Section 10
Application for bonus feed-in tariff rate
of Sabah Renewable Energy Feed Approval And Feed Tariff Rate Rules 2024
Where an eligible producer proposes to apply for any bonus feed-in tariff rate in respect of a renewable energy installation which —
(a)
only part of the installation has met or shall meet the applicable criteria as set out in column (2) of the First Schedule; and
(b)
has separate and dedicated interconnection cables and a separate and dedicated revenue meter in respect of renewable energy generated by the part of the installation referred to in paragraph (a), the eligible producer shall apply for a feed-in approval in respect of the installed capacity of the part of the installation referred to in paragraph (a) and a separate feed-in approval in respect of the installed capacity of the remaining part of such installation.