PERMULAAN
Nama
/akn/my/act/pua/2025/25
The full official text, structured for quick navigation. Copy any provision or jump straight to a section.
Quick answer
PERATURAN-PERATURAN KESELAMATAN DAN KESIHATAN PEKERJAAN (SKIM PEMERIKSAAN KHAS) 2025 is Malaysia P.U. (A), cited as P.U. (A) 25 2025, currently marked in force and first recorded in 2025.
Opening note
Bahagian I
Nama
Peraturan-peraturan ini bolehlah dinamakan
Peraturan-Peraturan
Keselamatan dan Kesihatan Pekerjaan (Skim Pemeriksaan Khas) 2025.
Tafsiran
“bejana tekanan”
mempunyai erti yang diberikan kepadanya dalam
Peraturan-Peraturan Keselamatan dan Kesihatan Pekerjaan (Loji yang Menghendaki
Perakuan Kelayakan) 2024 [P.U. (A) 99/2024];
“dandang stim”
mempunyai erti yang diberikan kepadanya dalam
Peraturan-Peraturan Keselamatan dan Kesihatan Pekerjaan (Loji yang Menghendaki
Perakuan Kelayakan) 2024;
“data berasaskan risiko” ertinya—
berhubung dengan dandang stim dan bejana tekanan, maklumat perincian reka bentuk dan pengendaliannya, termasuk komposisi bendalir proses, sifat bendalir proses, suhu dan tekanan pengendalian, bahan binaan, spesifikasi reka bentuk, ketebalan semasa, jenis mekanisme kerosakan
5
yang boleh menjejaskan fungsi dandang stim dan bejana tekanan, pemeriksaan dan penyelenggaraan; dan
berhubung dengan jentera mengangkat, maklumat perincian reka bentuk dan pengendaliannya, termasuk bahan binaan, spesifikasi reka bentuk, jenis mekanisme kerosakan yang boleh menjejaskan fungsi jentera mengangkat, pemeriksaan dan penyelenggaraan;
“jentera mengangkat” mempunyai erti yang diberikan kepadanya dalam
Peraturan-Peraturan Keselamatan dan Kesihatan Pekerjaan (Loji yang Menghendaki
Perakuan Kelayakan) 2024;
“loji yang menghendaki perakuan kelayakan” mempunyai erti yang diberikan kepadanya dalam Peraturan-Peraturan Keselamatan dan Kesihatan Pekerjaan
(Loji yang Menghendaki Perakuan Kelayakan) 2024;
“orang berkelayakan” ertinya orang terlatih yang mempunyai pengetahuan, kemahiran dan pengalaman dalam bidang berkaitan untuk melaksanakan apa-apa tugas atau perkhidmatan yang dikehendaki di bawah Peraturan-Peraturan ini;
“pemeriksaan berkala” ertinya pemeriksaan yang dijalankan mengikut peraturan 6 Peraturan-Peraturan Keselamatan dan Kesihatan Pekerjaan (Loji yang
Menghendaki Perakuan Kelayakan) 2024;
“pemeriksaan dalaman” ertinya pemeriksaan yang dijalankan pada bahagian dalam dandang stim dan bejana tekanan dengan menggunakan sama ada teknik visual, ujian tanpa musnah atau kedua-duanya;
“pemeriksaan luaran” ertinya pemeriksaan visual yang dijalankan pada bahagian luar loji yang menghendaki perakuan kelayakan bagi mentaksir keadaan yang boleh menjejaskan integriti loji yang menghendaki perakuan kelayakan dan struktur sokongannya, termasuk peralatan keselamatan loji yang menghendaki perakuan kelayakan itu;
6
“pemeriksaan semasa pengendalian” ertinya pemeriksaan pada bahagian luar dandang stim atau bejana tekanan yang sedang dikendalikan dan pemeriksaan itu dijalankan dengan menggunakan kaedah ujian tanpa musnah yang wajar untuk mengesan kecacatan pada dandang stim atau bejana tekanan itu berdasarkan mekanisme kerosakan;
“penganalisisan berasaskan risiko” ertinya suatu pemeriksaan dalaman dan pemeriksaan luaran termasuk ujian tanpa musnah yang dijalankan oleh penghuni terhadap suatu loji yang menghendaki perakuan kelayakan yang lat tempoh pemeriksaannya ditentukan berdasarkan risiko yang berkaitan dengan loji yang menghendaki perakuan kelayakan itu.
Bahagian II
Permohonan untuk kelulusan bagi skim pemeriksaan khas
Mana-mana penghuni boleh memohon kepada Ketua Pengarah untuk kelulusan bagi skim pemeriksaan khas—
bagi dandang stim dan bejana tekanan yang hendaklah dikenali sebagai skim pemeriksaan khas kelas A; atau
bagi semua loji yang menghendaki perakuan kelayakan yang hendaklah dikenali sebagai skim pemeriksaan khas kelas B, sekurang-kurangnya enam bulan sebelum habis tempoh perakuan kelayakan loji yang menghendaki perakuan kelayakannya bersama-sama dengan pembayaran fi sebagaimana yang dinyatakan dalam Jadual Pertama.
Kehendak bagi skim pemeriksaan khas kelas A
Mana-mana penghuni yang memohon untuk kelulusan bagi skim pemeriksaan khas kelas A hendaklah memenuhi kehendak berkenaan dengan dandang stim dan bejana tekanan seperti yang berikut:
7
penghuni hendaklah menubuhkan, melaksanakan dan menyenggarakan suatu sistem pengurusan keselamatan dan kesihatan pekerjaan sebagaimana yang dipersetujui oleh Ketua Pengarah;
penghuni hendaklah menyenaraikan satu atau lebih dandang stim dan bejana tekanan di suatu tempat kerja dan memastikan bahawa dandang stim dan bejana tekanan itu adalah dalam keadaan kerja yang memuaskan dan selamat untuk digunakan;
penghuni hendaklah memastikan setiap dandang stim dan bejana tekanan itu mempunyai perakuan kelayakan yang sah;
data berasaskan risiko bagi dandang stim dan bejana tekanan yang dikira dan ditaksir mengikut metodologi sebagaimana yang ditentukan oleh Ketua Pengarah; dan
maklumat ketebalan dandang stim dan bejana tekanan yang dikumpulkan mengikut mana-mana kaedah yang berikut:
pemeriksaan di bawah seksyen 27D Akta dan dua kali pemeriksaan berkala dandang stim dan bejana tekanan;
tiga kali pemeriksaan berkala dandang stim dan bejana tekanan;
pengukuran ketebalan dandang stim dan bejana tekanan hendaklah dilakukan tidak kurang daripada tiga kali semasa dandang stim dan bejana tekanan itu sedang beroperasi pada lat tempoh tidak kurang daripada dua belas bulan selepas setiap pengukuran; atau 8
pengukuran ketebalan dandang stim dan bejana tekanan hendaklah dilakukan tidak kurang daripada tiga kali semasa dandang stim dan bejana tekanan itu tidak beroperasi pada lat tempoh tidak kurang daripada dua belas bulan selepas setiap pengukuran;
pengukuran ketebalan dandang stim dan bejana tekanan di bawah subperenggan (d)(ii) hendaklah dilakukan mengikut kaedah yang diluluskan oleh Ketua Pengarah melainkan jika pengukuran itu dilakukan dengan menggunakan kaedah yang diterima secara amnya;
penghuni hendaklah mengemukakan kepada Ketua Pengarah maklumat mengenai baki hayat, kategori risiko, lat tempoh pemeriksaan dan pelan pemeriksaan bagi dandang stim dan bejana tekanan yang diperoleh melalui pengiraan dan pentaksiran data dan maklumat yang dikumpul mengikut perenggan (d);
penghuni hendaklah mempunyai satu atau lebih pasukan berasaskan risiko sebagaimana yang ditentukan oleh Ketua Pengarah yang terdiri daripada sekurang-kurangnya lima orang anggota seperti yang berikut:
seorang orang berkelayakan yang mempunyai ijazah kejuruteraan sebagai ketua pasukan untuk melaksanakan semua tugasan yang berhubungan dengan pemeriksaan integriti dandang stim dan bejana tekanan;
seorang orang berkelayakan dengan pengetahuan dan kepakaran dalam kejuruteraan kakisan;
seorang orang berkelayakan daripada bahagian proses atau bahagian pengeluaran;
9
seorang orang berkelayakan daripada bahagian pemeriksaan atau bahagian kejuruteraan; dan
seorang pegawai keselamatan dan kesihatan yang berdaftar di bawah Peraturan-Peraturan Keselamatan dan Kesihatan
Pekerjaan
(Pegawai
Keselamatan dan
Kesihatan)
1997
[P.U. (A) 315/1997] atau orang yang bertanggungjawab bagi keselamatan dan kesihatan pekerjaan jika tempat kerja itu tidak menghendaki seorang pegawai keselamatan dan kesihatan yang berdaftar itu; dan
penghuni hendaklah mengemukakan dokumen sebagaimana yang dinyatakan dalam Jadual Kedua.
