/akn/my/act/pua/2015/19

PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015

The full official text, structured for quick navigation. Copy any provision or jump straight to a section.

Open source PDF
Type
P.U. (A)
Status
In force
Enacted
2015
Sections
6

Quick answer

About this p.u. (a)

PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015 is Malaysia P.U. (A), cited as P.U. (A) 19 2015, currently marked in force and first recorded in 2015.

Opening note

Preamble

Suggest a correction
  1. PADA menjalankan kuasa yang diberikan oleh subseksyen 55(3) Akta Kilang dan Jentera 1967 [Akta 139], Menteri membuat perintah yang berikut: Nama

Seksyen 1

Open as pageSuggest a correction

Perintah ini bolehlah dinamakan Perintah Kilang dan Jentera (Pengecualian kepada Petronas Gas Berhad, Centralised Utility Facilities, Kertih Terengganu)

Seksyen 2

Open as pageSuggest a correction

Semua jentera yang didaftarkan dengan Ketua Pemeriksa, dengan nombor pendaftaran dan perihalan yang dinyatakan dalam ruang (1) dan (2) Jadual, atas nama

Petronas Gas Berhad, Centralised Utility Facilities, Kerteh Terengganu yang telah dikeluarkan perakuan kelayakan, adalah dikecualikan daripada persediaan yang dikehendaki di bawah perenggan 17(b) Peraturan-Peraturan (Pemberitahu, Perakuan

Kelayakan dan Pemeriksaan) Kilang dan Jentera 1970 [P.U. (A) 43/1970] bagi pemeriksaan ulangan yang berikutnya selepas habis tempoh perakuan kelayakan itu pada 13 Februari 2015.

Seksyen 3

Syarat pengecualian

Open as pageSuggest a correction

Pengecualian di bawah perenggan 2 tertakluk kepada syarat bahawa semua jentera yang dinyatakan dalam Jadual menjalani pemeriksaan luaran dan ujian tanpa musnah, dan Pemeriksa berpuas hati dengan keputusan pemeriksaan dan ujian itu.

P.U. (A) 19 3

Jadual

Suggest a correction

JADUAL

(1)

(2)

No. Pendaftaran

Perihalan Jentera

127615

Bejana tekanan tidak berapi

127616

Bejana tekanan tidak berapi

127617

Bejana tekanan tidak berapi

127618

Bejana tekanan tidak berapi

127619

Bejana tekanan tidak berapi

127620

Bejana tekanan tidak berapi

127621

Bejana tekanan tidak berapi

127622

Bejana tekanan tidak berapi

127623

Bejana tekanan tidak berapi

127624

Bejana tekanan tidak berapi

127625

Bejana tekanan tidak berapi

127626

Bejana tekanan tidak berapi

127627

Bejana tekanan tidak berapi

127628

Bejana tekanan tidak berapi

127629

Bejana tekanan tidak berapi

127630

Bejana tekanan tidak berapi

127631

Bejana tekanan tidak berapi

127632

Bejana tekanan tidak berapi

127633

Bejana tekanan tidak berapi

127634

Bejana tekanan tidak berapi

127635

Bejana tekanan tidak berapi

127636

Bejana tekanan tidak berapi

127637

Bejana tekanan tidak berapi

127638

Bejana tekanan tidak berapi

127641

Bejana tekanan tidak berapi

127644

Bejana tekanan tidak berapi

127645

Bejana tekanan tidak berapi

127646

Bejana tekanan tidak berapi

127647

Bejana tekanan tidak berapi

P.U. (A) 19 4

(1)

(2)

