Malaysia legislation

Section 10

of Sabah Renewable Energy Technical And Operational Requirements Rules 2024

Section 10

(a)

the distribution licensee and feed-in approval holder agree to such connection; and

(b)

such connection is found to be technically feasible pursuant to a power system study carried out under rule 4.

(2)

If a high voltage direct connection is agreed to be carried out under subrule

(1)

, the feed-in approval holder and distribution licensee shall comply with the provisions of the Third Schedule and all other applicable prudent utility practices.

Section 10 — Sabah Renewable Energy Technical And Operational Requirements Rules 2024