Kehendak bagi skim pemeriksaan khas kelas B
Mana-mana penghuni yang memohon untuk kelulusan bagi skim pemeriksaan khas kelas B hendaklah memenuhi kehendak berkenaan dengan loji yang menghendaki perakuan kelayakan seperti yang berikut:
penghuni hendaklah menubuhkan, melaksanakan dan menyenggarakan suatu sistem pengurusan loji yang dikendalikan oleh suatu pasukan pengurusan loji mengikut tataamalan industri yang diluluskan oleh Menteri;
penghuni hendaklah menyenaraikan semua loji yang menghendaki perakuan kelayakan yang dipasang di suatu tempat kerja mengikut kategori yang berikut:
loji yang menghendaki perakuan kelayakan yang telah dipasang bagi tempoh tiga puluh enam bulan atau lebih dari tarikh permohonan; dan 10
loji yang menghendaki perakuan kelayakan yang telah dipasang bagi tempoh tidak lebih daripada tiga puluh enam bulan dari tarikh permohonan, jika ada;
penghuni hendaklah memastikan loji yang menghendaki perakuan kelayakan itu dalam keadaan kerja yang memuaskan dan selamat untuk digunakan;
penghuni hendaklah memastikan semua loji yang menghendaki perakuan kelayakan mempunyai perakuan kelayakan yang sah;
data berasaskan risiko bagi dandang stim dan bejana tekanan yang dikira dan ditaksir mengikut metodologi sebagaimana yang ditentukan oleh Ketua Pengarah; dan
maklumat ketebalan dandang stim dan bejana tekanan yang dikumpulkan mengikut mana-mana kaedah yang berikut:
pemeriksaan di bawah seksyen 27D Akta dan dua kali pemeriksaan berkala dandang stim dan bejana tekanan;
tiga kali pemeriksaan berkala dandang stim dan bejana tekanan;
pengukuran ketebalan dandang stim dan bejana tekanan hendaklah dilakukan tidak kurang daripada tiga kali semasa dandang stim dan bejana tekanan itu sedang beroperasi pada lat tempoh tidak kurang daripada dua belas bulan selepas setiap pengukuran; atau 11
pengukuran ketebalan dandang stim dan bejana tekanan hendaklah dilakukan tidak kurang daripada tiga kali semasa dandang stim dan bejana tekanan itu tidak beroperasi pada lat tempoh tidak kurang daripada dua belas bulan selepas setiap pengukuran;
pengukuran ketebalan dandang stim dan bejana tekanan di bawah perenggan (e)(ii) hendaklah dilakukan mengikut kaedah yang diluluskan oleh Ketua Pengarah melainkan jika pengukuran itu dilakukan dengan menggunakan kaedah yang diterima secara amnya;
jika loji yang menghendaki perakuan kelayakan ialah dandang stim dan bejana tekanan, penghuni hendaklah mengemukakan kepada
Ketua Pengarah maklumat mengenai baki hayat, kategori risiko, lat tempoh pemeriksaan dan pelan pemeriksaan bagi dandang stim dan bejana tekanan yang diperoleh melalui pengiraan dan pentaksiran data dan maklumat yang dikumpul mengikut perenggan (e);
jika loji yang menghendaki perakuan kelayakan ialah jentera mengangkat, penghuni hendaklah mengemukakan kepada Ketua Pengarah maklumat kategori risiko, lat tempoh pemeriksaan dan pelan pemeriksaan bagi jentera mengangkat itu;
penghuni hendaklah memastikan bahawa tiada kematian, kecederaan badan yang serius, penyakit, keracunan pekerjaan atau kejadian berbahaya yang diakibatkan oleh aktiviti pemasangan, pembaikan, pembukaan, pengendalian dan penyenggaraan loji yang menghendaki perakuan kelayakan dalam tempoh dua tahun sebelum tarikh permohonan;
penghuni hendaklah memastikan bahawa tiada kejadian yang boleh menjejaskan integriti loji yang menghendaki perakuan kelayakan berlaku dalam tempoh dua tahun sebelum tarikh permohonan;
12
penghuni hendaklah mempunyai satu atau lebih pasukan berasaskan risiko sebagaimana yang ditentukan oleh Ketua Pengarah yang terdiri daripada sekurang-kurangnya lima orang anggota seperti yang berikut:
seorang orang berkelayakan yang mempunyai ijazah kejuruteraan sebagai ketua pasukan untuk melaksanakan semua tugasan yang berhubungan dengan pemeriksaan integriti loji yang menghendaki perakuan kelayakan;
seorang orang berkelayakan dengan pengetahuan dan kepakaran dalam kejuruteraan kakisan;
seorang orang berkelayakan daripada bahagian proses atau bahagian pengeluaran;
seorang orang berkelayakan daripada bahagian pemeriksaan atau bahagian kejuruteraan; dan
seorang pegawai keselamatan dan kesihatan yang berdaftar di bawah Peraturan-Peraturan Keselamatan dan Kesihatan
Pekerjaan
(Pegawai
Keselamatan dan
Kesihatan)
1997
[P.U. (A) 315/1997] atau orang yang bertanggungjawab bagi keselamatan dan kesihatan pekerjaan jika tempat kerja itu tidak menghendaki seorang pegawai keselamatan dan kesihatan yang berdaftar itu; dan
penghuni hendaklah mengemukakan dokumen sebagaimana yang dinyatakan dalam Jadual Kedua.
Maklumat atau dokumen tambahan 6.
Ketua Pengarah boleh, melalui notis secara bertulis pada bila-bila masa selepas permohonan bagi skim pemeriksaan khas diterima, menghendaki penghuni untuk memberikan apa-apa maklumat atau dokumen tambahan kepada Ketua Pengarah
13
dalam tempoh yang dinyatakan dalam notis itu atau apa-apa tempoh lanjutan yang diberikan oleh Ketua Pengarah.
