Section 13

of Sabah Renewable Energy Technical And Operational Requirements Rules 2024

Section 13

(2)

The distribution licensee shall ensure that the electrical protection schemes are properly co-ordinated for the reliable and safe operation of its electricity distribution network.

(3)

The feed-in approval holder shall install an electrical protection scheme of the type and design which ensures that a fault occurring within the renewable energy installation does not adversely affect any part of the electricity distribution network.

(4)

The distribution licensee shall install an electrical protection scheme of the type and design which ensures that a fault occurring within the electricity distribution network does not adversely affect any part of the renewable energy installation.

(5)

A distribution licensee and feed-in approval holder shall install an electrical protection scheme that contain protection devices which, on the detection of a fault or malfunction, isolate the faulty part of the installation to —

20

(a)

minimize equipment damage and safety hazards during such fault or malfunction; and

(b)

maintain the continuity of power supply to the functioning parts of the installation.