due date for payment of the amount claimed;

(b)

details to identify the cause of action including the provision in the construction contract to which the payment relates;

(c)

description of the work or services to which the payment relates; and

(d)

a statement that it is made under this Act.