Jika maklumat atau dokumen tambahan yang dikehendaki di bawah subperaturan (1) tidak diberikan oleh penghuni dalam tempoh sebagaimana yang dinyatakan dalam notis atau apa-apa tempoh lanjutan yang diberikan oleh
Ketua Pengarah, permohonan itu hendaklah disifatkan telah ditarik balik tanpa menjejaskan hak penghuni untuk membuat permohonan baharu.
Kelulusan skim pemeriksaan khas 7.
Ketua
Pengarah boleh meluluskan permohonan bagi skim pemeriksaan khas sebagai sama ada skim pemeriksaan khas kelas A atau skim pemeriksaan khas kelas B, di bawah peraturan 3 jika Ketua Pengarah berpuas hati bahawa kehendak di bawah peraturan 4 atau 5, mengikut mana-mana yang berkenaan, telah dipenuhi.
Tertakluk kepada subperaturan (1), Ketua Pengarah boleh mengeluarkan perakuan kelulusan bagi skim pemeriksaan khas kelas A atau skim pemeriksaan khas kelas B kepada penghuni yang hendaklah mengandungi butiran sebagaimana yang dinyatakan dalam Jadual Ketiga.
Seseorang penghuni yang skim pemeriksaan khasnya diluluskan oleh
Ketua Pengarah hanya boleh memegang satu kelas skim pemeriksaan khas pada satu-satu masa.
Seseorang penghuni yang telah memperoleh kelulusan bagi skim pemeriksaan khas kelas B oleh Ketua Pengarah tidak boleh memegang kelulusan bagi apa-apa skim pemeriksaan khas kelas B yang lain pada masa yang sama dan mana-mana skim pemeriksaan khas kelas A sedia ada yang diperoleh penghuni adalah terbatal.
14
Tempoh skim pemeriksaan khas 8.
Skim pemeriksaan khas kelas A hendaklah sah bagi tempoh satu ratus dua puluh bulan dari tarikh kelulusan permohonan bagi skim pemeriksaan khas itu melainkan jika dibatalkan atau ditamatkan lebih awal.
Skim pemeriksaan khas kelas B hendaklah sah bagi tempoh satu ratus lapan puluh bulan dari tarikh kelulusan permohonan bagi skim pemeriksaan khas itu melainkan jika dibatalkan atau ditamatkan lebih awal.
Kesahan perakuan kelayakan bagi loji yang menghendaki perakuan kelayakan di bawah skim pemeriksaan khas 9.
Kesahan perakuan kelayakan bagi loji yang menghendaki perakuan kelayakan di bawah skim pemeriksaan khas hendaklah tidak melebihi enam puluh bulan sebagaimana yang ditentukan oleh pegawai berdasarkan keputusan pengiraan dan pentaksiran data berasaskan risiko yang dikemukakan oleh penghuni.
Bahagian III
Kewajipan penghuni di bawah skim pemeriksaan khas kelas A
Seseorang penghuni dengan kelulusan bagi skim pemeriksaan khas kelas A hendaklah—
memastikan tiada kematian, kecederaan badan yang serius, keracunan, penyakit atau kejadian berbahaya yang berlaku akibat daripada pemasangan atau penggunaan loji yang menghendaki perakuan kelayakan;
memastikan data berasaskan risiko dikumpul oleh pasukan berasaskan risiko pada lat tempoh tidak melebihi dua belas bulan selepas setiap pengumpulan data;
menyimpan dan menyenggarakan data berasaskan risiko yang dikemukakan oleh pasukan berasaskan risiko;
15
menentukan baki hayat, kategori risiko, lat tempoh pemeriksaan dan pelan pemeriksaan bagi dandang stim dan bejana tekanan berdasarkan pengiraan dan pentaksiran data berasaskan risiko;
menyenggarakan dan memakai metodologi bagi pengiraan dan pentaksiran data berasaskan risiko di bawah subperenggan 4(d)(i);
memberitahu Ketua Pengarah secara bertulis mengenai apa-apa perubahan ketua pasukan berasaskan risiko dalam tempoh tiga puluh hari dari tarikh perubahan itu;
menyenggarakan sistem pengurusan keselamatan dan kesihatan pekerjaan di bawah perenggan 4(a);
menyimpan dan menyenggarakan rekod penggunaan dan penyenggaraan dandang stim dan bejana tekanan;
memastikan bahawa tiap-tiap anggota pasukan berasaskan risiko sentiasa kompeten.
Kewajipan penghuni di bawah skim pemeriksaan khas kelas B
Seseorang penghuni dengan kelulusan bagi skim pemeriksaan khas kelas B hendaklah—
memastikan tiada kematian, kecederaan badan yang serius, keracunan, penyakit atau kejadian berbahaya yang berlaku akibat daripada pemasangan atau penggunaan loji yang menghendaki perakuan kelayakan;
memastikan data berasaskan risiko dikumpul oleh pasukan berasaskan risiko pada lat tempoh tidak melebihi dua belas bulan selepas setiap pengumpulan data;
16
menyimpan dan menyenggarakan data berasaskan risiko yang dikemukakan oleh pasukan berasaskan risiko;
menentukan baki hayat, kategori risiko, lat tempoh pemeriksaan dan pelan pemeriksaan bagi dandang stim dan bejana tekanan berdasarkan pengiraan dan pentaksiran data berasaskan risiko;
menyenggarakan dan memakai metodologi bagi pengiraan dan pentaksiran data berasaskan risiko di bawah subperenggan 5(e)(i);
memberitahu Ketua Pengarah secara bertulis mengenai apa-apa perubahan ketua pasukan berasaskan risiko dalam tempoh tiga puluh hari dari tarikh perubahan itu;
memastikan bahawa tiap-tiap anggota pasukan berasaskan risiko sentiasa kompeten.
Bahagian IV
Pemeriksaan khas bagi loji yang menghendaki perakuan kelayakan 12.
Penghuni hendaklah memohon kepada pegawai untuk suatu pemeriksaan khas bagi loji yang menghendaki perakuan kelayakan bersama-sama dengan pembayaran fi sebagaimana yang dinyatakan dalam Jadual Pertama.
17
Penghuni hendaklah memastikan loji yang menghendaki perakuan kelayakan tersedia bagi pemeriksaan khas itu.
Pemeriksaan khas hendaklah dijalankan mengikut cara yang berikut—
bagi pemeriksaan khas kali pertama selepas kelulusan skim pemeriksan khas, loji yang menghendaki perakuan kelayakan hendaklah bersedia bagi kedua-dua pemeriksaan dalaman dan pemeriksaan luaran;
dandang stim dan bejana tekanan di bawah skim pemeriksaan khas kelas A hendaklah bersedia bagi kedua-dua pemeriksaan dalaman dan pemeriksaan luaran; dan
loji yang menghendaki perakuan kelayakan di bawah skim pemeriksaan khas kelas B hendaklah bersedia bagi pemeriksaan semasa pengendalian dan pemeriksaan luaran.
Sekiranya penghuni mendapati pemeriksaan dalaman tidak sesuai untuk dijalankan, penghuni hendaklah memohon kepada Ketua Pengarah bagi pemeriksaan semasa pengendalian.
Ketua Pengarah boleh meluluskan atau menolak permohonan penghuni di bawah subperaturan (4).
Jika Ketua Pengarah menolak permohonan penghuni di bawah subperaturan (5), pemeriksaan dalaman hendaklah dijalankan terhadap loji yang menghendaki perakuan kelayakan.
