Section 10

Application for bonus feed-in tariff rate

of Sabah Renewable Energy Feed Approval And Feed Tariff Rate Rules 2024

State Subsidiary LegislationIn forceProvision 10 of 29
Section 10
(1)

Where an eligible producer proposes to apply for any bonus feed-in tariff rate in respect of a renewable energy installation which —

(a)

only part of the installation has met or shall meet the applicable criteria as set out in column (2) of the First Schedule; and

(b)

has separate and dedicated interconnection cables and a separate and dedicated revenue meter in respect of renewable energy generated by the part of the installation referred to in paragraph (a), the eligible producer shall apply for a feed-in approval in respect of the installed capacity of the part of the installation referred to in paragraph (a) and a separate feed-in approval in respect of the installed capacity of the remaining part of such installation.