Malaysia legislation

Section 7

of Sabah Renewable Energy Recovery Moneys Distribution Licensee Rules 2024

Section 7

Discovery of understatement of claim by distribution licensee

(2)

Upon receipt of the notification under subrule (1), the Commission shall verify the understatement of claim.

(3)

The Commission may, for the purpose of verification under subrule (2), request the distribution licensee to provide any information and other supporting documents within the period specified in the request or any extension of time granted by the

Commission.

(4)

Upon receiving the request under subrule (3), the distribution licensee shall provide such information and other supporting documents within the period specified in the request or any extension of time granted by the Commission.

(5)

Upon the expiry of the period specified in the request or any extension of time granted by the Commission and after the verification under subrule (2) is carried out by taking into consideration the information and other supporting documents referred to in subrule (3), if any, the Commission shall make a decision on the claim.

6

(6)

The decision of the Commission under subrule (5) shall be final and shall, by written notice, be informed to the distribution licensee.

(7)

If the Commission decides under subrule (5) that the distribution licensee has understated the claim under subrule 2(1), the distribution licensee may include the understated amount in its subsequent claim under subrule 2(1).

Payment of claim

Section 7 — Sabah Renewable Energy Recovery Moneys Distribution Licensee Rules 2024