18
Penambahan, pengurangan dan perubahan maklumat kepada senarai loji yang menghendaki perakuan kelayakan di bawah skim pemeriksaan khas 13.
Jika terdapat apa-apa penambahan, pengurangan atau perubahan maklumat kepada senarai loji yang menghendaki perakuan kelayakan di bawah skim pemeriksaan khas kelas B yang diluluskan, penghuni hendaklah mengemukakan permohonan untuk meminda senarai loji yang menghendaki perakuan kelayakan bagi skim pemeriksaan khas yang diluluskan itu bagi suatu tempoh tidak lebih daripada empat puluh lapan bulan dari tarikh penambahan, pengurangan atau perubahan maklumat itu bersama-sama dengan pembayaran fi sebagaimana yang dinyatakan dalam Jadual Pertama.
Pemeriksaan verifikasi 14.
Seseorang penghuni yang diberikan kelulusan bagi skim pemeriksaan khas hendaklah tertakluk kepada pemeriksaan verifikasi.
Penghuni yang memperoleh skim pemeriksaan khas kelas A hendaklah memohon untuk suatu pemeriksaan verifikasi dalam tempoh enam bulan selepas suatu pemeriksaan khas dijalankan bersama-sama dengan pembayaran fi sebagaimana yang dinyatakan dalam Jadual Pertama.
Penghuni yang memperoleh skim pemeriksaan khas kelas B hendaklah memohon untuk suatu pemeriksaan verifikasi dalam tempoh tidak lebih daripada enam bulan sebelum suatu pemeriksaan khas dijalankan bersama-sama dengan pembayaran fi sebagaimana yang dinyatakan dalam Jadual Pertama.
Bahagian V
Pembatalan skim pemeriksaan khas 15.
Ketua Pengarah boleh membatalkan mana-mana skim pemeriksaan khas yang telah diluluskan jika penghuni memberikan apa-apa dokumen atau maklumat yang dikehendaki di bawah Peraturan-Peraturan ini yang palsu, mengelirukan atau mengandungi kesilapan atau peninggalan yang material.
19
Penamatan skim pemeriksaan khas 16.
Ketua Pengarah boleh menamatkan mana-mana skim pemeriksaan khas yang telah diluluskan jika—
penghuni yang mendapat kelulusan skim pemeriksaan khas didapati tidak mematuhi kewajipan yang dinyatakan dalam peraturan 10 atau 11, mengikut mana-mana yang berkenaan;
terdapat perubahan penghuni bagi loji yang menghendaki kelayakan yang berada di bawah skim pemeriksaan khas; atau
perakuan kelayakan bagi semua loji yang menghendaki kelayakan yang berada di bawah skim pemeriksaan khas itu ditamatkan di bawah subseksyen 27D(8).
Penamatan sukarela skim pemeriksaan khas 17.
Penghuni hendaklah memberitahu Ketua Pengarah secara bertulis bagi maksud penamatan sukarela mana-mana skim pemeriksaan khas yang telah diluluskan bagi mana-mana atau semua loji yang menghendaki perakuan kelayakan.
Perakuan kelayakan loji yang menghendaki perakuan kelayakan di bawah mana-mana skim pemeriksaan khas hendaklah terbatal sama ada pada tarikh habis tempoh perakuan kelayakan loji yang menghendaki perakuan kelayakan atau pada hari terakhir bulan keenam selepas tarikh skim pemeriksaan khas ditamatkan secara sukarela, mengikut mana-mana yang lebih awal.
Bahagian VI
Perubahan berhubung dengan loji yang menghendaki perakuan kelayakan di bawah skim pemeriksaan khas 18.
Penghuni hendaklah memberitahu Ketua Pengarah secara bertulis dalam tempoh tiga puluh hari mengenai apa-apa perubahan yang berikut:
20
penjualan, penyewaan atau pemindahan hak milik mana-mana loji yang menghendaki perakuan kelayakan di bawah skim pemeriksaan khas kepada mana-mana orang; atau
tekanan kerja selamat berkenaan dengan dandang stim dan bejana tekanan atau beban kerja selamat berkenaan dengan jentera mengangkat di bawah skim pemeriksaan khas.
Jika mana-mana loji yang menghendaki perakuan kelayakan yang berada di bawah mana-mana skim pemeriksaan khas dijual, disewakan atau dipindahkan hak milik secara tetap atau sementara oleh penghuni yang telah mendapat kelulusan skim pemeriksaan khas kepada mana-mana orang, loji yang menghendaki perakuan kelayakan itu hendaklah disifatkan telah dikeluarkan daripada skim pemeriksaan khas itu.
Fi yang tidak boleh dibayar balik 19.
Apa-apa fi yang dibayar di bawah Peraturan-Peraturan ini tidak boleh dibayar balik.
21
JADUAL PERTAMA
[Peraturan 3 dan 13 dan subperaturan 12(1), 14(2) dan 14(3)]
FI
(1)
Bil.
(2)
Perkara
(3)
Skim pemeriksaan khas kelas A
Skim pemeriksaan khas kelas B
1.
Permohonan untuk kelulusan bagi skim pemeriksaan khas:
bagi loji yang menghendaki perakuan kelayakan yang pertama
bagi tiap-tiap loji yang menghendaki perakuan kelayakan selanjutnya
51,000
1,000
81,000
1,000
2.
Permohonan untuk pemeriksaan khas bagi dandang stim:
Kategori 1
(a)
Permukaan pemanasan kurang daripada 5 meter persegi
(b)
Permukaan pemanas 5
meter persegi dan ke atas tetapi kurang daripada 10 meter persegi
(c)
Permukaan pemanasan 10
meter persegi dan ke atas tetapi kurang daripada 25 meter persegi
(d)
Permukaan pemanasan 25
meter persegi dan ke atas tetapi kurang daripada 50 meter persegi
300
800
1,050
1,300
300
800
1,050
1,300
22
(1)
Bil.
(2)
Perkara
(3)
Skim pemeriksaan khas kelas A
Skim pemeriksaan khas kelas B
(e)
Permukaan pemanasan 50
meter persegi dan ke atas tetapi kurang daripada 100 meter persegi
(f)
Permukaan pemanasan 100 meter persegi dan ke atas tetapi kurang daripada 250 meter persegi
(g)
Permukaan pemanasan 250 meter persegi dan ke atas
Kategori 2
Dandang stim elektrik, ketuhar tiub stim, plat panas tiub stim, autoklaf atau penjimat haba
Kategori 3
Pemanas lampau
1,600
2,000
2,400
300
300
1,600
2,000
2,400
300
300 3.
Permohonan untuk pemeriksaan khas bagi bejana tekanan
Kapasiti kurang daripada 0.1 meter padu
Kapasiti 0.1 meter padu dan ke atas tetapi kurang daripada 0.5 meter padu
Kapasiti 0.5 meter padu dan ke atas tetapi kurang daripada 5 meter padu
Kapasiti 5 meter padu dan ke atas tetapi kurang daripada 10 meter padu
140
200
300
400
140
200
300
400
23
(1)
Bil.
(2)
Perkara
(3)
Skim pemeriksaan khas kelas A
Skim pemeriksaan khas kelas B
Kapasiti 10 meter padu dan ke atas tetapi kurang daripada 15
meter padu
Kapasiti 15 meter padu dan ke atas
550
700 550
700 4.
