/akn/my/act/pua/2015/102

PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015

The full official text, structured for quick navigation. Copy any provision or jump straight to a section.

Open source PDF
Type
P.U. (A)
Status
In force
Enacted
2015
Sections
5

Quick answer

About this p.u. (a)

PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015 is Malaysia P.U. (A), cited as P.U. (A) 102 2015, currently marked in force and first recorded in 2015.

Opening note

Preamble

Suggest a correction
  1. PADA menjalankan kuasa yang diberikan oleh perenggan 37(2)(c) Akta Lembaga Pembangunan Industri Pembinaan Malaysia 1994 [Akta 520], Lembaga, dengan kelulusan Menteri, membuat peraturan-peraturan yang berikut: Nama dan permulaan kuat kuasa

Seksyen 1

Open as pageSuggest a correction

(1)

Peraturan-peraturan ini bolehlah dinamakan Peraturan-Peraturan

Lembaga Pembangunan Industri Pembinaan Malaysia (Penyampaian Notis) 2015.

Suggest a correction

(2)

Peraturan-Peraturan ini mula berkuat kuasa pada 1 Jun 2015.

Notis

Suggest a correction

Seksyen 2

Open as pageSuggest a correction

(1)

Notis untuk memberikan maklumat di bawah seksyen 27 Akta hendaklah dalam Borang I, II atau III Jadual.

Suggest a correction

(2)

Notis untuk berhenti daripada memulakan atau meneruskan kerja pembinaan di bawah seksyen 30 Akta hendaklah dalam Borang IV atau V Jadual.

Suggest a correction

(3)

Notis untuk berhenti daripada menggunakan bahan binaan yang tidak diperakukan di bawah seksyen 33E Akta hendaklah dalam Borang VI Jadual.

Penyampaian notis

Suggest a correction

Seksyen 3

Open as pageSuggest a correction

(1)

Notis yang disebut dalam subperaturan 2(1) hendaklah disampaikan kepada seseorang melalui penyampaian ke diri atau secara pos berdaftar.

Suggest a correction

(2)

Notis yang disebut dalam subperaturan 2(2) dan 2(3) boleh disampaikan kepada seseorang dengan cara yang berikut:

(a)

melalui penyampaian ke diri di alamat biasa atau alamat yang akhir diketahui atau tempat perniagaan orang itu; atau

P.U. (A) 102 3

Suggest a correction

(b)

melalui pos biasa atau pos berdaftar Akuan Terima yang dialamatkan ke tempat tinggal atau tempat perniagaan orang itu yang lazim atau yang akhir diketahui.

Suggest a correction
Suggest a correction

(3)

Notis yang disebut dalam peraturan 2 disifatkan telah disampaikan kepada syarikat atau pertubuhan yang diperbadankan jika notis itu telah disampaikan pada setiausaha syarikat atau pertubuhan itu di pejabat berdaftar atau pejabat utamanya.

Pembatalan

Suggest a correction

Seksyen 4

Peraturan-Peraturan Industri Pembinaan Malaysia (Notis Yang Ditetapkan) 1997

Open as pageSuggest a correction

[P.U. (A) 116/1997] dibatalkan.

P.U. (A) 102 4

Jadual

Suggest a correction

JADUAL

(Subperaturan 2(1) )

Borang I

NOTIS UNTUK MEMBERIKAN BUTIR-BUTIR MENGENAI INDUSTRI PEMBINAAN

(SEKSYEN 27)

Kepada :

........................................................................

........................................................................

........................................................................

Tarikh Notis

:

No. Rujukan CIDB

:

Menurut seksyen 27 Akta Lembaga Pembangunan Industri Pembinaan Malaysia 1994 (Akta), kamu dikehendaki memberi butir-butir yang berada dalam pengetahuan kamu atau yang kamu boleh mendapatkannya, kepada

Lembaga dalam masa ............................( ) hari dari tarikh surat ini mengenai industri pembinaan atau apa-apa jua yang dikehendaki di bawah Akta.