No. Pendaftaran

Perihalan Jentera

127648

Bejana tekanan tidak berapi

127649

Bejana tekanan tidak berapi

127650

Bejana tekanan tidak berapi

127651

Bejana tekanan tidak berapi

127652

Bejana tekanan tidak berapi

127765

Bejana tekanan tidak berapi

127766

Bejana tekanan tidak berapi

127767

Bejana tekanan tidak berapi

127768

Bejana tekanan tidak berapi

127769

Bejana tekanan tidak berapi

127770

Bejana tekanan tidak berapi

127771

Bejana tekanan tidak berapi

127772

Bejana tekanan tidak berapi

127773

Bejana tekanan tidak berapi

127774

Bejana tekanan tidak berapi

127775

Bejana tekanan tidak berapi

127776

Bejana tekanan tidak berapi

127777

Bejana tekanan tidak berapi

127778

Bejana tekanan tidak berapi

127779

Bejana tekanan tidak berapi

127780

Bejana tekanan tidak berapi

127784

Bejana tekanan tidak berapi

127785

Bejana tekanan tidak berapi

127786

Bejana tekanan tidak berapi

127787

Bejana tekanan tidak berapi

127788

Bejana tekanan tidak berapi

127789

Bejana tekanan tidak berapi

127790

Bejana tekanan tidak berapi

127791

Bejana tekanan tidak berapi

127792

Bejana tekanan tidak berapi

P.U. (A) 19 5

(1)

(2)

No. Pendaftaran

Perihalan Jentera

127793

Bejana tekanan tidak berapi

127794

Bejana tekanan tidak berapi

127795

Bejana tekanan tidak berapi

127814

Bejana tekanan tidak berapi

127815

Bejana tekanan tidak berapi

127816

Bejana tekanan tidak berapi

127817

Bejana tekanan tidak berapi

127818

Bejana tekanan tidak berapi

127819

Bejana tekanan tidak berapi

127820

Bejana tekanan tidak berapi

127821

Bejana tekanan tidak berapi

127822

Bejana tekanan tidak berapi

127823

Bejana tekanan tidak berapi

127824

Bejana tekanan tidak berapi

127825

Bejana tekanan tidak berapi

127826

Bejana tekanan tidak berapi

127827

Bejana tekanan tidak berapi

127828

Bejana tekanan tidak berapi

127829

Bejana tekanan tidak berapi

127830

Bejana tekanan tidak berapi

127831

Bejana tekanan tidak berapi

127832

Bejana tekanan tidak berapi

127833

Bejana tekanan tidak berapi

127834

Bejana tekanan tidak berapi

127835

Bejana tekanan tidak berapi

127836

Bejana tekanan tidak berapi

127837

Bejana tekanan tidak berapi

127838

Bejana tekanan tidak berapi

127839

Bejana tekanan tidak berapi

127840

Bejana tekanan tidak berapi

P.U. (A) 19 6

(1)

(2)

No. Pendaftaran

Perihalan Jentera

127841

Bejana tekanan tidak berapi

127842 Bejana tekanan tidak berapi

127843

Bejana tekanan tidak berapi

127844

Bejana tekanan tidak berapi

127845

Bejana tekanan tidak berapi

Dibuat 21 Januari 2015

[KSM/PUU/(S)/600-1/2/8/10/2 Jld.4; PN(PU2)235/XLIII]

DATO’ SRI RICHARD RIOT ANAK JAEM

Menteri Sumber Manusia

P.U. (A) 19 7

FACTORIES AND MACHINERY ACT 1967

FACTORIES AND MACHINERY (EXEMPTION TO PETRONAS GAS BERHAD,

CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) ORDER 2015

IN exercise of the powers conferred by subsection 55(3) of the Factories and Machinery

Act 1967 [Act 139], the Minister makes the following order:

Citation 1.

This order may be cited as the Factories and Machinery (Exemption to

Petronas Gas Berhad, Centralised Utility Facilities, Kertih Terengganu)

Order 2015.

Exemption 2.

All machinery registered with the Chief Inspector, with the registration numbers and descriptions as specified in columns (1) and (2) of the Schedule, in the name of

Petronas Gas Berhad, Centralised Utility Facilities, Kerteh Terengganu which have been issued with certificates of fitness, are exempted from the preparation required under paragraph 17(b) of the Factories and Machinery (Notification, Certificate of Fitness and Inspection) Regulations 1970 [P.U. (A) 43/1970] for subsequent regular inspection after the expiry of such certificates of fitness on 13 February 2015.

Condition of exemption 3.

The exemption under paragraph 2 is subject to the conditions that all of the machinery as specified in the Schedule undergo an external inspection and non-destructive tests, and the Inspector is satisfied with the result of such inspection and tests.

P.U. (A) 19 8

Jadual

Suggest a correction

(1)

(2)

Registration No.