Permohonan untuk pemeriksaan khas bagi kren bergerak
(1)
Beban kerja selamat kurang daripada 25,000 kilogram
(2)
Beban kerja selamat 25,000 kilogram dan ke atas tetapi kurang daripada 50,000 kilogram
(3)
Beban kerja selamat 50,000
kilogram dan ke atas tetapi kurang daripada 250,000 kilogram
(4)
Beban kerja selamat 250,000 kilogram dan ke atas
-
-
-
-
550
700
850
1,000
5.
Permohonan untuk pemeriksaan khas bagi kren menara dan kren dermaga
-
1,300 6.
Permohonan untuk pemeriksaan khas bagi kren yang lain
Beban kerja selamat kurang daripada 3,000 kilogram
Beban kerja selamat 3,000 kilogram dan ke atas tetapi kurang daripada 5,000 kilogram
-
-
350
600
24
(1)
Bil.
(2)
Perkara
(3)
Skim pemeriksaan khas kelas A
Skim pemeriksaan khas kelas B
Beban kerja selamat 5,000 kilogram dan ke atas tetapi kurang daripada 10,000 kilogram
Beban kerja selamat 10,000 kilogram dan ke atas tetapi kurang daripada 20,000 kilogram
Beban kerja selamat 20,000 kilogram dan ke atas
-
-
-
750
950
1,200 7.
Permohonan untuk pemeriksaan khas bagi pengangkat
Pengangkat benda:
(a)
Beban kerja selamat kurang daripada 500 kilogram
(b)
Beban kerja selamat 500 kilogram dan ke atas tetapi kurang daripada 1,000 kilogram
(c)
Beban kerja selamat 1,000
kilogram dan ke atas tetapi kurang daripada 1,500 kilogram
(d)
Beban kerja selamat 1,500
kilogram dan ke atas
Pengangkat penumpang
-
-
-
-
-
350
600
750
1,000
1,000
8.
Permohonan untuk pemeriksaan khas bagi kelengkapan akses gantung
-
350 9.
Permohonan untuk pemeriksaan khas bagi gantri pelancaran
-
2,000
25
(1)
Bil.
(2)
Perkara
(3)
Skim pemeriksaan khas kelas A
Skim pemeriksaan khas kelas B
10. Permohonan untuk pemeriksaan khas bagi kereta api funikular
-
2,000
11. Permohonan untuk pemeriksaan khas bagi pelantar kerja aerial
Kuasa kurang daripada 15 kilowatt
Kuasa 15 kilowatt dan ke atas tetapi kurang daripada 37 kilowatt
Kuasa 37 kilowatt dan ke atas tetapi kurang daripada 75 kilowatt
Kuasa 75 kilowatt dan ke atas
-
-
-
-
350
600
750
950
12. Permohonan untuk pemeriksaan khas bagi lif
(1)
Jarak perjalanan kurang daripada 12 meter
(2)
Jarak pergerakan 12 meter dan ke atas tetapi kurang daripada 30 meter
(3)
Jarak pergerakan 30 meter dan ke atas tetapi kurang daripada 80 meter
(4)
Jarak pergerakan 80 meter dan ke atas tetapi kurang daripada 140 meter
(5)
Jarak pergerakan 140 meter dan ke atas tetapi kurang daripada 300 meter
-
-
-
-
-
650
750
1,300
1,500
1,700
26
(1)
Bil.
(2)
Perkara
(3)
Skim pemeriksaan khas kelas A
Skim pemeriksaan khas kelas B
(6)
Jarak pergerakan 300 meter dan ke atas
-
1,900
13. Permohonan untuk pemeriksaan khas bagi eskalator atau laluan gerak
-
350
14. Permohonan untuk pemeriksaan khas bagi jentera mengangkat yang lain
Kuasa kurang daripada 15 kilowatt
Kuasa 15 kilowatt dan ke atas tetapi kurang daripada 37 kilowatt
Kuasa 37 kilowatt dan ke atas tetapi kurang daripada 75 kilowatt
Kuasa 75 kilowatt ke atas
-
-
-
-
350
600
750
950
15. Permohonan untuk pemeriksaan verifikasi
25,000 40,000
16. Permohonan untuk meminda senarai loji yang menghendaki perakuan kelayakan bagi skim pemeriksaan khas yang diluluskan:
(a)
bagi apa-apa penambahan loji kepada senarai yang menghendaki perakuan kelayakan
(b)
bagi apa-apa pengurangan kepada senarai loji yang menghendaki perakuan kelayakan
-
-
1,000
bagi tiap-tiap loji yang menghendaki perakuan kelayakan
-
27
(1)
Bil.
(2)
Perkara
(3)
Skim pemeriksaan khas kelas A
Skim pemeriksaan khas kelas B
(c)
bagi apa-apa perubahan maklumat kepada senarai loji yang menghendaki perakuan kelayakan
-
-
JADUAL KEDUA
[Perenggan 4(h) dan 5(l)]
DOKUMEN PENGISYTIHARAN PEMATUHAN
1.
Senarai loji yang menghendaki perakuan kelayakan 2.
Jangka hayat loji yang menghendaki perakuan kelayakan 3.
Kategori risiko bagi dandang stim, bejana tekanan dan jentera mengangkat 4.
Pengesahan bahawa loji yang menghendaki perakuan kelayakan adalah dalam keadaan kerja yang memuaskan atau sesuai untuk digunakan
28
JADUAL KETIGA
[Subperaturan 7(2)]
BUTIRAN SIJIL KELULUSAN SKIM PEMERIKSAAN KHAS
1.
Jenis skim pemeriksaan khas yang diluluskan 2.
Nombor skim pemeriksaan khas yang diluluskan 3.
Nama pemegang skim pemeriksaan khas 4.
Alamat pemegang skim pemeriksaan khas 5.
Tempat pengendalian loji yang menghendaki perakuan kelayakan di bawah skim pemeriksaan khas 6.
Senarai loji yang menghendaki perakuan kelayakan di bawah skim pemeriksaan khas 7.
Tempoh skim pemeriksaan khas 8.
Tarikh kelulusan bagi skim pemeriksaan khas
Dibuat 15 Januari 2025
[KSM.PUU(S)600-1/2/9/8(11); PN(PU2)541/JLD.14]
SIM CHEE KEONG
Menteri Sumber Manusia
29
OCCUPATIONAL SAFETY AND HEALTH ACT 1994
______________________________
IN exercise of the powers conferred by sections 27F and 66
of the
Occupational Safety and Health Act 1994 [Act 514], the Minister makes the following regulations:
PART I
PRELIMINARY
Citation 1.
These regulations may be cited as the Occupational Safety and Health (Special
Scheme of Inspection) Regulations 2025.
Interpretation 2.
