Construction Industry Payment and Adjudication Act 2012 · Updated to 22 Jun 2012 · Part II · Adjudication of Payment Disputes
15. Improperly procured adjudication decision
Feedback & supportAn aggrieved party may apply to the High Court to set aside an adjudication decision on one or more of the following grounds:
High Court
“High Court” means the High Court in Malaya or the High Court in Sabah and Sarawak, as the case may require;
the adjudication decision was improperly procured through fraud or bribery;
adjudication decision
“adjudication decision” means the decision made by an adjudicator under subsection 12(2);
there has been a denial of natural justice;
the adjudicator has not acted independently or impartially;
adjudicator
“adjudicator” means an individual appointed to adjudicate a dispute under this Act;
or
the adjudicator has acted in excess of his jurisdiction.
Construction Industry Payment and Adjudication 15
payment
“payment” means a payment for work done or services rendered under the express terms of a construction contract;