Construction Industry Payment and Adjudication Act 2012 · Updated to 22 Jun 2012 · Part IV · Enforcement of Adjudication Decision
29. Suspension or reduction of rate of progress of performance
Feedback & supportA party may suspend performance or reduce the rate of progress of performance of any construction work or construction consultancy services under a construction contract if the adjudicated amount pursuant to an adjudication decision has not been paid wholly or partly after receipt of the adjudicated decision under subsection 12(6).
construction work
“construction work” means the construction, extension, installation, repair, maintenance, renewal, removal, renovation, alteration, dismantling, or demolition of— (a) any building, erection, edifice, structure, wall, fence or chimney, whether constructed wholly or partly above or below ground level; (b) any road, harbour works, railway, cableway, canal or aerodrome; (c) any drainage, irrigation or river control work; (d) any electrical, mechanical, water, gas, oil, petrochemical or telecommunication work; or (e) any bridge, viaduct, dam, reservoir, earthworks, pipeline, sewer, aqueduct, culvert, drive, shaft, tunnel or reclamation work, and includes— (A) any work which forms an integral part of, or are preparatory to or temporary for the works described in paragraphs (a) to (e), including site clearance, soil investigation and improvement, earth-moving, excavation, laying of foundation, site restoration and landscaping; and (B) procurement of construction materials, equipment or workers, as necessarily required for any works described in paragraphs (a) to (e);
The party intending to suspend the performance or reduce the rate of progress of performance under subsection (1) shall give written notice of intention to suspend performance or reduce the rate of progress of performance to the other party if the adjudicated amount is not paid within fourteen calendar days from the date of receipt of the notice.
The party intending to suspend the performance or reduce the rate of progress of performance under subsection (1) shall have the right to suspend performance or reduce the rate of progress of performance of any construction work or construction consultancy services under a construction contract upon the expiry of fourteen calendar days of the service of the notice given under subsection (2).
construction contract
“construction contract” means a construction work contract or construction consultancy contract;
The party who exercises his right under subsection (3)—
is not in breach of contract;
is entitled to a fair and reasonable extension of time to complete his obligations under the contract;
is entitled to recover any loss and expenses incurred as a result of the suspension or reduction in the rate of progress of performance from the other party; and
shall resume performance or the rate of progress of performance of the construction work or construction consultancy services under a construction contract in accordance with the contract within ten working days after having been paid the adjudicated amount or an amount as may be determined by arbitration or the court pursuant to subsection 37(1).