In these Regulations—
“pressure vessel” has the meaning assigned to it in the Occupational Safety and
Health (Plant Requiring Certificate of Fitness) Regulations 2024 [P.U. (A) 99/2024];
“steam boiler” has the meaning assigned to it in the Occupational Safety and
Health (Plant Requiring Certificate of Fitness) Regulations 2024;
“risk-based data” means—
(a)
in relation to steam boiler and pressure vessel, information on the details of its design and operation, including the composition of process fluid, properties of process fluid, operating temperature and pressure, building material, design specification, current thickness, type of damage mechanism that may affect the function of the steam boiler and pressure vessel, inspection and maintenance; and
32
(b)
in relation to lifting machinery, information on the details of its design and operation, including building material, design specification, type of damage mechanism that may affect the function of the lifting machinery, inspection and maintenance;
“lifting machinery” has the meaning assigned to it in the Occupational Safety and Health (Plant Requiring Certificate of Fitness) Regulations 2024;
“plant requiring certificate of fitness” has the meaning assigned to it in the Occupational Safety and Health (Plant Requiring Certificate of Fitness)
Regulations 2024;
“qualified person” means a trained person who has the knowledge, skills and experience in the relevant field to perform any task or service required under these Regulations;
“periodical inspection” means an inspection carried out in accordance with regulation 6 of the Occupational Safety and Health (Plant Requiring Certificate of Fitness)
Regulations 2024;
“internal inspection” means an inspection carried out on the interior of a steam boiler and pressure vessel using whether a visual technique, non-destructive testing or both;
“external inspection” means a visual inspection carried out on the exterior of a plant requiring certificate of fitness to assess conditions that may affect the integrity of the plant requiring certificate of fitness and its support structure, including the safety equipment of the plant requiring certificate of fitness;
“inspection during operation” means an inspection on the exterior of a steam boiler or pressure vessel which is in operation and the inspection is carried out using appropriate non-destructive testing methods to detect defects in the steam boiler or pressure vessel based on the damage mechanism;
33
“risk-based analysis” means an internal inspection and external inspection, including a non-destructive test carried out by an occupier on a plant requiring certificate of fitness whose inspection intervals are determined based on the risks associated with the plant requiring certificate of fitness.
PART II
SPECIAL SCHEME OF INSPECTION
Application for approval for special scheme of inspection 3.
Any occupier may apply to the Director General for approval for a special scheme of inspection—
(a)
for a steam boiler and a pressure vessel which shall be known as special scheme of inspection of class A; or
(b)
for all plants requiring certificate of fitness which shall be known as special scheme of inspection of class B, at least six months before the expiry of the certificate of fitness of his plant requiring certificate of fitness together with the payment of fees as specified in the First Schedule.
Requirements for special scheme of inspection of class A
4.
Any occupier who applies for approval for a special scheme of inspection of class A shall fulfil the requirements in respect of a steam boiler and a pressure vessel as follows:
(a)
the occupier shall establish, implement and maintain an occupational safety and health management system as agreed by the Director General;
(b)
the occupier shall list one or more steam boilers and pressure vessels at a place of work and ensure that the steam boiler and pressure vessel are in satisfactory working condition and safe for use;
34
(c)
the occupier shall ensure that each of the steam boilers and pressure vessels has a valid certificate of fitness;
(d)
the occupier shall submit to the Director General—
(i)
the risk-based data for the steam boiler and pressure vessel which is calculated and assessed in accordance with the methodology as determined by the Director General; and
(ii)
the information on the thickness of the steam boiler and pressure vessel which is collected in accordance with any of the following methods:
an inspection under section 27D of the Act and two periodical inspections of the steam boiler and pressure vessel;
three periodical inspections of the steam boiler and pressure vessel;
the measurement of the thickness of the steam boiler and pressure vessel shall be done not less than three times while the steam boiler and pressure vessel are in operation at intervals of not less than twelve months after each measurement; or the measurement of the thickness of the steam boiler and pressure vessel shall be done not less than three times while the steam boiler and pressure vessel are not in operation at intervals of not less than twelve months after each measurement;
35
(e)
the measurement of the thickness of the steam boiler and pressure vessel under subparagraph (d)(ii) shall be done in accordance with the method approved by the Director General unless the measurement is done using a method that is generally accepted;
(f)
the occupier shall submit to the Director General the information on remnant life, risk category, inspection interval and inspection plan for the steam boiler and pressure vessel obtained through the calculation and assessment of data and information collected in accordance with paragraph (d);
(g)
the occupier shall have one or more risk-based teams as determined by the Director General consisting of at least five members as follows:
(i)
a qualified person with an engineering degree as the team leader to perform all tasks relating to the inspection of the integrity of the steam boilers and pressure vessels;
(ii)
a qualified person with knowledge and expertise in corrosion engineering;
(iii)
a qualified person from the process department or production department;
(iv)
a qualified person from the inspection department or engineering department; and
(v)
a safety and health officer registered under the Occupational Safety and Health (Safety and Health Officer) Regulations 1997
[P.U. (A) 315/1997] or the person responsible for occupational safety and health if the place of work does not require such registered safety and health officer; and
36
(h)
the occupier shall submit the documents as specified in the
Second Schedule.
Requirements for special scheme of inspection of class B
5.
Any occupier who applies for approval for a special scheme of inspection of class B shall fulfil the requirements in respect of the plant requiring certificate of fitness as follows:
(a)
the occupier shall establish, implement and maintain a plant management system operated by a plant management team in accordance with the industry codes of practice as approved by the Minister;
(b)
the occupier shall list all plants requiring certificate of fitness installed at a place of work in accordance with the following categories:
(i)
a plant requiring certificate of fitness which has been installed for a period of thirty-six months or more from the date of application; and
(ii)
a plant requiring certificate of fitness which has been installed for a period of not more than thirty-six months from the date of application, if any;
(c)
the occupier shall ensure that the plant requiring the certificate of fitness is in a satisfactory working condition and safe for use;
(d)
the occupier shall ensure that all plants requiring certificate of fitness have a valid certificate of fitness;
(e)
the occupier shall submit to the Director General—
37
(i)
the risk-based data for the steam boiler and pressure vessel which is calculated and assessed in accordance with the methodology as determined by the Director General; and
(ii)
the information on the thickness of the steam boiler and pressure vessel which is collected in accordance with any of the following methods:
an inspection under section 27D of the Act and two periodical inspections of steam boiler and pressure vessel;
three periodical inspections of the steam boiler and pressure vessel;
the measurement of the thickness of the steam boiler and pressure vessel shall be done not less than three times while the steam boiler and pressure vessel are in operation at intervals of not less than twelve months after each measurement; or the measurement of the thickness of the steam boiler and pressure vessel shall be done not less than three times while the steam boiler and pressure vessel are not in operation at intervals of not less than twelve months after each measurement;
(f)
the measurement of the thickness of the steam boiler and pressure vessel under paragraph (e)(ii) shall be done in accordance with the method approved by Director General unless the measurement is done using a method that is generally accepted;
(g)
if the plant requiring certificate of fitness is a steam boiler and a pressure vessel, the occupier shall submit to the Director General the information on
38
the remnant life, risk category, inspection interval and inspection plan for the steam boiler and pressure vessel obtained through the calculation and assessment of data and information collected in accordance with paragraph (e);
(h)
if the plant requiring certificate of fitness is lifting machinery, the occupier shall submit to the Director General the information on the risk category, inspection interval and inspection plan for the lifting machinery;
(i)
the occupier shall ensure that there is no fatality, serious bodily injury, disease, occupational poisoning or dangerous occurrence resulting from the installation, repair, opening, operation and maintenance activities of the plant requiring certificate of fitness within two years before the date of application;
(j)
the occupier shall ensure that no incident that can affect the integrity of the plant requiring certificate of fitness occurs within two years before the date of application;
(k)
the occupier shall have one or more risk-based teams as determined by the Director General consisting of at least five members as follows:
(i)
a qualified person with an engineering degree as the team leader to perform all tasks relating to the inspection of the integrity of the plant requiring certificate of fitness;
(ii)
a qualified person with knowledge and expertise in corrosion engineering;
(iii)
a qualified person from the process department or production department;
39
(iv)
a qualified person from the inspection department or engineering department; and
(v)
a safety and health officer registered under the Occupational Safety and Health (Safety and Health Officer) Regulations 1997
[P.U. (A) 315/1997] or the person responsible for occupational safety and health if the place of work does not require such registered safety and health officer; and
(l)
the occupier shall submit the documents as specified in the
Second Schedule.
