6. Payment response
Feedback & supportA non-paying party who admits to the payment claim served on him shall serve a payment response on the unpaid party together with the whole amount claimed or any amount as admitted by him.
non-paying party
“non-paying party” means a party against whom a payment claim is made pursuant to a construction contract;
A non-paying party who disputes the amount claimed in the payment claim, either wholly or partly, shall serve a payment response in writing on the unpaid party stating the amount disputed and the reason for the dispute.
payment
“payment” means a payment for work done or services rendered under the express terms of a construction contract;
A payment response issued under subsection (1) or (2)
shall be served on the unpaid party within ten working days of the receipt of the payment claim.
unpaid party
“unpaid party” means a party who claims payment of a sum which has not been paid in whole or in part under a construction contract;
A non-paying party who fails to respond to a payment claim in the manner provided under this section is deemed to have disputed the entire payment claim.