Section 5

Change in particulars of application

of Sabah Renewable Energy Feed Approval And Feed Tariff Rate Rules 2024

State Subsidiary LegislationIn forceProvision 5 of 29
Section 5
(1)

Where after the eligible producer has submitted his or its application under rule 4 and before the Commission grants a feed-in approval and issues a certificate of feed-in approval, there is any change in any of the particulars in the application,

8

the eligible producer shall, as soon as possible, request in writing to the Commission to amend the relevant particulars in the application.

(2)

Upon receipt of the request under subrule (1), the Commission may approve or reject the request.

(3)

The processing fee as prescribed in the Second Schedule —

(a)

to be charged to the eligible producer whose request has been approved and shall be paid after receipt of a notice from the Commission; and

(b)

shall not be charged to the eligible producer when the change in particulars is due to any reasons attributable to the Commission.

(4)

The Commission shall, at any time, after approving the request and receiving the processing fee, amend the relevant particulars as specified in the request and notify the eligible producer of such amendment.

Application for feed-in approval for renewable energy installation utilizing only one type of renewable resource