Additional information or documents 6.
(1)
The Director General may, by notice in writing at any time after an application for special scheme of inspection is received, requires the occupier to provide any additional information or document to the Director General within the period as specified in the notice or any extended period granted by the Director General.
(2)
If the additional information or document required under subregulation (1) is not provided by the occupier within the period as specified in the notice or any extended period granted by the Director General, the application shall be deemed to have been withdrawn without prejudice to the right of the occupier to make a fresh application.
Approval for special scheme of inspection 7.
(1)
The Director General may approve the application for a special scheme of inspection as either special scheme of inspection of class A or special scheme of inspection of class B, under regulation 3 if the Director General is satisfied that the requirements under regulation 4 or 5, as the case may be, have been fulfilled.
(2)
Subject to subregulation (1), the Director General may issue a certificate of approval for special scheme of inspection of class A or special scheme of inspection of
40
class B to the occupier which shall contain the particulars as specified in the Third Schedule.
(3)
An occupier whose special scheme of inspection is approved by the
Director General may only hold one class of special scheme of inspection at any one time.
(4)
An occupier who has obtained approval for special scheme of inspection of class B by the Director General shall not hold approval for any other special scheme of inspection of class B at the same time and any existing special scheme of inspection of class A obtained by the occupier is revoked.
Duration of special scheme of inspection 8.
(1)
A special scheme of inspection of class A shall be valid for a period of one hundred and twenty months from the date of approval of the application for the special scheme of inspection unless revoked or terminated earlier.
(2)
A special scheme of inspection of class B shall be valid for a period of one hundred and eighty months from the date of approval of the application for the special scheme of inspection unless revoked or terminated earlier.
Validity of certificate of fitness for plant requiring certificate of fitness under special scheme of inspection 9.
The validity of a certificate of fitness for a plant requiring certificate of fitness under a special scheme of inspection shall not exceed sixty months as determined by the officer based on the outcome of calculation and assessment of risk-based data submitted by the occupier.
PART III
DUTIES OF OCCUPIER
Duties of occupier under special scheme of inspection of class A
10.
An occupier with approval for a special scheme of inspection of class A shall—
41
(a)
ensure that no fatality, serious bodily injury, poisoning, disease or dangerous occurrence happens as a result of the installation or use of the plant requiring certificate of fitness;
(b)
ensure that risk-based data is collected by a risk-based team at intervals not exceeding twelve months after each collection of data;
(c)
keep and maintain risk-based data submitted by the risk-based team;
(d)
determine the remnant life, risk category, inspection interval and inspection plan for the steam boiler and pressure vessel based on the calculation and assessment of risk-based data;
(e)
maintain and apply the methodology for the calculation and assessment of risk-based data under subparagraph 4(d)(i);
(f)
notify the Director General in writing on any change of leader of risk-based team within thirty days from the date of the change;
(g)
maintain the occupational safety and health management system under paragraph 4(a);
(h)
keep and maintain a record of the usage and maintenance of the steam boiler and pressure vessel;
(i)
ensure verification inspection is performed; and
(j)
ensure that every member of the risk-based inspection team is always competent.
Duties of occupier under special scheme of inspection of class B
11.
An occupier with approval for a special scheme of inspection of class B shall—
42
(a)
ensure that no fatality, serious bodily injury, poisoning, disease or dangerous occurrence happens as a result of the installation or use of the plant requiring certificate of fitness;
(b)
ensure that risk-based data is collected by a risk-based team at intervals not exceeding twelve months after each collection of data;
(c)
keep and maintain risk-based data submitted by the risk-based team;
(d)
determine the remnant life, risk category, inspection interval and inspection plan for the steam boiler and pressure vessel based on the calculation and assessment of risk-based data;
(e)
maintain and apply the methodology for the calculation and assessment of risk-based data under subparagraph 5(e)(i);
(f)
notify the Director General in writing on any change of leader of risk-based team within thirty days from the date of the change;
(g)
ensure verification inspection is performed;
(h)
maintain the plant management system referred to in paragraph 5(a);
(i)
conduct risk-based analysis; and
(j)
ensure that every member of the risk-based inspection team is always competent.
43
PART IV
SPECIAL INSPECTION
Special inspection for plant requiring certificate of fitness 12.
(1)
An occupier shall apply to the officer for a special inspection for a plant requiring certificate of fitness together with the payment of fee as specified in the First Schedule.
(2)
The occupier shall ensure the plant requiring certificate of fitness is available for the special inspection.
(3)
A special inspection shall be conducted in the following manner—
(a)
for the first special inspection after approval of a special scheme of inspection, the plant requiring certificate of fitness shall be prepared for both internal inspection and external inspection;
(b)
for subsequent special inspections—
(i)
the steam boiler and pressure vessel under a special scheme of inspection of class A shall be prepared for both internal inspection and external inspection; and
(ii)
the plant requiring certificate of fitness under a special scheme of inspection of class B shall be prepared for an inspection during operation and an external inspection.
(4)
In the event that the occupier finds that an internal inspection is not suitable to be carried out, the occupier shall apply to the Director General for an inspection during operation.
(5)
The Director General may approve or reject the application of the occupier under subregulation (4).
44
(6)
If the Director General rejects the application of the occupier under subregulation (5), an internal inspection shall be carried out on the plant requiring certificate of fitness.
Addition, reduction and change of information to list of plant requiring certificate of fitness under special scheme of inspection 13.
If there is any addition, reduction or change of information to the list of plant requiring certificate of fitness under an approved special scheme of inspection of class B, the occupier shall submit an application to amend the list of plant requiring certificate of fitness of the approved special scheme of inspection for a period of not more than forty-eight months from the date of the additional, reduction or change of information together with the payment of fee as specified in the First Schedule.
Verification inspection 14.
(1)
An occupier who is granted approval for a special scheme of inspection shall be subject to a verification inspection.
(2)
An occupier who obtains a special scheme of inspection of class A shall apply for a verification inspection within six months after a special inspection is conducted together with the payment of fee as specified in the First Schedule.
(3)
An occupier who obtains a special scheme of inspection of class B shall apply for a verification inspection within a period of not more than six months before a special inspection is conducted together with the payment of fee as specified in the First Schedule.
PART V
REVOCATION AND TERMINATION OF SPECIAL SCHEME OF INSPECTION
Revocation of special scheme of inspection 15.
The Director General may revoke any approved special scheme of inspection if the occupier provides any document or information required under any provision of these Regulations that is false, misleading or contains material errors or omissions.
45
Termination of special scheme of inspection 16.
The Director General may terminate any approved special scheme of inspection if—
(a)
the occupier who obtains approval for a special scheme of inspection is found to have failed to comply with the duties specified in regulation 10
or 11, as the case may be;
(b)
there is change of occupier for plant requiring certificate of fitness under special scheme of inspection; or
(c)
the certificate of fitness for plant requiring certificate of fitness under the special scheme of inspection is terminated under subsection 27D(8);
Voluntary termination of special scheme of inspection 17.
