30. Direct payment from principal
Feedback & supportIf a party against whom an adjudication decision was made fails to make payment of the adjudicated amount, the party who obtained the adjudication decision in his favour may make a written request for payment of the adjudicated amount direct from the principal of the party against whom the adjudication decision is made.
adjudication decision
“adjudication decision” means the decision made by an adjudicator under subsection 12(2);
Upon receipt of the written request under subsection (1), the principal shall serve a notice in writing on the party against whom the adjudication decision was made to show proof of payment and to state that direct payment would be made after the expiry of ten working days of the service of the notice.
principal
“principal” means a party who has contracted with and is liable to make payment to another party where that other party has in turn contracted with and is liable to make payment to a further person in a chain of construction contracts;
In the absence of proof of payment requested under subsection (2), the principal shall pay the adjudicated amount to the party who obtained the adjudication decision in his favour.
payment
“payment” means a payment for work done or services rendered under the express terms of a construction contract;
Construction Industry Payment and Adjudication 23
The principal may recover the amount paid under subsection (3) as a debt or set off the same from any money due or payable by the principal to the party against whom the adjudication decision was made.
This section shall only be invoked if money is due or payable by the principal to the party against whom the adjudication decision was made at the time of the receipt of the request under subsection (1).