10. Adjudication response
Feedback & supportThe respondent shall, within ten working days from the receipt of the adjudication claim under subsection 9(1), serve a written adjudication response which shall answer the adjudication claim together with any supporting document on the claimant.
respondent
“respondent” means the person on whom the notice of adjudication and adjudication claim has been served;
The respondent shall provide the adjudicator with a copy of the adjudication response together with any supporting document within the time specified under subsection (1).
adjudicator
“adjudicator” means an individual appointed to adjudicate a dispute under this Act;
If the respondent fails to serve any adjudication response, the claimant may proceed with the adjudication after the expiry of the time specified under subsection (1).
claimant
“claimant” means an aggrieved party in a construction contract who initiates adjudication proceedings;