Kamu adalah diminta untuk memberikan maklumat dan mengemukakan butir-butir yang berikut:

..................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

Diingatkan bahawa adalah menjadi suatu kesalahan di bawah seksyen 28 jika kamu tidak mengemukakan maklumat yang dikehendaki seperti di atas dan apabila disabitkan, kamu boleh didenda tidak melebihi lima ratus ringgit dan dalam hal kesalahan yang berterusan, boleh didenda tidak melebihi lima ratus ringgit bagi tiap-tiap hari atau sebahagian daripada hari yang kesalahan itu berterusan selepas sabitan.

.....................................................

Ketua Pegawai Eksekutif

Lembaga Pembangunan Industri Pembinaan Malaysia

………………………………………………………….

(tandatangan)

Nama

: …………………………………………………...

: ……………………………………….................

No. Tel.

: ……………………………………….................

Tarikh

: …………………………………………………...

Cap Syarikat

:

P.U. (A) 102 5

Borang II

NOTIS PENGEMUKAAN MAKLUMAT BERKENAAN KERJA PEMBINAAN

(SEKSYEN 27)

Kepada :

........................................................................

........................................................................

........................................................................

Tarikh Notis

:

No. Rujukan CIDB

:

Nama Projek

:

..................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

Menurut seksyen 27 Akta Lembaga Pembangunan Industri Pembinaan Malaysia 1994 (Akta), kamu dikehendaki memberi butir-butir yang berada dalam pengetahuan kamu atau yang kamu boleh mendapatkannya, dengan menggunakan Borang III yang dilampirkan dan mengembalikannya kepada Lembaga dalam masa 14 hari dari tarikh surat ini mengenai kerja pembinaan atau apa-apa jua yang dikehendaki di bawah Akta.

Kamu adalah diminta untuk mengemukakan dan mengembalikan butir-butir yang berikut:

..................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

Diingatkan bahawa adalah menjadi suatu kesalahan di bawah seksyen 28 jika kamu tidak mengemukakan maklumat yang dikehendaki seperti di atas dan apabila disabitkan, kamu boleh didenda tidak melebihi lima ratus ringgit dan dalam hal kesalahan yang berterusan, boleh didenda tidak melebihi lima ratus ringgit bagi tiap-tiap hari atau sebahagian daripada hari yang kesalahan itu berterusan selepas sabitan.

........................................................

Ketua Pegawai Eksekutif

Lembaga Pembangunan Industri Pembinaan Malaysia

………………………………………………………….

(tandatangan)

Nama

: …………………………………………………...

: ……………………………………….................

No. Tel.

: ……………………………………….................

Tarikh

: …………………………………………………...

Cap Syarikat

:

P.U. (A) 102 6

Borang III

NOTIS PENGEMUKAAN MAKLUMAT BERKENAAN KERJA PEMBINAAN

Kepada

:

Tarikh Notis

:

No. Rujukan CIDB :

Senarai Subkontraktor / NSC

* Sila lampirkan salinan Surat Setuju Terima Tender / Award

Saya dengan ini mengaku bahawa maklumat yang diberikan adalah benar dan lengkap.

Tarikh:

Tandatangan Pegawai Yang Diberi Kuasa

Nama :

Jawatan :

Cap/Meterai Rasmi Syarikat

-

Nama dan Alamat Kontraktor Utama :

No. Arahan Pembangunan :

Tarikh Mula Kerja :

Tarikh Surat Setuju Terima Tender :

Negeri :

Daerah:

Nama Projek :

MAKLUMAT INI PERLU DIPENUHKAN OLEH KLIEN/KONTRAKTOR UTAMA

No. Perakuan Pendaftaran CIDB :

Tarikh Milik

Tapak

Tarikh

Award Kerja

No. Perakuan

Pendaftaran CIDB

Nama Kontraktor & Alamat

Kontraktor

Bil

Jumlah

Kontrak

Pengkhususan

P.U. (A) 102 7

Borang IV

[SUBSEKSYEN 30(1)]

Rujukan Kami :

Kepada :

........................................................................