(1)
The occupier shall notify the Director General in writing for the purpose of voluntary termination of any special scheme of inspection that has been approved for any or all plants requiring certificate of fitness.
(2)
A certificate of fitness for plant requiring certificate of fitness under any special scheme of inspection shall be revoked either on the expiry date of the certificate of fitness of the plant requiring certificate of fitness or on the last day of the sixth month after the date of voluntary termination of the special scheme of inspection, whichever is earlier.
PART VI
GENERAL
Changes in relation to plant requiring certificate of fitness under special scheme of inspection 18.
(1)
The occupier shall notify the Director General in writing within thirty days of any changes of the following:
46
(a)
the sale, lease or transfer of ownership of any plant requiring certificate of fitness under a special scheme of inspection to any person; or
(b)
the safe working pressure in respect of steam boiler and pressure vessel or safe working load in respect of lifting machinery under special scheme of inspection.
(2)
If any plant requiring certificate of fitness under any special scheme of inspection is sold, leased or the ownership is transferred on a permanent or temporary basis by an occupier who has obtained approval for a special scheme of inspection to any person, the plant requiring certificate of fitness shall be deemed to have been withdrawn from the special scheme of inspection.
Non-refundable fee 19.
Any fee paid under these Regulations shall not be refundable.
47
FIRST SCHEDULE
[Regulations 3 and 13 and subregulations 12(1), 14(2) and 14(3)]
FEES
(1)
(2)
Matter
(3)
Fees
Special scheme of class A
Special scheme of class B
1.
Application for approval for a special scheme of inspection:
(a)
for the first plant requiring certificate of fitness
(b)
for every subsequent plant requiring certificate of fitness
51,000
1,000
81,000
1,000
2.
Application for special inspection for steam boiler:
Category 1
Heating surface less than 5
square metres
Heating surface of 5 square metres and above but less than 10 square metres
(c)
Heating surface of 10 square metres and above but less than 25 square metres
Heating surface of 25 square metres and above but less than 50 square metres
(e)
Heating surface of 50 square metres and above but less than 100 square metres
300
800
1,050
1,300
1,600
300
800
1,050
1,300
1,600
48
(1)
(2)
Matter
(3)
Fees
Special scheme of class A
Special scheme of class B
(f)
Heating surface of 100 square metres and above but less than 250 square metres
Heating surface of 250 square metres and above
Category 2
Electric steam boiler, steam tube oven, steam tube hot plate, autoclaves or economiser
Category 3
Superheater
2,000
2,400
300
300 2,000
2,400
300
300 3.
Application for special inspection for pressure vessel
Capacity less than 0.1 cubic metres
Capacity of 0.1 cubic metres and above but less than 0.5 cubic metres
Capacity of 0.5 cubic metres and above but less than 5 cubic metres
Capacity of 5 cubic metres and above but less than 10 cubic metres
Capacity of 10 cubic metres and above but less than 15 cubic metres
Capacity of 15 cubic metres and above
140
200
300
400
550
700
140
200
300
400
550
700 4.
Application for special inspection for mobile crane
49
(1)
(2)
Matter
(3)
Fees
Special scheme of class A
Special scheme of class B
Safe working load less than 25,000
kilogrammes
Safe working load of 25,000
kilogrammes and above but less than 50,000 kilogrammes
Safe working load of 50,000
kilogrammes and above but less than 250,000 kilogrammes
Safe working load of 250,000
kilogrammes and above
-
-
-
-
550
700
850
1,000
5.
Application for special inspection for tower crane and quay crane
-
1,300 6.
Application for special inspection for other crane
Safe working load less than 3,000 kilogrammes
Safe working load of 3,000 kilogrammes and above but less than 5,000 kilogrammes
Safe working load of 5,000 kilogrammes and above but less than 10,000 kilogrammes
Safe working load of 10,000 kilogrammes and above but less than 20,000
kilogrammes
Safe working load of 20,000 kilogrammes and above
-
-
-
-
-
350
600
750
950
1,200 7.
Application for special inspection for hoist
50
(1)
(2)
Matter
(3)
Fees
Special scheme of class A
Special scheme of class B
Material hoist:
(a)
Safe working load less than 500 kilogrammes
(b)
Safe working load of 500
kilogrammes and above but less than 1,000 kilogrammes
(c)
Safe working load of 1,000
kilogrammes and above but less than 1,500 kilogrammes
(d)
Safe working load of 1,500 kilogrammes and above
Passenger hoist
-
-
-
-
-
350
600
750
1,000
1,000
8.
Special inspection for suspended access equipment
-
350 9.
Application for special inspection for launching gantry
-
2,000
10. Application for special inspection for funicular railway
-
2,000
11. Application for special inspection for aerial working platform
(1)
Power less than 15 kilowatt
(2)
Power of 15 kilowatt and above but less than 37 kilowatt
(3)
Power of 37 kilowatt and above but less than 75 kilowatt
-
-
-
350
600
750
51
(1)
(2)
Matter
(3)
Fees
Special scheme of class A
Special scheme of class B
(4)
Power of 75 kilowatt and above
-
950
12. Application for special inspection for lift
Travel distance less than 12 meter
Travel distance of 12 metres and above but less than 30 metres
Travel distance of 30 metres and above but less than 80 metres
Travel distance of 80 metres and above but less than 140 metres
Travel distance of 140 meters and above but less than 300 metres
Travel distance of 300 metres and above
-
-
-
-
-
-
650
750
1,300
1,500
1,700
1,900
13. Application for special inspection for escalator or walkalator
-
350
14. Application for special inspection for other lifting machinery
Power less than 15 kilowatt
Power of 15 kilowatt and above but less than 37 kilowatt
Power of 37 kilowatt and above but less than 75 kilowatt
Power of 75 kilowatt and above
-
-
-
-
350
600
750
950
15. Application for verification inspection
25,000 40,000
52
(1)
(2)
Matter
(3)
Fees
Special scheme of class A
Special scheme of class B
16. Application to amend the list of plant requiring certificate of fitness of an approved special scheme of inspection:
(a)
for any addition to the list of plant requiring certificate of fitness
(b)
for any reduction to the list of plant requiring certificate of fitness
(c)
for any change of information to the list of plant requiring certificate of fitness
-
-
-
1,000
for every plant requiring certificate of fitness
-
-
SECOND SCHEDULE
[Paragraphs 4(h) and 5(l)]
COMPLIANCE DECLARATION DOCUMENTS
1.
List of plant requiring certificate of fitness 2.
Remaining life of plant requiring certificate of fitness 3.
Risk categories for steam boiler, pressure vessel and lifting machinery 4.
Confirmation that plant requiring certificate of fitness is in satisfactory working condition or suitable for use
53
THIRD SCHEDULE
[Subregulation 7(2)]
DETAILS OF CERTIFICATE OF APPROVAL OF SPECIAL SCHEME OF INSPECTION
1.
Type of the approved special scheme of inspection 2.
Number of approved special scheme of inspection 3.
Name of the special scheme of inspection holder 4.
Address of the special scheme of inspection holder 5.
Place of operation plant requiring certificate of fitness under the special scheme of inspection 6.
List of plant requiring approved certificate of fitness under the special scheme of inspection 7.
Duration of special scheme of inspection 8.
Approval date of the special scheme of inspection
Made 15 January 2025
[KSM.PUU(S)600-1/2/9/8(11); PN(PU2)541/JLD.14]
SIM CHEE KEONG
Minister of Human Resources