Skip to content

Section 15

Application to relocate renewable energy installation utilizing solar photovoltaic

of Sabah Renewable Energy Feed Approval And Feed Tariff Rate Rules 2024

State Subsidiary LegislationIn forceProvision 15 of 29
Section 15
(1)

A feed-in approval holder may apply to the Commission to relocate a renewable energy installation utilizing solar photovoltaic to another location.

(2)

The application made under subrule (1) shall be made to the Commission in writing in a form as may be determined by the Commission and accompanied by the fees as specified in the Second Schedule.

(3)

The Commission may, after being satisfied that the relocation referred to in subrule (1) is not reasonably foreseeable at the time of the application for the feed-in approval, grant or refuse the application.

(4)

The Commission shall, by written notice, communicate its decision to the feed-in approval holder as soon as practicable.