.........................................................................

.......................................................................

Nombor Rujukan CIDB :

Nama Projek

:

..................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

Lembaga mendapati bahawa kerja pembinaan di atas sedang diusahakan atau dijalankan oleh kamu/syarikat kamu sedangkan kamu/syarikat kamu tidak berdaftar dengan Lembaga. Kamu/Syarikat kamu telah melanggar subseksyen 25(1) Akta Lembaga Pembangunan Industri Pembinaan Malaysia 1994 (Akta) yang memperuntukkan bahawa tiada seorang pun boleh menjalankan/menyiapkan/mengaku janji untuk menjalankan atau menyiapkan kerja pembinaan atau mengaku dirinya sebagai kontraktor tanpa mendapatkan perakuan pendaftaran yang sah daripada Lembaga.

Menurut seksyen 29 Akta, mana-mana orang yang melanggar subseksyen 25(1) melakukan suatu kesalahan dan apabila disabitkan, boleh didenda tidak kurang daripada sepuluh ribu ringgit tetapi tidak lebih daripada satu ratus ribu ringgit.

SILA AMBIL PERHATIAN bahawa tertakluk kepada syarat yang terkandung dalam Lampiran, Notis ini yang dikeluarkan di bawah subseksyen 30(1) Akta kepada kamu/syarikat kamu menghendaki kamu/syarikat kamu dan/atau pekerja kamu/syarikat kamu dan/atau wakil kamu/syarikat kamu/atau ejen kamu/syarikat kamu dan/atau pekhidmat kamu/syarikat kamu DENGAN SERTA-MERTA UNTUK TIDAK MEMULAKAN ATAU

MENERUSKAN KERJA PEMBINAAN.

Menurut subseksyen 30(2) Akta, seseorang yang tidak mematuhi kehendak notis di bawah subseksyen 30(1) adalah melakukan suatu kesalahan dan apabila disabitkan, boleh didenda tidak melebihi lima ribu ringgit, dan dalam hal kesalahan yang berterusan, boleh didenda tidak melebihi satu ribu ringgit bagi tiap-tiap hari atau sebahagian daripada hari yang kesalahan itu berterusan selepas sabitan.

Bertarikh : ..............................................

..............................................................................

( )

Ketua Pegawai Eksekutif

Lembaga Pembangunan Industri Pembinaan Malaysia s.k

1) Pengurus Besar

Bahagian Penguatkuasaan

2) Pengurus Besar

Bahagian Pendaftaran Dan Levi

3) Pihak Berkuasa Tempatan

4) Arkitek / Jurutera

5) Pemaju / Klien

6) Fail

Muka surat 1 dari 2

………………………………………………………….

(tandatangan)

Nama

: …………………………………………………...

: ……………………………………….................

No. Tel.

: ……………………………………….................

Tarikh

: …………………………………………………...

Cap Syarikat

:

P.U. (A) 102 8

Lampiran

Suggest a correction

[SUBSEKSYEN 30(1)]

NOMBOR

SYARAT

Muka surat 2 dari 2

P.U. (A) 102 9

Borang V

[SUBSEKSYEN 30(1A)]

Rujukan Kami :

Kepada :

........................................................................

.........................................................................

.......................................................................

Nombor Rujukan CIDB

:

Nama Projek

:

..................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

Lembaga mendapati bahawa kerja pembinaan di atas yang sedang dijalankan atau disiapkan, atau telah diaku janji untuk dijalankan atau disiapkan oleh seorang kontraktor berdaftar melanggar peruntukan Akta Lembaga

Pembangunan Industri Pembinaan Malaysia 1994 (Akta), iaitu –

..................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

*(Sila nyatakan jenis pelanggaran yang dimaksudkan)

SILA AMBIL PERHATIAN bahawa Notis ini yang dikeluarkan di bawah subseksyen 30(1A) Akta kepada kamu/syarikat kamu menghendaki kamu/syarikat kamu dan/atau pekerja kamu/syarikat kamu dan/atau wakil kamu/syarikat kamu atau ejen kamu/syarikat kamu dan/atau pekhidmat kamu/syarikat kamu DENGAN

SERTA-MERTA UNTUK TIDAK MEMULAKAN ATAU MENERUSKAN KERJA PEMBINAAN.