Description of Machinery

127615

Unfired pressure vessel

127616

Unfired pressure vessel

127617

Unfired pressure vessel

127618

Unfired pressure vessel

127619

Unfired pressure vessel

127620

Unfired pressure vessel

127621

Unfired pressure vessel

127622

Unfired pressure vessel

127623

Unfired pressure vessel

127624

Unfired pressure vessel

127625

Unfired pressure vessel

127626

Unfired pressure vessel

127627

Unfired pressure vessel

127628

Unfired pressure vessel

127629

Unfired pressure vessel

127630

Unfired pressure vessel

127631

Unfired pressure vessel

127632

Unfired pressure vessel

127633

Unfired pressure vessel

127634

Unfired pressure vessel

127635

Unfired pressure vessel

127636

Unfired pressure vessel

127637

Unfired pressure vessel

127638

Unfired pressure vessel

127641

Unfired pressure vessel

127644

Unfired pressure vessel

127645

Unfired pressure vessel

127646

Unfired pressure vessel

127647

Unfired pressure vessel

P.U. (A) 19 9

(1)

(2)

Registration No.

Description of Machinery

127648

Unfired pressure vessel

127649

Unfired pressure vessel

127650

Unfired pressure vessel

127651

Unfired pressure vessel

127652

Unfired pressure vessel

127765

Unfired pressure vessel

127766

Unfired pressure vessel

127767

Unfired pressure vessel

127768

Unfired pressure vessel

127769

Unfired pressure vessel

127770

Unfired pressure vessel

127771

Unfired pressure vessel

127772

Unfired pressure vessel

127773

Unfired pressure vessel

127774

Unfired pressure vessel

127775

Unfired pressure vessel

127776

Unfired pressure vessel

127777

Unfired pressure vessel

127778

Unfired pressure vessel

127779

Unfired pressure vessel

127780

Unfired pressure vessel

127784

Unfired pressure vessel

127785

Unfired pressure vessel

127786

Unfired pressure vessel

127787

Unfired pressure vessel

127788

Unfired pressure vessel

127789

Unfired pressure vessel

127790

Unfired pressure vessel

127791

Unfired pressure vessel

127792

Unfired pressure vessel

P.U. (A) 19 10

(1)

(2)

Registration No.

Description of Machinery

127793

Unfired pressure vessel

127794

Unfired pressure vessel

127795

Unfired pressure vessel

127814

Unfired pressure vessel

127815

Unfired pressure vessel

127816

Unfired pressure vessel

127817

Unfired pressure vessel

127818

Unfired pressure vessel

127819

Unfired pressure vessel

127820

Unfired pressure vessel

127821

Unfired pressure vessel

127822

Unfired pressure vessel

127823

Unfired pressure vessel

127824

Unfired pressure vessel

127825

Unfired pressure vessel

127826

Unfired pressure vessel

127827

Unfired pressure vessel

127828

Unfired pressure vessel

127829

Unfired pressure vessel

127830

Unfired pressure vessel

127831

Unfired pressure vessel

127832

Unfired pressure vessel

127833

Unfired pressure vessel

127834

Unfired pressure vessel

127835

Unfired pressure vessel

127836

Unfired pressure vessel

127837

Unfired pressure vessel

127838

Unfired pressure vessel

127839

Unfired pressure vessel

127840

Unfired pressure vessel

P.U. (A) 19 11

(1)

(2)

Registration No.

Description of Machinery

127841

Unfired pressure vessel

127842

Unfired pressure vessel

127843

Unfired pressure vessel

127844

Unfired pressure vessel

127845

Unfired pressure vessel

Made 21 January 2015

[KSM/PUU/(S)/600-1/2/8/10/2 Jld.4; PN(PU2)235/XLIII]

DATO’ SRI RICHARD RIOT ANAK JAEM

Minister of Human Resources

Common questions

What is PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015?
PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015 is Malaysia P.U. (A), cited as P.U. (A) 19 2015, currently marked in force and first recorded in 2015.
Is PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015 still in force?
Yes — PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015 is currently in force.
When did PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015 take effect?
PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015 was first recorded in 2015.
How many sections does PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015 have?
PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015 contains 4 sections.
Where can I read the official version of PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015?
The official text of PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015 is published at lom.agc.gov.my.
PERINTAH KILANG DAN JENTERA (PENGECUALIAN KEPADA PETRONAS GAS BERHAD, CENTRALISED UTILITY FACILITIES, KERTIH TERENGGANU) 2015 (No. 19)