Section 13

of *RENEWABLE ENERGY ACT 2011

Section 13

(2)

Upon receiving the application under subsection (1), the distribution licensee shall connect the renewable energy installation to a supply line connection point within such period as may be prescribed by the Authority.

(3)

The location of the applicable supply line connection point shall be determined by the distribution licensee, without prejudice to section 15.

20

(4)

A distribution licensee who contravenes subsection (2) commits an offence and shall, on conviction, be liable to a fine not exceeding one million ringgit.

Priority of purchase and distribution