Menurut subseksyen 30(2) Akta, seseorang yang tidak mematuhi kehendak notis di bawah subseksyen 30(1) adalah melakukan suatu kesalahan dan apabila disabitkan, boleh didenda tidak melebihi lima ribu ringgit, dan dalam hal kesalahan yang berterusan, boleh didenda tidak melebihi satu ribu ringgit bagi tiap-tiap hari atau sebahagian daripada hari yang kesalahan itu berterusan selepas sabitan.

Bertarikh : ..............................................

..............................................................................

( )

Ketua Pegawai Eksekutif

Lembaga Pembangunan Industri Pembinaan Malaysia s.k

1) Pengurus Besar

Bahagian Penguatkuasaan

2) Arkitek / Jurutera

3) Pemaju / Klien

4) Fail

………………………………………………………….

(tandatangan)

Nama

: …………………………………………………...

: ……………………………………….................

No. Tel.

: ……………………………………….................

Tarikh

: …………………………………………………...

Cap Syarikat

:

P.U. (A) 102 10

Borang VI

NOTIS UNTUK BERHENTI DARIPADA MENGGUNAKAN BAHAN BINAAN YANG TIDAK DIPERAKUKAN

[SUBSEKSYEN 33E(1)]

Rujukan Kami :

Kepada :

........................................................................

.........................................................................

........................................................................

Nombor Rujukan CIDB

:

Nama Projek

:

..................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

Lembaga mendapati bahawa kamu menggunakan bahan binaan yang tidak diperakukan menurut Akta Lembaga

Pembangunan Pembinaan Malaysia 1994 (Akta). Kamu/syarikat kamu telah melanggar subseksyen 33D(1) Akta.

SILA AMBIL PERHATIAN bahawa Notis ini dikeluarkan di bawah subseksyen 33E(1) Akta yang menghendaki kamu/

syarikat kamu dan/atau kamu/pekerja syarikat kamu dan/atau wakil syarikat kamu/ejen/pekhidmat syarikat kamu

DENGAN SERTA-MERTA UNTUK TIDAK MEMULAKAN ATAU MENERUSKAN, MELIBATKAN DALAM ATAU

TERLIBAT DALAM ATAU MENGAKU JANJI UNTUK MELIBATKAN DALAM ATAU TERLIBAT DALAM, URUSAN

DENGAN BAHAN BINAAN YANG TIDAK DIPERAKUKAN ITU.

Menurut subseksyen 33E(2) Akta, seseorang yang tidak mematuhi kehendak notis di bawah subseksyen 33E(1)

adalah melakukan suatu kesalahan dan boleh, apabila disabitkan, didenda tidak melebihi lima puluh ribu ringgit dan dalam hal kesalahan yang berterusan, boleh didenda tidak melebihi lima ratus ringgit bagi setiap hari atau sebahagian daripada sehari yang kesalahan itu berterusan selepas sabitan.

Bertarikh : ..............................................

.................................................................................

( )

Ketua Pegawai Eksekutif

Lembaga Pembangunan Industri Pembinaan Malaysia s.k

1) Pengurus Besar

Bahagian Pendaftaran dan Levi

2) Arkitek / Jurutera

3) Pemaju / Klien

4) Fail

………………………………………………………….

(tandatangan)

Nama

: …………………………………………………...

: ……………………………………….................

No. Tel.

: ……………………………………….................

Tarikh

: …………………………………………………...

Cap Syarikat

:

P.U. (A) 102 11

Dibuat 22 Mei 2015

Diluluskan 26 Mei 2015

TAN SRI DR. AHMAD TAJUDDIN ALI

Pengerusi

Lembaga Pembangunan Industri Pembinaan Malaysia

DATO’ SRI HAJI FADILLAH HAJI YUSOF

Menteri Kerja Raya

P.U. (A) 102 12

IN exercise of the powers conferred by paragraph 37(2)(c) of the Lembaga

Pembangunan Industri Pembinaan Malaysia Act 1994 [Act 520], the Lembaga, with the approval of the Minister, makes the following regulations:

Citation and commencement 1.

