Skip to content

Section 11

Displaced cost

of Sabah Renewable Energy Recovery Moneys Distribution Licensee Rules 2024

State Subsidiary LegislationIn forceProvision 11 of 11
Section 11
(1)

Subject to subrule (2), the displaced cost in respect of each renewable energy installation shall be as follows:

Particulars

Ringgit per kilowatt-hour

(a)

in respect of a renewable energy installation connected to a supply line at a voltage exceeding 50,000 volts up to and including 230,000 volts alternating current

(b)

in respect of a renewable energy installation connected to a supply line at a voltage exceeding 1,000 volts up to and including 50,000 volts alternating current

(c)

in respect of a renewable energy installation connected to a supply line at a voltage equal to or less than 1,000 volts alternating current 0.2100 0.2200 0.3000

(2)

Following every revision in the tariffs levied by a distribution licensee under subsection 39(1) of the Electricity Supply Enactment 2024 after the date of coming into operation of these Rules, the displaced cost values shall be revised by the Commission, to reflect the change in tariffs due to the changes in the fuel and operational costs of the distribution licensee.

Made this 3 January 2024.

DATUK SERI PANGLIMA HAJI HAJIJI BIN HAJI NOOR,

Chief Minister of Sabah.