Section 9

Medium voltage direct connection

of Sabah Renewable Energy Technical And Operational Requirements Rules 2024

State Subsidiary LegislationIn forceProvision 9 of 26
Section 9
(1)

Subject to rule 10, a distribution licensee shall connect a medium voltage renewable energy installation to a connection point through a medium voltage direct connection, provided that such connection is found to be technically feasible pursuant to a connection confirmation check carried out under rule 3 or a power system study carried out under rule 4.

(2)

If a medium voltage direct connection is required to be carried out under subrule

(1)

, the relevant feed-in approval holder and distribution licensee shall comply with the provisions of the Third Schedule.