Part III · Connection, Purchase and Distribution of Renewable Energy

13. Connection to supply line

(1)

Where the renewable energy power purchase agreement has been concluded under section 12, a feed-in approval holder may apply to a distribution licensee for connection of his or its renewable energy installation to a supply line connection point in such manner as may be prescribed by the Authority.

(2)

Upon receiving the application under subsection (1), the distribution licensee shall connect the renewable energy installation to a supply line connection point within such period as may be prescribed by the Authority.

(3)

The location of the applicable supply line connection point shall be determined by the distribution licensee, without prejudice to section 15.

20

(4)

A distribution licensee who contravenes subsection (2) commits an offence and shall, on conviction, be liable to a fine not exceeding one million ringgit.

Report

Part IV

Feed-In Tariff

Part V

Renewable Energy Fund

Part VI

Information Gathering Powers

Part VII

Enforcement

Part VIII

General

Part IX

Savings and Transitional

Schedules