Section 16

(1)

A feed-in approval holder shall operate his or its renewable energy installation in accordance with prudent utility practices.

(2)

Without prejudice to the generality of subrule (1) —

(a)

a feed-in approval holder who owns a major renewable energy installation and a distribution licensee shall comply with the provisions of the Fourth

Schedule; and

(b)

a feed-in approval holder who owns a renewable energy installation having a net export capacity exceeding 2MW or rated kWp exceeding 2,000kWp shall, at his or its own cost, purchase, install and operate such interconnection facilities as may be required for the operation of his or its installation and delivery of renewable energy to the distribution licensee in accordance with prudent utility practices.

(3)

A person who fails to comply with subrule (1) commits an offence under these

Rules.