Malaysia legislation

Section 4

of Sabah Renewable Energy Renewable Energy Power Purchase Agreement Rules 2024

Section 4

The distribution licensee shall enter into a renewable energy power purchase agreement with the feed-in approval holder pursuant to rule 3 —

(a)

in respect of a renewable energy installation having a rated kWp of up to and including 1,000kWp and utilizing solar photovaltaic as its renewable resource, within thirty days from the date of receipt of the written notice under subrule 13(1) of the Sabah Renewable Energy (Feed-In Approval and Feed-In Tariff Rate) Rules 2024; and

(b)

in respect of a renewable energy installation other than a renewable energy installation referred to in paragraph (a), within sixty days from the date of receipt of the written notice under subrule 13(1) of the Sabah Renewable

Energy (Feed-In Approval and Feed-In Tariff Rate) Rules 2024.

Types, substance and form of renewable energy power purchase agreement