37. Relationship between adjudication and other dispute resolution process

Feedback & support
(1)

A dispute in respect of payment under a construction contract may be referred concurrently to adjudication, arbitration or the court.

(2)

Subject to subsection (3), a reference to arbitration or the court in respect of a dispute which is being adjudicated shall not bring the adjudication proceedings to an end nor affect the adjudication proceedings.

(3)

An adjudication proceeding is terminated if the dispute being adjudicated is settled by agreement in writing between the parties or decided by arbitration or the court.