Seksyen 1
(1)
Perintah ini bolehlah dinamakan Perintah Tenaga Boleh Baharu
(Pindaan Jadual) 2015.
/akn/my/act/pua/2015/82
The full official text, structured for quick navigation. Copy any provision or jump straight to a section.
Quick answer
PERINTAH TENAGA BOLEH BAHARU (PINDAAN JADUAL) 2015 is Malaysia P.U. (A), cited as P.U. (A) 82 2015, currently marked in force and first recorded in 2015.
Opening note
Perintah ini bolehlah dinamakan Perintah Tenaga Boleh Baharu
(Pindaan Jadual) 2015.
Jadual kepada Akta Tenaga Boleh Baharu 2011 dipinda dengan menggantikan butiran “Geoterma” dan butiran lain yang berhubungan dengannya dengan butiran yang berikut:
Ruang
Pertama
Ruang Kedua
Ruang Ketiga
Ruang
Keempat
Ruang
Kelima
Sumber boleh baharu
Perihalan pepasangan tenaga boleh baharu yang layak
Kadar tarif galakan (dalam ringgit bagi setiap kilowatt jam)
Tempoh berkuat kuasa
(bermula dari tarikh permulaan kuat kuasa tarif galakan)
Kadar pengurangan tahunan
“Geoterma
Pepasangan tenaga boleh baharu yang mempunyai kapasiti terpasang sehingga dan termasuk 30
megawatt 0.45 21 tahun 0%”.
P.U. (A) 82 3
Dibuat 29 April 2015
[KeTTHA: (S)100-1/1/5; PN(PU2)693/VII]
DATUK SERI PANGLIMA DR. MAXIMUS JOHNITY ONGKILI
Menteri Tenaga, Teknologi Hijau dan Air
P.U. (A) 82 4
RENEWABLE ENERGY ACT 2011
RENEWABLE ENERGY (AMENDMENT OF SCHEDULE) ORDER 2015
Opening note
This order may be cited as the Renewable Energy
(Amendment of Schedule) Order 2015.
This Order comes into operation on 6 May 2015.
Amendment of Schedule 2.
The Schedule to the Renewable Energy Act 2011 is amended by substituting for the item “Geothermal” and other items relating to it the following items:
First
Column
Second Column
Third
Column
Fourth Column
Fifth Column
Renewable resource
Description of qualifying renewable energy installation
Feed-in tariff rate (in ringgit per kilowatt hour)
Effective period
(commencing from the feed-in tariff commencement date)
Annual degression rate
“Geothermal
Renewable energy installation having an installed capacity of up to and including 30
megawatts 0.45 21 years 0%”.
Made 29 May 2015
[KeTTHA: (S)100-1/1/5; PN(PU2)693/VII]
DATUK SERI PANGLIMA DR. MAXIMUS JOHNITY ONGKILI
Minister of Energy, Green Technology and Water