Section 10

(a)

only part of the installation has met or shall meet the applicable criteria as set out in column (2) of the First Schedule; and

(b)

has separate and dedicated interconnection cables and a separate and dedicated revenue meter in respect of renewable energy generated by the part of the installation referred to in paragraph (a), the eligible producer shall apply for a feed-in approval in respect of the installed capacity of the part of the installation referred to in paragraph (a) and a separate feed-in approval in respect of the installed capacity of the remaining part of such installation.

Required information for application for feed-in approval