(1)

These regulations may be cited as the Lembaga Pembangunan Industri

Pembinaan Malaysia (Service of Notice) Regulations 2015.

(2)

These Regulations come into operation on 1 June 2015.

Notices 2.

(1)

A notice to furnish particulars under section 27 of the Act shall be in

Form I, II or III of the Schedule.

(2)

A notice to abstain from commencing or proceeding with construction works under section 30 of the Act shall be in Form IV or V of the Schedule.

(3)

A notice to abstain from dealing with non-certified construction materials under section 33E of the Act shall be in Form VI of the Schedule.

Service of notice 3.

(1)

The notice referred to in subregulation 2(1) shall be served on a person by personal service or by registered post.

(2)

The notice referred to in subregulations 2(2) and 2(3) may be served on a person in the manner as follows:

(a)

by personal service at the usual or last known address or place of business of that person; or

P.U. (A) 102 13

(b)

by ordinary post or prepaid A.R. registered post addressed to the person’s usual or last known place of abode or place of business.

(3)

The notices referred to in regulation 2 are deemed served on an incorporated company or body if the notices have been served on the secretary of the company or body at its registered or principal office.

Revocation 4.

The

Construction

Industry

(Prescribed

Notice)

Regulations 1997

[P.U. (A) 116/1997] are revoked.

P.U. (A) 102 14

SCHEDULE

(Subregulation 2(1) )

Form I

NOTICE TO FURNISH PARTICULARS ON CONSTRUCTION INDUSTRY

(SECTION 27)

To :

........................................................................

.........................................................................

........................................................................

........................................................................

Date of Notice

:

CIDB Reference No.

:

Pursuant to section 27 of the Lembaga Pembangunan Industri Pembinaan Malaysia Act 1994 (the Act), you are required to furnish particulars which are within your knowledge or which you are able to obtain, to the Lembaga within ............................( ) days from the date of this letter on the construction industry or anything required under this

Act.

You are requested to furnish the information and submit the following particulars:

..................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

Please be reminded that it is an offence under section 28 if you fail to submit information required above and on conviction, you may be liable to a fine not exceeding five hundred ringgit and in the case of a continuing offence, to a fine not exceeding five hundred ringgit for every day or part of a day during which the offence continues after conviction.

....................................................

Chief Executive Officer

Lembaga Pembangunan Industri Pembinaan Malaysia

DERAF

………………………………………………………….

(signature)

Name

: …………………………………………………...

Tel. No. : ……………………………………….................

Date

: …………………………………………………...

Company’s Stamp :

P.U. (A) 102 15

Form II

NOTICE OF SUBMISSION OF INFORMATION ON CONSTRUCTION WORKS

(SECTION 27)

........................................................................

.........................................................................

........................................................................

........................................................................

Date of Notice

:

CIDB Reference No.

:

Name of Project

:

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

Pursuant to section 27 of the Lembaga Pembangunan Industri Pembinaan Malaysia Act 1994 (the Act), you are required to furnish particulars which are within your knowledge or which you are able to obtain, by using the attached Form III and return it to the Lembaga within 14 days from the date of this letter on the construction works or anything required under the Act.

You are required to submit and return the following particulars:

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

Please be reminded that it is an offence under section 28 if you fail to submit information required above and on conviction, you may be liable to a fine not exceeding five hundred ringgit and in the case of a continuing offence, to a fine not exceeding five hundred ringgit for every day or part of a day during which the offence continues after conviction.

....................................................

Chief Executive Officer

Lembaga Pembangunan Industri Pembinaan Malaysia

………………………………………………………….

(signature)

Name

: …………………………………………………...

Tel. No.

: ……………………………………….................

Date

: …………………………………………………...

