Section 10
(a)
the distribution licensee and feed-in approval holder agree to such connection; and
(b)
such connection is found to be technically feasible pursuant to a power system study carried out under rule 4.
(2)
If a high voltage direct connection is agreed to be carried out under subrule
(1)
, the feed-in approval holder and distribution licensee shall comply with the provisions of the Third Schedule and all other applicable prudent utility practices.