Perintah Lembaga Pembangunan Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017 is Malaysia P.U. (A), cited as P.U. (A) 49 2017, currently marked in force and first recorded in 2017.

Front matterCover and publication detailsOpen

P.U. (A) 49

WARTA KERAJAAN PERSEKUTUAN

FEDERAL GOVERNMENT

GAZETTE

PERINTAH LEMBAGA PEMBANGUNAN INDUSTRI

PEMBINAAN MALAYSIA

(PINDAAN JADUAL KETIGA) 2017

LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN

MALAYSIA (AMENDMENT OF THIRD SCHEDULE)

ORDER 2017

DISIARKAN OLEH/

JABATAN PEGUAM NEGARA/

ATTORNEY GENERAL’S CHAMBERS

P.U. (A) 49 2

AKTA LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA 1994

PERINTAH LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA

(PINDAAN JADUAL KETIGA) 2017

Opening note

Preamble

  1. PADA menjalankan kuasa yang diberikan oleh subseksyen 33A(3) Akta Lembaga Pembangunan Industri Pembinaan Malaysia 1994 [Akta 520], Menteri membuat perintah yang berikut: Nama dan permulaan kuat kuasa

(1)

Perintah ini bolehlah dinamakan Perintah Lembaga Pembangunan

Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017.

(2)

Perintah ini mula berkuat kuasa pada 10 Februari 2017.

Pindaan Jadual Ketiga

Akta Lembaga Pembangunan Industri Pembinaan Malaysia 1994 [Akta 520]

dipinda dengan menggantikan Jadual Ketiga dengan Jadual yang berikut:

“JADUAL KETIGA

[Seksyen 2 dan subseksyen 33A(2)]

PEKERJA BINAAN MAHIR

Seksyen 1

Jurubagas dan jurucat 2.

Pakar penyaman udara dan pengudaraan mekanikal

Tukang perancah”.

Dibuat 8 Februari 2017

[KKR.PUU.110-1/5/3; PN(PU2)546/V]

DATO’ SRI HAJI FADILLAH BIN HAJI YUSOF

Menteri Kerja Raya

P.U. (A) 49 4

LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA ACT 1994

LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA

(AMENDMENT OF THIRD SCHEDULE) ORDER 2017

Opening note

Preamble

  1. IN exercise of the powers conferred by subsection 33A(3) of the Lembaga Pembangunan Industri Pembinaan Malaysia Act 1994 [Act 520], the Minister makes the following order: Citation and commencement 1.

(1)

This order may be cited as the Lembaga Pembangunan Industri

Pembinaan Malaysia (Amendment of Third Schedule) 2017.

(2)

This Order comes into operation on 10 February 2017.

Amendment of Third Schedule 2.

The Lembaga Pembangunan Industri Pembinaan Malaysia Act 1994 [Act 520]

is amended by substituting for the Third Schedule the following Schedule:

“THIRD SCHEDULE

[Section 2 and subsection 33A(2)]

SKILLED CONSTRUCTION WORKERS

Seksyen 1

Blaster and painter 2.

Air conditioning and mechanical ventilation specialist 3.

Drywall installer 4.

Ceiling installer 5.

Petrochemical fitter 6.

Roof truss installer 7.

Precast concrete installer 8.

Formwork system installer

P.U. (A) 49 5

Seksyen 9

Block system installer 10.

Bar bender 11.

Wireman 12.

Bricklayer 13.

Plant operator 14.

Crane operator 15.

Chargeman 16.

Cable jointer 17.

Slinger and rigger 18.

Painter 19.

Tiler 20.

Carpenter 21.

Welder 22.

Concretor 23.

Plasterer 24.

Plumber 25.

Scaffolder”.

Made 8 February 2017

[KKR.PUU.110-1/5/3; PN(PU2)546/V]

DATO’ SRI HAJI FADILLAH BIN HAJI YUSOF

Minister of Works

Common questions

What is Perintah Lembaga Pembangunan Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017?
Perintah Lembaga Pembangunan Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017 is Malaysia P.U. (A), cited as P.U. (A) 49 2017, currently marked in force and first recorded in 2017.
Is Perintah Lembaga Pembangunan Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017 still in force?
Yes — Perintah Lembaga Pembangunan Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017 is currently in force.
When did Perintah Lembaga Pembangunan Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017 take effect?
Perintah Lembaga Pembangunan Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017 was first recorded in 2017.
How many sections does Perintah Lembaga Pembangunan Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017 have?
Perintah Lembaga Pembangunan Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017 contains 28 sections.
Where can I read the official version of Perintah Lembaga Pembangunan Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017?
The official text of Perintah Lembaga Pembangunan Industri Pembinaan Malaysia (Pindaan Jadual Ketiga) 2017 is published at lom.agc.gov.my.