Company’s Stamp :

P.U. (A) 102 16

Form III

NOTICE OF SUBMISSION OF INFORMATION ON CONSTRUCTION WORKS

To

:

Date of Notice

:

CIDB Reference No. :

List of Subcontractor / NSC

* Please attach a copy of the Letter of Acceptance of Tender / Award

I hereby certify that the information given is true and complete.

Date:

Signature of Authorised Officer

Name :

Designation :

Stamp/Official Seal of Company

-

Name and Address of Main Contractor:

No. of Development Order :

Date of Commencement of Work:

Date of Letter of Acceptance of Tender:

State :

District:

Name of Project:

THIS INFORMATION MUST BE COMPLETED BY THE CLIENT/MAIN CONTRACTOR

No. of CIDB Certificate of Registration :

Date of

Possession of

Site

Date of

Award of

Work

No. of CIDB Certificate of

Registration

Name of Contractor &

Address of Contractor

No.

Contract Sum

Specialization

P.U. (A) 102 17

Form IV

NOTICE TO ABSTAIN FROM COMMENCING OR PROCEEDING WITH CONSTRUCTION WORKS

[SUBSECTION 30(1)]

Our Reference :

To :

.......................................................................

.......................................................................

.......................................................................

CIDB Reference No.

:

Name of Project

:

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

The Lembaga finds that the construction works above are being undertaken or carried out by you/your company whereas you/your company is not registered with the Lembaga. You/Your company’s have/has contravened subsection 25(1) of the Lembaga Pembangunan Industri Pembinaan Malaysia Act 1994 (the Act) which provides that no person shall carry out/complete/undertake to carry out or complete construction works or hold himself out as a contractor without obtaining a valid certificate of registration from the Lembaga.

Pursuant to section 29 of the Act, any person who contravenes subsection 25(1) shall be guilty of an offence and on conviction, shall be liable to a fine of not less than ten thousand ringgit but not more than one hundred thousand ringgit.

TAKE NOTICE that subject to the conditions contained in Annexure, this Notice issued under subsection 30(1) of the

Act to you/your company requires you/your company and/or your/your company’s employees and/or your/your company’s representatives or your/your company’s agents and/or your/your company’s servants IMMEDIATELY

NOT TO COMMENCE OR PROCEED WITH THE CONSTRUCTION WORKS.

Pursuant to subsection 30(2) of the Act, a person who fails to comply with the requirements of the notice issued under subsection 30(1) shall be guilty of an offence and on conviction, shall be liable to a fine not exceeding five thousand ringgit, and in the case of a continuing offence, to a fine not exceeding one thousand ringgit for every day or part of a day during which the offence continues after conviction.

Dated : ..............................................

...................................................................................

( )

Chief Executive Officer

Lembaga Pembangunan Industri Pembinaan Malaysia c.c

1) General Manager

Enforcement Division

2) General Manager

Registration and Levy Division

3) Local Authority

4)

Architect/ Engineer 5)

Developer/Client

6) File

Page 1 of 2

………………………………………………………….

(signature)

Name

: …………………………………………………...

NRIC. No. : ………………………....................................

Tel. No.

: ……………………………………….................

Date

: …………………………………………………...

Company’s Stamp :

P.U. (A) 102 18

ANNEXURE

NOTICE TO ABSTAIN FROM COMMENCING OR PROCEEDING WITH CONSTRUCTION WORKS

[SUBSECTION 30(1)]

NUMBER

CONDITIONS

Page 2 of 2

P.U. (A) 102 19

Form V

(SERVICE OF NOTICE) REGULATIONS 2015

NOTICE TO ABSTAIN FROM COMMENCING OR PROCEEDING WITH CONSTRUCTION WORKS

[SUBSECTION 30(1A)]

Our Reference :

........................................................................

.........................................................................

.......................................................................

CIDB Reference No.

