Malaysia legislation

Section 184

of CONTRACTS ACT 1950

Section 184

(b)

If the principal discloses himself before the contract is completed, the other contracting party may refuse to fulfil the contract, if he can show that, if he had known who was the principal in the contract, or if he had known that the agent was not a principal, he would not have entered into the contract.

Performance of contract with agent supposed to be principal

Section 184 — CONTRACTS ACT 1950 | mylaw.my