:

Name of Project

:

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

The Lembaga finds that the construction works above are being carried out or completed, or undertaken to be carried out or completed by a registered contractor in contravention of the provision of the Lembaga Pembangunan Industri

Pembinaan Malaysia Act 1994 (the Act), namely –

..................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

*(Please state the types of contravention referred to)

TAKE NOTICE that this Notice is issued under subsection 30(1A) of the Act to you/your company requires you/your company and/or your/your company’s employees and/or your/your company’s representatives or your/your company’s agents and/or your/your company’s servants IMMEDIATELY NOT TO COMMENCE OR PROCEED WITH

THE CONSTRUCTION WORKS.

Pursuant to subsection 30(2) of the Act, a person who fails to comply with the requirements of the notice issued under subsection 30(1) shall be guilty of an offence and on conviction, shall be liable to a fine not exceeding five thousand ringgit, and in the case of a continuing offence, to a fine not exceeding one thousand ringgit for every day or part of a day during which the offence continues after conviction.

Dated: ..............................................

.....................................................................................

( )

Chief Executive Officer

Lembaga Pembangunan Industri Pembinaan Malaysia c.c

1) General Manager

Enforcement Division

2) Architect/Engineer

3) Developer/Client

4) File

………………………………………………………….

(signature)

Name

: …………………………………………………...

Tel. No. : ……………………………………….................

Date

: …………………………………………………...

Company’s Stamp :

P.U. (A) 102 20

Form VI

NOTICE TO ABSTAIN FROM DEALING WITH NON-CERTIFIED CONSTRUCTION MATERIALS

[SUBSECTION 33E(1)]

Our reference :

.......................................................................

.......................................................................

.......................................................................

.......................................................................

CIDB Reference No.

:

Name of Project

:

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

...................................................................................................................................................................................................................................................................................

The Lembaga finds that you have been using construction materials not certified according to the Lembaga

Pembangunan Industri Pembinaan Malaysia Act 1994 (the Act). Your/your company’s action has contravened subsection 33D(1) of the Act.

TAKE NOTICE that this Notice is issued under subsection 33E(1) of the Act which requires you/your company and/or your/your company’s employees and/or your company’s representatives/agents/servants IMMEDIATELY

NOT TO COMMENCE OR PROCEED WITH, ENGAGE IN OR BE INVOLVED IN OR UNDERTAKE TO BE ENGAGED IN

OR BE INVOLVED IN, DEALING WITH THE NON-CERTIFIED CONSTRUCTION MATERIALS.

Pursuant to subsection 33E(2) of the Act, any person who fails to comply with the requirements of the notice under subsection 33E(1) shall be guilty of an offence and shall, on conviction, be liable to a fine not exceeding fifty thousand ringgit and in the case of a continuing offence, to a fine not exceeding five hundred ringgit for every day or part of a day during which the offence continues after conviction.

Dated : ..............................................

.....................................................................................

( )

Chief Executive Officer

Lembaga Pembangunan Industri Pembinaan Malaysia c.c

1) General Manager

Registration and Levy Division

2) Architect/Engineer

3) Developer/Client

4) File

………………………………………………………….

(signature)

Name

: …………………………………………………...

NRIC. No.

: ………………………...................................

Tel. No. : ……………………………………….................

Date

: …………………………………………………...

Company’s Stamp :

P.U. (A) 102 21

Made 22 May 2015

[KKR.PUU.110-1/5/2 jld9(26); PN(PU2)546/IV

Approved 26 May 2015

TAN SRI DR. AHMAD TAJUDDIN ALI

Chairman

Lembaga Pembangunan Industri Pembinaan Malaysia

DATO’ SRI HAJI FADILLAH HAJI YUSOF

Minister of Works

Common questions

What is PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015?
PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015 is Malaysia P.U. (A), cited as P.U. (A) 102 2015, currently marked in force and first recorded in 2015.
Is PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015 still in force?
Yes — PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015 is currently in force.
When did PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015 take effect?
PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015 was first recorded in 2015.
How many sections does PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015 have?
PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015 contains 4 sections.
Where can I read the official version of PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015?
The official text of PERATURAN-PERATURAN LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA (PENYAMPAIAN NOTIS) 2015 is published at lom.agc.gov.my.